Generation Interconnection Feasibility Study Report - Queue Position AH1-931

C-bbdfdec1fc · Page 2 of 2 · DR-0021 · 2022-04-14

The claim, in the assessor's words

Cost estimates are planning-level with accuracy of about plus or minus 50 percent and may change.

Quoted from page 2
The costs above are planning-level estimates with an accuracy of about plus or minus 50 percent.

Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by PE-04 Interconnection and Transmission · Filed under PE-04

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

PJM Generation Interconnection Feasibility Study Report - AH1-931 4. Analysis Summer peak load flow, light load and short circuit analyses were performed on the PJM 2026 base case with all earlier-queued projects modeled. The overload of the Ardley-Pine Fork 138 kV line (up to 118 percent of its emergency rating) is driven by AH1-931 together with three other AH1 positions; AH1-931's share of the reconductoring cost reflects its distribution factor. No short circuit violations were found. No affected system impacts were identified at this stage. 5. Cost allocation and next steps Quote starts. The costs above are planning-level estimates with an accuracy of about plus or minus 50 percent. Quote ends. Network upgrade costs may change as earlier-queued projects withdraw or as later studies refine the cases. To remain in the queue, the Interconnection Customer must execute the System Impact Study agreement and pay the study deposit. The System Impact Study will confirm the upgrades, the capacity interconnection rights and the cost allocation, and will be followed by a Facilities Study and an Interconnection Service Agreement. The Transmission Owner estimates 36 to 42 months from execution of an interconnection agreement to complete the switching station and the network upgrades, which may constrain the requested in-service date. 6. Interconnection Customer requirements The Interconnection Customer is responsible for the project substation, the 138 kV gen-tie to the switching station, protection and control compatible with the Transmission Owner's standards, telemetry to PJM, and meeting the ride-through and reactive power requirements of the PJM tariff. PJM Interconnection, Interconnection Planning. This report is based on information provided by the Interconnection Customer and the Transmission Owner and is subject to revision. PJM Interconnection - Interconnection Planning Page 2 of 2

The page

The outline marks where the quote begins on the page.

Page 2 of Generation Interconnection Feasibility Study Report - Queue Position AH1-931

Other claims quoted on this page

  • C-ab3abd8d5e

    No short circuit violations were found and no affected system impacts were identified at this stage.

  • C-9bf4e1b156

    Feasibility study is complete; System Impact Study, Facilities Study and Interconnection Service Agreement follow.

  • C-cdf3d7697c

    Transmission Owner estimates 36 to 42 months after interconnection agreement execution to complete upgrades, which may constrain the requested in-service date.