PE-04 · Matrix · Additional Permitting

Rating
3Resource is present, likely difficult to address
Why
Core of the site; partly avoidable
Worst case
Not above the rating
Evidence
Reported
Cited claims
12
Requirements
0
Requests
2

Rating

3Resource is present, likely difficult to address

The engine shows this rating as 3

The rule

Code computed the rating from the assessor's inputs:

extent=core, avoidable=partly -> 3

Set by the rule

Decision
Released
Evidence state
Reported · desktop, consultant or developer record

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

Restudy raises upgrade costs toward the top of the plus or minus 50% band, affected-system impacts appear, and the 36 to 42 month build leaves no workable route to the December 2026 COD.

Step still pending
System Impact and Facilities Studies under PJM's reformed process
Inputs in the worst case
Extent core · Avoidable no · Pathway standard · Impact likely yes
The rule on the worst case
worst case (extent=core, avoidable=no -> 3) not above the point

Revision

First verdict
weakened
First critique

Core and partly are reasonable, but OPSB is unsupported on this row, the $31.4M is called 'allocated' when the quote says total, and the December 2026 schedule risk is understated given that no studies or agreement are in place. Some status statements are unsupported.

Revised once after the first critique. Rating unchanged.

The five inputs

Comments

PJM queue AH1-931 has a feasibility study (April 14, 2022) listing total network upgrades of $31.4 million (plus or minus 50%); the project's share is not stated. Transmission Owner estimates 36 to 42 months after agreement execution, which may constrain the December 2026 date. No agreement in the data room; next study phase not started.

Critique

Verdict
upheld
Suggested direction for the rating
same
Summary

Assessment is largely supported by the cited quotes. Core extent and partly avoidable are defensible. Minor issues: schedule risk is understated as 'may constrain', a few inferences (restudy, funding unresolved) are not quoted, and the FERC and Ohio gen-tie review next steps are missing.

Critic model
Luminol

Issues

  1. Severity minor · Kind understatement

    Comments and avoidable rationale say the December 2026 date 'may constrain' or 'looks difficult'. The cited quotes show 36-42 months from agreement execution. As of 2023-08-01 no agreement exists and the next study phase has not started. So even immediate execution would not clearly meet December 2026, and the date is very likely unachievable. Wording should be firmer. The category is unchanged.

    Cites C-cdf3d7697c, C-ddff0b0f72, C-502eff95b5

  2. Severity minor · Kind unsupported_statement

    'Funding and schedule of required upgrades are unresolved' and 'restudy in the reformed process' are inferences. The quotes say only that the next study phase has not started and the position is moving to the reformed process. No quote says restudy will occur or that funding is unresolved.

    Cites C-502eff95b5, C-9696e61ce3

  3. Severity minor · Kind missing_next_step

    Agencies list omits FERC, whose tariff governs PJM. The gen-tie route may need state review (Ohio Power Siting Board) if it is not covered by the PE-02 certificate. A next step should confirm whether the 0.4-mile 138 kV gen-tie sits inside the PE-02 siting application. Also request an updated study or PJM transition schedule, since the feasibility study is over a year old.

    Cites C-a21ca05339, C-502eff95b5

Checks

  • Passed

    rating_has_evidence · blocking

  • Passed

    presence_is_evidenced · not blocking

  • Passed

    counter_evidence_considered · not blocking

  • Passed

    numbers_grounded · not blocking

  • Passed

    agencies_grounded · not blocking

  • Passed

    cutoff_respected · blocking

  • Passed

    critic_not_refuted · blocking

Evidence (12)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

Arrow keys move the selection. A middle-click opens the claim's own page.

