This is a fictional demonstration project in which every organisation, person, parcel and finding is invented.
Permits
?
The permit matrix, grouped by the level of each requirement, in the engine's order within each level.
Permits
26
Requirements
26
Engine 0.1.0, which made this run, wrote no timelines or citations of law.
Permits (26)
26 shown
Permit
Level
Legal authority
Applicability
Rows
Citations
Section 404 permit (Nationwide Permit, e.g. NWP 51, or Individual Permit) (Clean Water Act Section 404 (33 U.S.C. 1344); 33 CFR Parts 320-332)F-CWA404
Federal
U.S. Army Corps of Engineers (district by location)
Likely
1
Section 404 permit (Nationwide Permit, e.g. NWP 51, or Individual Permit) (Clean Water Act Section 404 (33 U.S.C. 1344); 33 CFR Parts 320-332)
F-CWA404
Legal authority
U.S. Army Corps of Engineers (district by location)
Applicability
Likely
Description
Regulates discharge of dredged or fill material into waters of the United States, including wetlands. Permit type depends on the area of impact and the activity.
Notes
Likely required. As of the cut-off: Sackett v. EPA narrowed the scope of waters of the United States. (2023-05-25) Changed after the cut-off (not applied): EPA and USACE published the conforming WOTUS rule. (2023-09-08)
Section 7 consultation (with a federal nexus) or Section 10 incidental take permit and habitat conservation plan (Endangered Species Act Sections 7 and 10 (16 U.S.C. 1536, 1539); 50 CFR Parts 17 and 402)F-ESA
Federal
U.S. Fish and Wildlife Service (NMFS for marine and anadromous species)
Conditional
1
Section 7 consultation (with a federal nexus) or Section 10 incidental take permit and habitat conservation plan (Endangered Species Act Sections 7 and 10 (16 U.S.C. 1536, 1539); 50 CFR Parts 17 and 402)
F-ESA
Legal authority
U.S. Fish and Wildlife Service (NMFS for marine and anadromous species)
Applicability
Conditional
Description
Federal actions must not jeopardize listed species or adversely modify critical habitat; without a federal nexus, take of listed species is prohibited unless authorized under Section 10.
Notes
Required only if triggered. Technical assistance and seasonal clearing restrictions usually suffice where impacts are avoided; formal consultation or an incidental take permit is needed if take cannot be avoided. As of the cut-off: Tricolored bat proposed for listing as endangered. (2022-09-14) Northern long-eared bat reclassification from threatened to endangered took effect. (2023-03-31) Changed after the cut-off (not applied): Monarch butterfly proposed for listing as threatened. (2024-12-12)
Eagle nest buffers; eagle incidental take permit if disturbance cannot be avoided (Bald and Golden Eagle Protection Act (16 U.S.C. 668-668d); 50 CFR Part 22)F-BGEPA
Federal
U.S. Fish and Wildlife Service
Conditional
1
Eagle nest buffers; eagle incidental take permit if disturbance cannot be avoided (Bald and Golden Eagle Protection Act (16 U.S.C. 668-668d); 50 CFR Part 22)
F-BGEPA
Legal authority
U.S. Fish and Wildlife Service
Applicability
Conditional
Description
Protects bald and golden eagles, their nests and eggs from take, including disturbance.
Notes
Required only if triggered. Only where eagle nests are near the site; follow buffer guidance. Changed after the cut-off (not applied): Revised eagle permit regulations (including general permits) took effect. (2024-04-12)
NEPA review (categorical exclusion, environmental assessment or EIS) (National Environmental Policy Act (42 U.S.C. 4321 et seq.))F-NEPA
Federal
Lead federal agency
Conditional
1
NEPA review (categorical exclusion, environmental assessment or EIS) (National Environmental Policy Act (42 U.S.C. 4321 et seq.))
F-NEPA
Legal authority
Lead federal agency
Applicability
Conditional
Description
Environmental review of major federal actions, such as federal land use, funding, loans or individual federal permits.
Notes
Required only if triggered. Only if federal land, funding or an individual federal permit is involved. As of the cut-off: Fiscal Responsibility Act amended NEPA. (2023-06-03) Changed after the cut-off (not applied): CEQ's NEPA implementing regulations were rescinded. (2025-04-11)
Form 7460-1 Notice of Proposed Construction or Alteration (14 CFR Part 77)F-FAA77
Federal
Federal Aviation Administration
Conditional
1
Form 7460-1 Notice of Proposed Construction or Alteration (14 CFR Part 77)
F-FAA77
Legal authority
Federal Aviation Administration
Applicability
Conditional
Description
Notice for construction that meets Part 77 notice criteria (for example structures over 200 feet, or within defined distances and slopes of public-use airports); glare analysis may be requested near airports.
