Skip to content

CO-03 · Matrix · Community Resources

Rating
2Impacts likely but may be easily resolved
Why
Impact likely
Worst case
Not above the rating
Evidence
Reported
Cited claims
15
Requirements
1
Requests
3

Rating

2Impacts likely but may be easily resolved

The engine shows this rating as 2

The rule

Code computed the rating from the assessor's inputs:

impact_likely=yes -> 2

Set by the rule

Decision
Released
Evidence state
Reported · desktop, consultant or developer record

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

Selected mitigation only partly closes the R-6 and R-7 exceedances, so OPSB staff or Linnet Road neighbors press for further BESS cooling or transformer changes or relocation of the BESS yard, adding cost and review time.

Step still pending
Mitigation selection and modeling for R-6 and R-7, and OPSB staff review of the noise information
Inputs in the worst case
Extent peripheral · Avoidable partly · Pathway standard · Impact likely yes
The rule on the worst case
worst case (impact_likely=yes -> 2) not above the point

Revision

First verdict
weakened
First critique

Category 2 is reasonable. However, the claim that the design goal is proposed as a certificate condition is unsupported by its cited quote. The R-7 2 dBA figure is not in the quotes. The worst case's 'contested exception' is inconsistent with there being no numeric limit.

Revised once after the first critique. Rating unchanged.

The five inputs

Comments

Noise assessment predicts operating sound above its design goal at two non-participating homes (R-6 by 3 dBA, 44 against 41 dBA), with a possible 120 Hz transformer tone at R-7. Pile driving would reach about 80 to 87 dBA at R-2, 260 feet away. No numeric solar limit applies; mitigation not yet selected.

Critique

Verdict
upheld
Suggested direction for the rating
same
Summary

The assessment is mostly well supported. The inputs and the OPSB pathway follow the evidence. The minor problems are an unsupported attribution to battery cooling, R-7 treated as an exceedance, 'committed' overstating a recommendation, and unsupported vibration monitoring. The category stays the same.

Critic model
Luminol

Issues

  1. Severity minor · Kind unsupported_statement

    The assessment says the R-6 night level is 'attributed to battery cooling equipment'. No cited quote says that. C-597c5c8469 only places R-6 610 feet from the BESS yard. A quote linking the exceedance to the cooling equipment would settle it.

    Cites C-a188dcc65e, C-597c5c8469

  2. Severity minor · Kind unsupported_statement

    The quote for the second exceedance is truncated. The assessment names R-7 as that second residence, but C-a559672e76 only says a transformer tone 'may' be audible at R-7. R-7 is not shown as exceeding the goal.

    Cites C-597c5c8469, C-a559672e76

  3. Severity minor · Kind overstatement

    The assessment says Northfold 'committed' to model and mitigate and to share the study. C-20dcb5e601 is a recommendation-type line in a developer document, which is weaker than a commitment. The next step 'as committed' repeats this.

    Cites C-20dcb5e601

  4. Severity minor · Kind unsupported_statement

    The next step on vibration monitoring is not supported by any cited quote. C-25d20304cf supports the construction hours, and C-fd52f76b29 supports 'blasting is not expected' but is not cited.

    Cites C-25d20304cf, C-fd52f76b29

Checks

  • Passed

    rating_has_evidence · blocking

  • Passed

    presence_is_evidenced · not blocking

  • Passed

    counter_evidence_considered · not blocking

  • Passed

    numbers_grounded · not blocking

  • Passed

    agencies_grounded · not blocking

  • Passed

    cutoff_respected · blocking

  • Passed

    critic_not_refuted · blocking

Evidence (15)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

Arrow keys move the selection. A middle-click opens the claim's own page.

  1. Pile driving would reach about 80 to 87 dBA for several days at the nearest non-participating residence, 260 feet from the array fence (R-2).Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 3Exact
  2. Design goal is measured daytime background Leq plus 5 dBA at non-participating residences, proposed by Northfold as a certificate condition.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  3. Northfold committed to model and mitigate battery yard noise at Linnet Road homes and share the noise study.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  4. Recommended construction controls: loud work 7 a.m. to 7 p.m. Monday to Saturday, notice, complaint line, and vibration monitoring within 200 feet of residences or wells.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 3Exact
  5. Neither Carroll County nor Harrison Township has a numeric noise limit ordinance applying to the Project, and OPSB rules set no numeric operating noise limit for solar.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  6. Predicted operating sound exceeds the design goal at two non-participating residences: R-6 by 3 dBA and R-7 by 2 dBA.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  7. Daytime background Leq was 36 to 41 dBA and nighttime L90 was 28 to 31 dBA, measured May 16 to 23, 2023.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  8. Predicted nighttime level at R-6 is 43 dBA, about 14 dBA above nighttime background, driven by battery cooling equipment.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  9. The main power transformer may produce an audible 120 Hz tone at R-7.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  10. The OPSB application must report construction and operating noise at each residence by day and night, with a preconstruction background noise study.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  11. Mitigation options for R-6 and R-7 are under evaluation and none had been selected when the report was issued.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 1Exact
  12. Neighbors on Linnet Road raised concern about night noise from the battery yard and substation.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  13. Staff highlighted a preconstruction background noise study with day and night data and predicted operating noise at every residence within one mile.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  14. Blasting is not expected.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 3Exact
  15. There are 23 residences within 1,000 feet of the fence.Tamsin Ridge Solar and Storage Project - Project Description · Page 1Exact

Noise Assessment - Tamsin Ridge Solar and Storage Project

C-0a6e65688e · Page 3 of 3 · DR-0016

Open the claim, C-0a6e65688e

Pile driving would reach about 80 to 87 dBA for several days at the nearest non-participating residence, 260 feet from the array fence (R-2).