  1. Interconnection is in PJM.Tamsin Ridge Solar and Storage Project - Project Description · Page 1Exact
  2. Proposed point of interconnection is a new Tamsin Ridge 138 kV switching station on the Vesper Hill-Ardley 138 kV line.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 1Exact
  3. The position is in PJM's transition to its reformed process and the next study phase has not started.Tamsin Ridge Solar and Storage Project - Project Description · Page 1Exact
  4. Total network upgrades allocated to AH1-931 are estimated at $31.4 million.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 1Exact
  5. Feasibility study is complete; System Impact Study, Facilities Study and Interconnection Service Agreement follow.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 2Exact
  6. Interconnection voltage is 138 kV via a 0.4-mile gen-tie.Tamsin Ridge Solar and Storage Project - Project Description · Page 1Exact
  7. No short circuit violations were found and no affected system impacts were identified at this stage.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 2Exact
  8. Cost estimates are planning-level with accuracy of about plus or minus 50 percent and may change.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 2Exact
  9. Transmission Owner estimates 36 to 42 months after interconnection agreement execution to complete upgrades, which may constrain the requested in-service date.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 2Exact
  10. Requested in-service date is December 2026.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 1Exact
  11. Queue position is AH1-931.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 1Exact
  12. Feasibility study found reliability violations under deliverability and multiple facility contingency tests requiring network upgrades.Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · Page 1Exact

Tamsin Ridge Solar and Storage Project - Project Description

C-387e001e3f · Page 1 of 1 · DR-0001

Open the claim, C-387e001e3f

Interconnection is in PJM.

Quote check Exact · Placed verbatim · The quote occurs on the page exactly as written. · Read as docx

Northfold Energy Partners, LLC - Confidential Tamsin Ridge Solar and Storage Project Project Description, Revision 3. Prepared by Northfold Energy Partners, LLC. June 12, 2023. 1. Overview The Tamsin Ridge Solar and Storage Project (the Project) is a proposed 120 MW (AC) solar photovoltaic generating facility of approximately 168 MW (DC) with a co-located 60 MW / 240 MWh battery energy storage system (BESS). Northfold Energy Partners, LLC is developing the Project through its project company, Tamsin Ridge Solar, LLC. The Project is in Harrison Township, Carroll County, Ohio, west of State Route 43 and about 4 miles northwest of the Village of Carrollton. 2. Site The Project Area covers approximately 1,140 acres on 14 parcels held by 9 landowners. The fenced area is approximately 780 acres, in a West Block and an East Block separated by the Sallow Creek valley. Land cover is cropland and hay with woodlots along Sallow Creek and on reclaimed surface-mined ground in the East Block. An existing 138 kV transmission line crosses the West Block, and natural gas gathering pipelines cross Parcels 5, 7 and 10. There are 23 residences within 1,000 feet of the fence. 3. Facility Single-axis trackers; 40 central inverters of 3.0 MW each; a 34.5/138 kV project substation and the BESS yard (about 6 acres, 60 lithium iron phosphate enclosures) on Parcel 5; underground 34.5 kV collection lines; about 9 miles of gravel access roads; perimeter fencing; and an operations building. Modules carry a hail impact rating and the trackers have an automatic hail stow mode. Structures are designed for an ASCE 7-16 basic wind speed of 115 mph and a 20 psf ground snow load. 4. Interconnection Quote starts. PJM queue position AH1-931; the interconnection request was submitted on September 24, 2021. Quote ends. The point of interconnection is the proposed Tamsin Ridge 138 kV switching station on the Transmission Owner's Vesper Hill-Ardley 138 kV line, reached by a 0.4-mile 138 kV gen-tie line. PJM issued the Feasibility Study report on April 14, 2022. The position is now in PJM's transition to its reformed interconnection process, and the next study phase has not started. 5. Permitting and schedule The Project needs a certificate of environmental compatibility and public need from the Ohio Power Siting Board (OPSB). The pre-application conference with OPSB staff was held on March 21, 2023, and the county public meeting required by ORC 303.61 was held on May 11, 2023. The OPSB application is planned for the third quarter of 2023, construction from the first quarter of 2025, and commercial operation in December 2026. No federal land, federal funding or federal loan program is involved. A U.S. Army Corps of Engineers nationwide permit is expected for one access road crossing of an ephemeral stream. 6. Site control Option-to-lease agreements cover 12 parcels, a recorded collection line easement covers Parcel 7, and Parcel 11 is not yet under agreement (see the Option and Lease Summary and the Parcel Schedule).

This document has no page picture (only PDF and image documents have one).

