Brook Hollow Project Overview 2023-03-15
C-fe67965fc1 · Page 1 of 1 · DR-0001 · 2023-03-15
The claim, in the assessor's words
An existing 138 kV transmission line crosses the eastern portion of the Project Area.
An existing 138 kV transmission line crosses the eastern portion of the Project Area.
Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
Cited by EN-01 Land Use and Site Features, PE-03 Other · Filed under EN-01, PE-03
On the page
The page text exactly as the engine read it, with the quote marked.
Placed verbatim · The quote occurs on the page exactly as written.
Read as docx
The page
This document has no page picture (only PDF and image documents have one).
Other claims quoted on this page
The project covers approximately 1,050 acres of leased farmland.
Land cover is predominantly row crops (corn and soybeans).
Scattered woodlots occur along Sugar Run.