Phase I Environmental Site Assessment - Tamsin Ridge Solar and Storage Project
C-b2025b56f8 · Page 1 of 3 · DR-0012 · 2023-01-27
The claim, in the assessor's words
Dark staining and stressed vegetation cover about 60 by 90 feet down-slope of the former tank battery on Parcel 5.
Dark staining and stressed vegetation cover an area of about 60 by 90 feet down-slope of the former brine and crude oil tank battery
Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
Cited by EN-04 Environmental Contamination · Filed under EN-04
On the page
The page text exactly as the engine read it, with the quote marked.
Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own.
Read as native
The page
The outline marks where the quote begins on the page.

Other claims quoted on this page
The Project Area is approximately 1,265 acres of cropland, hay, woodlots and reclaimed mine land, with four farmsteads.
REC 1: a release of brine and petroleum to soil is suspected at the former tank battery site on Parcel 5, with no release report found.
No HREC or CREC was identified; a 2016 brine spill was cleaned up under ODNR oversight and closed as de minimis.
Two plugged and abandoned oil and gas wells are listed in ODNR records on Parcels 4 and 10.
A natural gas gathering pipeline crosses Parcels 5, 7 and 10.
A farm debris pile with empty pesticide containers and scrap metal at the Strohl farmstead, Parcel 3, is a de minimis condition.
A limited Phase II with soil and shallow groundwater sampling is recommended at the Parcel 5 former tank battery before the substation and BESS yard are sited there.
Removal of the debris pile and pesticide containers on Parcel 3 is recommended before construction.
Plugged wells should be surveyed and fenced, keeping setbacks required by the operator and ODNR.