  1. C-387e001e3f

    Interconnection is in PJM.

    Quoted from page 1
    PJM queue position AH1-931; the interconnection request was submitted on September 24, 2021.

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  2. C-4a00292b36

    Proposed point of interconnection is a new Tamsin Ridge 138 kV switching station on the Vesper Hill-Ardley 138 kV line.

    Quoted from page 1
    Proposed Tamsin Ridge 138 kV switching station (new three-breaker ring bus)

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  3. C-502eff95b5

    The position is in PJM's transition to its reformed process and the next study phase has not started.

    Quoted from page 1
    The position is now in PJM's transition to its reformed interconnection process, and the next study phase has not started.

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type data_gap · Polarity presence · Confidence high · Quote check exact, 100 of 100

  4. C-9696e61ce3

    Total network upgrades allocated to AH1-931 are estimated at $31.4 million.

    Quoted from page 1
    Total network upgrades $31.4 million

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100

  5. C-9bf4e1b156

    Feasibility study is complete; System Impact Study, Facilities Study and Interconnection Service Agreement follow.

    Quoted from page 2
    will be followed by a Facilities Study and an Interconnection Service Agreement.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

  6. C-a21ca05339

    Interconnection voltage is 138 kV via a 0.4-mile gen-tie.

    Quoted from page 1
    reached by a 0.4-mile 138 kV gen-tie line

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  7. C-ab3abd8d5e

    No short circuit violations were found and no affected system impacts were identified at this stage.

    Quoted from page 2
    No short circuit violations were found. No affected system impacts were identified at this stage.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

  8. C-bbdfdec1fc

    Cost estimates are planning-level with accuracy of about plus or minus 50 percent and may change.

    Quoted from page 2
    The costs above are planning-level estimates with an accuracy of about plus or minus 50 percent.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100

  9. C-cdf3d7697c

    Transmission Owner estimates 36 to 42 months after interconnection agreement execution to complete upgrades, which may constrain the requested in-service date.

    Quoted from page 2
    The Transmission Owner estimates 36 to 42 months from execution of an interconnection agreement to complete the switching station and the network upgrades

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type schedule · Polarity presence · Confidence high · Quote check exact, 100 of 100

  10. C-ddff0b0f72

    Requested in-service date is December 2026.

    Quoted from page 1
    Requested in-service date December 2026

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

  11. C-edf1371b18

    Queue position is AH1-931.

    Quoted from page 1
    Queue position AH1-931, "Tamsin Ridge 138 kV".

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  12. C-fa0fe91ee0

    Feasibility study found reliability violations under deliverability and multiple facility contingency tests requiring network upgrades.

    Quoted from page 1
    The study found reliability violations under the generator deliverability and multiple facility contingency tests that require network upgrades.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

Requirements and permits

The requirements the assessor tied to this row, by level. Each quote from dated law is shown with its source.

No requirement is tied to this row.

Information requests

  • IR-b24dc38cf1 · High priority

    Provide the executed or draft interconnection agreement for the project area, or confirm none exists.

    Missing evidence
    Executed or draft interconnection agreement
    Consequence
    Interconnection and Transmission is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-78fe2a615a · High priority

    Provide the gen-tie route study, line siting application or route map for the project area, or confirm none exists.

    Missing evidence
    Gen-tie route study, line siting application or route map
    Consequence
    Interconnection and Transmission is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

Next steps

  • Obtain PJM status letter on transition timing and the project's share of upgrade costs.
  • Re-baseline COD against the 36 to 42 month build time and the plus or minus 50% estimate.
  • Confirm deposits are current and obtain the gen-tie route and permit needs.

Agencies

  • PJM
  • Transmission Owner

Cost and impact

Impact
C, S
Potential cost level
M-H
Why

Network upgrades totalling $31.4M at plus or minus 50%, with the project's share not stated, plus the project's own interconnection facilities and gen-tie (no figure in the record). Schedule exposure against the December 2026 COD.

Impact: C = cost, S = schedule. Potential cost level: L, L-M, M, M-H, H (relative to a utility-scale solar budget).