Non-RTE Species: desk report
One row of the risk matrix, EC-02 Non-RTE Species, in the Ecological Resources section: what the record holds on it.
A desk review of the record as it stood: not a field survey and not a modelled study.
- Information cut-off
- 2023-08-15
- Row in the matrix
- EC-02 Non-RTE Species
Downloads
This report as a Word file, and the engine's own files for the whole run.
- This reportbrook-hollow-solar-EC-02.docx · Word · 41 KB
- The engine's risk matrixRiskMatrix_Brook_Hollow_Solar.xlsx · Excel · 35 KB
- The engine's permit matrixPermittingMatrix_Brook_Hollow_Solar.docx · Word · 42 KB
1Finding
Impacts likely but may be easily resolved
- The rule
Code computed the rating from the assessor's inputs:
impact_likely=yes -> 2
Set by the rule
- Decision
- Released
- Evidence state
- INFERRED · reasoned from several records
The assessor's comments
Scattered woodlots occur along Sugar Run, and field delineation identified four wetlands totaling 6.2 acres and three streams, providing migratory bird habitat. No avian or eagle nest survey or wildlife agency correspondence is in the data room.
2What the record shows
The five inputs
Present: yes
Woodlots along Sugar Run (C-71ef7a1eed) and delineated forested/emergent wetlands and a perennial stream (C-473bc604fa, C-b2682b602a) provide suitable habitat for migratory birds and general wildlife. No bird or eagle survey is in the data room, so presence is based on habitat, not documented use.
Cites C-71ef7a1eed, C-473bc604fa, C-b2682b602a
Extent: unknown
Woodlots are described only as scattered along Sugar Run (C-71ef7a1eed); wetlands total 6.2 acres across a 1,356-acre area (C-473bc604fa). Habitat position relative to the buildable area is not documented, so extent cannot be set as core or peripheral.
Cites C-71ef7a1eed, C-473bc604fa
Avoidable: yes
Scattered woodlots and limited wetland acreage can typically be handled by clearing outside the nesting season and by siting around the Sugar Run corridor (C-71ef7a1eed, C-b2682b602a). This is a judgment; no eagle nest information is available.
Cites C-71ef7a1eed, C-b2682b602a
Pathway: standard
MBTA compliance is by avoidance (F-MBTA), through seasonal clearing restrictions. No eagle nests are documented, so an individual eagle permit is not indicated on current evidence (C-71ef7a1eed).
Cites C-71ef7a1eed
Impact likely: yes
A typical solar build involves grading, tree clearing and crossings of Sugar Run, which would likely disturb woodlot and stream-corridor habitat used by migratory birds (C-71ef7a1eed, C-b2682b602a). Impact is mainly timing.
Cites C-71ef7a1eed, C-b2682b602a
Supporting statements (3)
Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.
C-473bc604fa
Field delineation on April 10-14, 2023 identified four wetlands totaling 6.2 acres (palustrine emergent and forested) and three streams within the Project Area.
Quoted from page 2 identified four wetlands totaling 6.2 acres (palustrine emergent and palustrine forested) and three streams within the Project Area.
Wetland and Stream Delineation Report May2023 · DR-0005 · Page 2 · 2023-05-22
Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-71ef7a1eed
Scattered woodlots occur along Sugar Run.
Quoted from page 1 scattered woodlots along Sugar Run
Brook Hollow Project Overview 2023-03-15 · DR-0001 · Page 1 · 2023-03-15
Source developer_document · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100
C-b2682b602a
Sugar Run, a perennial stream, bisects the center of the Project Area from north to south.
Quoted from page 2 Sugar Run, a perennial stream, bisects the center of the Project Area from north to south.
Wetland and Stream Delineation Report May2023 · DR-0005 · Page 2 · 2023-05-22
Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
3Permits and requirements
The requirements tied to the rows of this report, by level.
Engine 0.1.0, which made this run, wrote no timelines or citations of law.
