Generation Interconnection Feasibility Study Report - Queue Position AH1-931

C-9696e61ce3 · Page 1 of 2 · DR-0021 · 2022-04-14

The claim, in the assessor's words

Total network upgrades allocated to AH1-931 are estimated at $31.4 million.

Quoted from page 1
Total network upgrades $31.4 million

Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by PE-04 Interconnection and Transmission · Filed under PE-04

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

PJM Interconnection Interconnection Planning Generation Interconnection Feasibility Study Report Queue position AH1-931, "Tamsin Ridge 138 kV". April 14, 2022. 1. Introduction This report presents the results of the feasibility study for queue position AH1-931, submitted by Tamsin Ridge Solar, LLC (the Interconnection Customer) on September 24, 2021. The study assesses the impact of the proposed generating facility on the PJM transmission system and gives a preliminary estimate of the cost of the facilities needed to interconnect it. 2. Project description Item Value Location Harrison Township, Carroll County, Ohio Fuel Solar with battery storage Maximum facility output (MFO) 120 MW Capacity interconnection rights requested 72 MW Point of interconnection Proposed Tamsin Ridge 138 kV switching station (new three-breaker ring bus) on the Transmission Owner's Vesper Hill-Ardley 138 kV line Requested in-service date December 2026 3. Summary of results The study found reliability violations under the generator deliverability and multiple facility contingency tests that require network upgrades. Preliminary costs allocated to AH1-931: Facility Description Estimated cost Attachment facilities Gen-tie termination, revenue metering, relaying $1.2 million Direct connection New 138 kV ring bus switching station and line tap $7.4 million Network upgrade NU-1 Reconductor 9.6 miles of the Ardley-Pine Fork 138 kV line $24.8 million Network upgrade NU-2 Replace two 138 kV circuit breakers at Vesper Hill $1.9 million Network upgrade NU-3 (share) Ardley 345/138 kV transformer replacement, allocated share $4.7 million Quote starts. Total network upgrades $31.4 million Quote ends. PJM Interconnection - Interconnection Planning Page 1 of 2

The page

The outline marks where the quote begins on the page.

Page 1 of Generation Interconnection Feasibility Study Report - Queue Position AH1-931

Other claims quoted on this page

  • C-edf1371b18

    Queue position is AH1-931.

  • C-4a00292b36

    Proposed point of interconnection is a new Tamsin Ridge 138 kV switching station on the Vesper Hill-Ardley 138 kV line.

  • C-ddff0b0f72

    Requested in-service date is December 2026.

  • C-fa0fe91ee0

    Feasibility study found reliability violations under deliverability and multiple facility contingency tests requiring network upgrades.