ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477)

C-07bc294f85 · Page 1 of 2 · DR-0011 · 2023-05-02

The claim, in the assessor's words

The Division recommends cutting trees only October 1 through March 31, with a presence or absence survey first if summer clearing is needed.

Quoted from page 1
The Division recommends that trees be cut only from October 1 through March 31.

Source agency_determination · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

Cited by EC-01 Threatened and Endangered Species · Filed under EC-01

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

Ohio Department of Natural Resources Office of Real Estate - Environmental Review | Columbus, Ohio May 2, 2023 Linnea Barrow, Corvane Environmental, Inc., Wooster, Ohio Re: ODNR 23-0477, Tamsin Ridge Solar and Storage Project, Harrison Township, Carroll County The Ohio Department of Natural Resources (ODNR) has reviewed the project information you submitted on behalf of Northfold Energy Partners, LLC. These comments are made under ODNR's authorities and are offered for the project's application to the Ohio Power Siting Board. Division of Wildlife State-listed species. The project is within the range of the Indiana bat, the northern long-eared bat, the little brown bat and the tricolored bat, all state endangered. Trees with loose bark, cavities or cracks are potential summer roost habitat. Quote starts. The Division recommends that trees be cut only from October 1 through March 31. Quote ends. If clearing must happen in summer, a presence or absence survey is recommended first. A search of the Division's records of state-listed animals and plants found no records within one mile of the project boundary. Aquatic resources. Sallow Creek supports a diverse fish assemblage. No in-water work is recommended from April 15 to June 30. The Division recommends HDD for collection crossings of Sallow Creek and avoidance of the Category 3 wetland with a 300-foot buffer. Solar facilities. The Division recommends wildlife-permeable fencing with openings at ground level, native pollinator-friendly seed mixes under and around the arrays, and mowing outside the grassland bird nesting season (April 15 to July 31). Division of Mineral Resources Management Division records show abandoned underground coal mining, the Elsby No. 2 Mine in the Upper Freeport (No. 7) coal, beneath the eastern part of the project area, and surface mining reclaimed under the pre-1977 program. Mine subsidence is possible over abandoned underground workings. Division records also show two plugged and abandoned oil and gas wells within the project area and an active horizontal Utica well pad adjoining it. Locate all wells before design. Division of Water Resources Carroll County participates in the National Flood Insurance Program. Contact the county floodplain administrator about development in the mapped floodplain of Sallow Creek. Stormwater basins with embankments may need a dam permit if they exceed the statutory size thresholds. (Continued on page 2.) Ohio Department of Natural Resources - Office of Real Estate Page 1 of 2

The page

The outline marks where the quote begins on the page.

Page 1 of ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477)

Other claims quoted on this page

  • C-834477b4bd

    The project is within the range of four state-endangered bat species: Indiana, northern long-eared, little brown and tricolored.

  • C-2a17c48d5e

    A search of Division records found no state-listed animal or plant records within one mile of the project boundary.

  • C-ee75dcde7f

    Sallow Creek supports a diverse fish assemblage, and no in-water work is recommended April 15 to June 30.

  • C-c98dca4336

    The Division recommends HDD for collection crossings of Sallow Creek and avoiding the Category 3 wetland with a 300-foot buffer.

  • C-557a6ccbbf

    The Division recommends wildlife-permeable fencing, native pollinator-friendly seed mixes, and mowing outside the grassland bird nesting season (April 15 to July 31).

  • C-d9db0a1832

    Records show abandoned underground Elsby No. 2 Mine beneath the eastern part of the project area, plus pre-1977 reclaimed surface mining.

  • C-caad69ed74

    Mine subsidence is possible over abandoned underground workings.

  • C-a3cebd779c

    Two plugged and abandoned oil and gas wells are within the project area, and an active horizontal Utica well pad adjoins it.

  • C-21574b55b6

    Carroll County participates in the NFIP; a mapped floodplain of Sallow Creek exists, and the county floodplain administrator should be contacted.

  • C-41d7bff0bb

    Stormwater basins with embankments may need a dam permit if they exceed statutory size thresholds.