Federal (2)
Compliance through avoidance (no incidental take permit program)
F-MBTA · U.S. Fish and Wildlife Service
- Applicability
- Conditional
- Instrument
- Migratory Bird Treaty Act (16 U.S.C. 703-712); 50 CFR Parts 10 and 21
- Trigger
- Vegetation clearing or construction where migratory birds nest.
- Description
Prohibits take of migratory birds, nests and eggs. Managed by clearing vegetation outside the nesting season and avoiding active nests.
- Verification
- PACK_PENDING_QUALIFIED_REVIEW
- Source
- pack:federal
- In the permit matrix
- F-MBTA
Eagle nest buffers; eagle incidental take permit if disturbance cannot be avoided
F-BGEPA · U.S. Fish and Wildlife Service
- Applicability
- Conditional
- Instrument
- Bald and Golden Eagle Protection Act (16 U.S.C. 668-668d); 50 CFR Part 22
- Trigger
- Eagle nests or concentration areas near construction.
- Description
Protects bald and golden eagles, their nests and eggs from take, including disturbance.
- As of the cut-off
Changed after the cut-off (not applied): Revised eagle permit regulations (including general permits) took effect. (2024-04-12)
- Verification
- PACK_PENDING_QUALIFIED_REVIEW
- Source
- pack:federal
- In the permit matrix
- F-BGEPA
State (1)
Environmental review request for state endangered and threatened species
S-05 · Indiana DNR Division of Fish & Wildlife / Nature Preserves; USFWS Bloomington field office
- Applicability
- Likely
- Instrument
- Natural Heritage Database review and state-listed species review (IC 14-31, 312 IAC 9)
- Trigger
- Always for screening; tree clearing and stream work raise risk
- Description
Request a DNR Environmental Review for state-listed species and natural heritage. Indiana bat and northern long-eared bat tree clearing windows are commonly recommended.
- As of the cut-off
As of 2023-08-15. NLEB was reclassified as federally endangered effective March 2023.
- Verification
- MODEL_KNOWLEDGE_UNVERIFIED
- Source
- model:jurisdiction
- In the permit matrix
- S-05
4What is missing
The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.
Medium priority (2)
IR-c5e9053166 · Medium priority
Provide the eagle nest review or avian survey for the project area, or confirm none exists.
- Missing evidence
- Eagle nest review or avian survey
- Consequence
- Non-RTE Species is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
IR-8469920792 · Medium priority
Provide the wildlife agency correspondence for the project area, or confirm none exists.
- Missing evidence
- Wildlife agency correspondence
- Consequence
- Non-RTE Species is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
5Next steps and agencies
Next steps
- Site visit to confirm habitat and screen for eagle nests.
- Site around woodlots and Sugar Run; clear trees outside nesting season.
- Request USFWS/Indiana DNR review.
Agencies
- USFWS
- Indiana DNR
6Basis and limits
This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-15.
It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.
Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.
Documents quoted (2)
- Wetland and Stream Delineation Report May2023 · DR-0005 · 2023-05-22 · page 2
- Brook Hollow Project Overview 2023-03-15 · DR-0001 · 2023-03-15 · page 1
Versions and data hashes
As the engine and the exporter recorded them. Hashes are SHA-256.
- Information cut-off
- 2023-08-15
- Engine version
- 0.1.0
- Prompt version
- 2026-10-02.1
- Rows pack
- rows.json sha256 d1df27b21f79b09d
- Federal pack
- federal.json sha256 aa17c41356542d46
- State pack
- none
- Local pack
- Not written by this engine
- Data room manifest
- 6141b7dc1f8441489d39e4023d551e4c0021a37ce4f9ad157607d9096c58bfb5
- Audit chain
- valid (92 events)
- QA status
- PASS
- Rendered at
- 2026-10-01T21:09:12+00:00
- Run record (annex)
- a03418c2562baa8a57b7c256ce665acd2c20e92d06e365604d162e9029f8fdd6
- Exporter
- Prism/room/exporter 1.4.0
Prism desk report · engine 0.1.0 · prompts 2026-10-02.1 · information cut-off 2023-08-15