Tamsin Ridge Solar and Storage
This is a fictional demonstration project in which every organisation, person, parcel and finding is invented.
OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project
C-ef25cbb708 · Page 1 of 2 · DR-0026 · 2023-03-28
The claim, in the assessor's words
Staff highlighted a preconstruction background noise study with day and night data and predicted operating noise at every residence within one mile.
A preconstruction background noise study with day and night data, and predicted operating noise at every
Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100
Cited by CO-03 Noise · Filed under CO-03
On the page
The page text exactly as the engine read it, with the quote marked.
Placed verbatim · The quote occurs on the page exactly as written.
Read as native
The page
The outline marks where the quote begins on the page.

Other claims quoted on this page
OPSB staff agreed the project is a major utility facility needing an OPSB certificate before construction under the standard process.
Staff will treat the battery system as part of the generating facility.
SB 52 Section 4 queue exemption appears unavailable because no PJM system impact study was complete for AH1-931 as of October 11, 2021.
Applicant must hold a public meeting in Carroll County 90 to 300 days before filing the application (ORC 303.61).
Within 90 days after the county public meeting, the Board of County Commissioners may adopt a resolution prohibiting the facility or limiting its boundaries (ORC 303.62).
Two ad hoc members, for county commissioners and township trustees, will sit on the Board for this case.
Decommissioning plan and performance bond requirements of ORC 4906.21 to 4906.222 apply.
A resolution designating restricted areas under ORC 303.58 would bar an application for a facility within them.
Counsel's search found no ORC 303.58 restricted-area resolution for Harrison Township on the conference date.
Staff expects ecological surveys coordinated with ODNR and USFWS, wetland delineation before filing, and ODNR buffers for Category 3 wetlands.
Cultural resources surveys to SHPO standards must be submitted to the SHPO.
Staff expects a fire protection, safety and medical emergency plan prepared with local responders, including the battery system.
Staff expects mapping of agricultural district land and a drain tile repair plan.
A geotechnical report must address an abandoned underground mine in the East Block.