Notes
Required only if triggered. Screen distances to public-use airports; file if notice criteria are met.
Spill Prevention, Control and Countermeasure (SPCC) Plan (Oil Pollution Prevention, 40 CFR Part 112)F-SPCC
Federal
U.S. Environmental Protection Agency
Conditional
1
Spill Prevention, Control and Countermeasure (SPCC) Plan (Oil Pollution Prevention, 40 CFR Part 112)
F-SPCC
Legal authority
U.S. Environmental Protection Agency
Applicability
Conditional
Description
Required where aggregate aboveground oil storage capacity exceeds 1,320 gallons (counting containers of 55 gallons or more, including oil-filled transformers) and a discharge could reach navigable waters.
Notes
Required only if triggered. Usually required for utility-scale substations; confirm once equipment oil volumes are known.
No state siting certificate for 120 MWac merchant solar (IURC CPCN not required) (Certificate of Public Convenience and Necessity / siting)S-01
State
Indiana Utility Regulatory Commission (IURC)
Conditional
1
No state siting certificate for 120 MWac merchant solar (IURC CPCN not required) (Certificate of Public Convenience and Necessity / siting)
S-01
Legal authority
Indiana Utility Regulatory Commission (IURC)
Applicability
Conditional
Description
Indiana has no state siting permit for private solar; siting is local. IURC jurisdiction applies only to regulated utilities (IC 8-1-8.5 CPCN for utility-owned generation or PPA approval) and would be triggered only if Prairie Electric owns or seeks approval for the project.
Notes
Required only if triggered. Trigger: Only if project is utility-owned or the utility seeks IURC approval of PPA/ownership Note: As of 2023-08-15 Indiana had no state solar siting permit; local control prevails (the 2023 legislative session considered but did not enact a state siting override for solar; IC 36-7-4-1109 on local wind/solar ordinances was later amended in 2024-2025 efforts). Check later changes. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
401 WQC and isolated wetland permit (Section 401 Water Quality Certification / State Isolated Wetland permit (IC 13-18-22))S-02
State
Indiana Department of Environmental Management (IDEM)
Likely
2
401 WQC and isolated wetland permit (Section 401 Water Quality Certification / State Isolated Wetland permit (IC 13-18-22))
S-02
Legal authority
Indiana Department of Environmental Management (IDEM)
Applicability
Likely
Description
Sugar Run and tributaries are likely jurisdictional waters, so a 401 WQC is required with any federal Section 404 permit. Isolated state-regulated wetlands and waters not covered federally need an IDEM isolated wetland permit if impacted.
Notes
Likely required. Note: As of 2023-08-15, after Sackett v. EPA (May 2023), federal jurisdiction narrowed, making state isolated wetland permitting more important. Indiana SEA 389 (2021) deregulated Class I and some Class II isolated wetlands.
Notice of Intent and Construction Stormwater Pollution Prevention Plan (Construction Stormwater General Permit (327 IAC 15-5, Rule 5))S-03
State
IDEM
Required
2
Notice of Intent and Construction Stormwater Pollution Prevention Plan (Construction Stormwater General Permit (327 IAC 15-5, Rule 5))
S-03
Legal authority
IDEM
Applicability
Required
Description
Land disturbance of one acre or more requires Rule 5 NOI submitted to IDEM, with the SWPPP reviewed by the county SWCD or MS4. This project disturbs well over one acre.
Notes
Required. Note: Rule 5 as of 2023-08-15. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
Construction in a Floodway permit (Flood Control Act permit (IC 14-28-1))S-04
State
Indiana Department of Natural Resources (DNR) Division of Water
Conditional
3
Construction in a Floodway permit (Flood Control Act permit (IC 14-28-1))
S-04
Legal authority
Indiana Department of Natural Resources (DNR) Division of Water
Applicability
Conditional
Description
Required for construction in a designated floodway of streams with drainage area of 1 square mile or more, e.g. Sugar Run crossings, collection lines, or fencing.
Notes
Required only if triggered. Trigger: Any work in a mapped floodway or on a stream with 1+ sq mi drainage area Note: As of 2023-08-15. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
Environmental review request for state endangered and threatened species (Natural Heritage Database review and state-listed species review (IC 14-31, 312 IAC 9))S-05
State
Indiana DNR Division of Fish & Wildlife / Nature Preserves; USFWS Bloomington field office
Likely
3
Environmental review request for state endangered and threatened species (Natural Heritage Database review and state-listed species review (IC 14-31, 312 IAC 9))
S-05
Legal authority
Indiana DNR Division of Fish & Wildlife / Nature Preserves; USFWS Bloomington field office
Applicability
Likely
Description
Request a DNR Environmental Review for state-listed species and natural heritage. Indiana bat and northern long-eared bat tree clearing windows are commonly recommended.
Notes
Likely required. Note: As of 2023-08-15. NLEB was reclassified as federally endangered effective March 2023. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
SHPO review; Section 106 consultation if a federal nexus exists; DNR Archaeology Plan/Permit for state-land or discovered human remains (IC 14-21-1 Historic Preservation and Archaeology Act, state permit)S-06
State
Indiana DNR Division of Historic Preservation and Archaeology (SHPO)
Conditional
3
SHPO review; Section 106 consultation if a federal nexus exists; DNR Archaeology Plan/Permit for state-land or discovered human remains (IC 14-21-1 Historic Preservation and Archaeology Act, state permit)
S-06
Legal authority
Indiana DNR Division of Historic Preservation and Archaeology (SHPO)
Applicability
Conditional
Description
No general state review for private land without a state or federal nexus, but SHPO consultation is triggered through federal permits. Inadvertent discovery of human remains or burials requires DNR notification under IC 14-21-1.
Notes
Required only if triggered. Trigger: Federal nexus (e.g. 404 permit) or discovery of burials/archaeological artifacts Note: As of 2023-08-15. Federal nexus is missing from the project facts. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
INDOT access and utility ROW permits and oversize/overweight load permits (Road/ROW permits, oversize/overweight haul permits)S-07
State
Indiana Department of Transportation (INDOT) and county highway department
Conditional
2
INDOT access and utility ROW permits and oversize/overweight load permits (Road/ROW permits, oversize/overweight haul permits)
S-07
Legal authority
Indiana Department of Transportation (INDOT) and county highway department
Applicability
Conditional
Description
Needed for state-highway driveway access, utility crossings of state ROW, and delivery of heavy equipment such as main power transformers.
Notes
Required only if triggered. Trigger: Access, crossings or hauling on state routes Note: As of 2023-08-15. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
Indiana DNR / county Drainage Board / County Surveyor
Applicability
Conditional
Description
Crossings or work near county regulated drains need Drainage Board approval. Agricultural tile disturbed by construction must be repaired.
Notes
Required only if triggered. Trigger: Work within regulated drain easements or disturbing drainage tile Note: As of 2023-08-15. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
Construction Design Release for certain structures (Indiana Design Release / electrical code)S-09
State
Indiana Department of Homeland Security (Fire Prevention and Building Safety Commission)
Conditional
2
Construction Design Release for certain structures (Indiana Design Release / electrical code)
S-09
Legal authority
Indiana Department of Homeland Security (Fire Prevention and Building Safety Commission)
Applicability
Conditional
Description
Applies to qualifying buildings such as O&M or substation control buildings. Not typically needed for solar arrays themselves.
Notes
Required only if triggered. Trigger: Construction of enclosed buildings of qualifying class Note: As of 2023-08-15. Unverified: proposed from regulatory knowledge, not evidenced in the data room.
Special exception for commercial solar energy system following public hearing (Fixture County Solar Ordinance; A-1 zoning; special exception)L-01
Local
Fixture County Board of Zoning Appeals
Required
3
Special exception for commercial solar energy system following public hearing (Fixture County Solar Ordinance; A-1 zoning; special exception)
L-01
Legal authority
Fixture County Board of Zoning Appeals
Applicability
Required
Description
Parcels are zoned A-1 Agricultural, where commercial solar is allowed only by special exception from the BZA following a public hearing. Local opposition has been voiced, so the hearing is a key risk.
Notes
Required. Note: Ordinance as shown in the data-room records dated 2023-04-02. Later amendments are not known.
Compliance with 250-foot setback from non-participating residences (Setback and screening standards)L-02
Local
Fixture County Solar Ordinance
Required
3
Compliance with 250-foot setback from non-participating residences (Setback and screening standards)
L-02
Legal authority
Fixture County Solar Ordinance
Applicability
Required
Description
The ordinance requires 250 ft from non-participating residences. Residents asked for 500 ft and screening along CR 400 N, which the BZA could impose as a condition of the special exception, but this request is not part of the ordinance.
Notes
Required. Note: Ordinance as of 2023-04-02. The 500 ft request is undated and non-binding.
Local road use agreement and moratorium check (to be confirmed) (Road use and maintenance agreement; local moratorium check)L-04
Local
Fixture County / township
To be confirmed
3
Local road use agreement and moratorium check (to be confirmed) (Road use and maintenance agreement; local moratorium check)
L-04
Legal authority
Fixture County / township
Applicability
To be confirmed
Description
The data room says nothing about road use agreements or moratoria. The township trustees took no action after the April 2023 meeting, and no moratorium is evidenced.
Notes
To be confirmed. Note: As of 2023-08-15 no moratorium is evidenced.