Quote check Exact · Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own. · Read as native

Noise Assessment - Tamsin Ridge Solar and Storage Project Construction noise and vibration Pile driving is the loudest construction activity, at 85 to 95 dBA at 100 feet. Quote starts. The nearest non-participating residence is 260 feet from the array fence (R-2), where pile driving would reach about 80 to 87 dBA for several days. Quote ends. Blasting is not expected; pre-drilling where piles meet refusal is quieter than driving. Recommended controls: pile driving and other loud work only from 7:00 a.m. to 7:00 p.m., Monday to Saturday; notice to residences within 1,000 feet a week before pile driving nearby; a complaint line; vibration monitoring within 200 feet of any residence or well. Recommendations • Select and model a mitigation for the BESS yard and substation that brings R-6 and R-7 to the design goal by day and by night before the OPSB application is filed. • Specify a main power transformer with reduced sound power, or an enclosure, to remove the prominent tone at R-7. • Repeat background measurements in winter, when leaf cover and insect noise are absent, if OPSB staff ask for seasonal data. Signe Dalby, INCE Bd. Cert., Senior Acoustician, Halvard Acoustics, LLC. Halvard Acoustics, LLC - Report HA-23-061 Page 3 of 3

The outline marks where the quote begins on the page.

Page 3 of Noise Assessment - Tamsin Ridge Solar and Storage Project
  1. C-0a6e65688e

    Pile driving would reach about 80 to 87 dBA for several days at the nearest non-participating residence, 260 feet from the array fence (R-2).

    Quoted from page 3
    The nearest non-participating residence is 260 feet from the array fence (R-2), where pile driving would reach about 80 to 87 dBA for several days.

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 3 · 2023-07-10

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

  2. C-11157696c9

    Design goal is measured daytime background Leq plus 5 dBA at non-participating residences, proposed by Northfold as a certificate condition.

    Quoted from page 1
    this assessment applies a design goal of the measured daytime background Leq plus 5 dBA at each non-participating residence

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source consultant_memo · Claim type study_finding · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  3. C-20dcb5e601

    Northfold committed to model and mitigate battery yard noise at Linnet Road homes and share the noise study.

    Quoted from page 1
    Model and mitigate battery yard noise at the Linnet Road homes; share the noise study.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02 · Filed under CO-02, CO-03

  4. C-25d20304cf

    Recommended construction controls: loud work 7 a.m. to 7 p.m. Monday to Saturday, notice, complaint line, and vibration monitoring within 200 feet of residences or wells.

    Quoted from page 3
    pile driving and other loud work only from 7:00 a.m. to 7:00 p.m., Monday to Saturday;

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 3 · 2023-07-10

    Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  5. C-28e17ecd77

    Neither Carroll County nor Harrison Township has a numeric noise limit ordinance applying to the Project, and OPSB rules set no numeric operating noise limit for solar.

    Quoted from page 1
    Neither Carroll County nor Harrison Township has a noise ordinance with a numeric sound level limit

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Filed under CO-03, PE-01

  6. C-597c5c8469

    Predicted operating sound exceeds the design goal at two non-participating residences: R-6 by 3 dBA and R-7 by 2 dBA.

    Quoted from page 1
    It exceeds the goal at two non-participating residences: R-6, 610 feet west of the BESS yard, by 3 dBA (44 dBA against 41 dBA)

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02 · Filed under CO-02, CO-03

  7. C-9dd9799912

    Daytime background Leq was 36 to 41 dBA and nighttime L90 was 28 to 31 dBA, measured May 16 to 23, 2023.

    Quoted from page 1
    Daytime background Leq was 36 to 41 dBA and nighttime L90 was 28 to 31 dBA

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source field_study · Claim type study_finding · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  8. C-a188dcc65e

    Predicted nighttime level at R-6 is 43 dBA, about 14 dBA above nighttime background, driven by battery cooling equipment.

    Quoted from page 1
    so the nighttime level at R-6 (43 dBA) is about 14 dBA above the nighttime background

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

  9. C-a559672e76

    The main power transformer may produce an audible 120 Hz tone at R-7.

    Quoted from page 1
    The main power transformer may produce an audible 120 Hz tone at R-7.

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

  10. C-b46e7e0088

    The OPSB application must report construction and operating noise at each residence by day and night, with a preconstruction background noise study.

    Quoted from page 1
    The OPSB application must report construction and operating noise at each residence by day and by night, with a preconstruction background noise study.

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source consultant_memo · Claim type regulatory · Polarity presence · Confidence low · Quote check exact, 100 of 100

    Filed under CO-03, PE-02

  11. C-e87269852b

    Mitigation options for R-6 and R-7 are under evaluation and none had been selected when the report was issued.

    Quoted from page 1
    No option had been selected when this report was issued.

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 1 · 2023-07-10

    Source consultant_memo · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  12. C-ec66acfa65

    Neighbors on Linnet Road raised concern about night noise from the battery yard and substation.

    Quoted from page 1
    Noise from the battery yard and the substation at night, from neighbors on Linnet Road.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02 · Filed under CO-02, CO-03

  13. C-ef25cbb708

    Staff highlighted a preconstruction background noise study with day and night data and predicted operating noise at every residence within one mile.

    Quoted from page 1
    A preconstruction background noise study with day and night data, and predicted operating noise at every

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

  14. C-fd52f76b29

    Blasting is not expected.

    Quoted from page 3
    Blasting is not expected;

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 3 · 2023-07-10

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-02 · Filed under CO-03, EN-02

  15. C-ffd9a025a0

    There are 23 residences within 1,000 feet of the fence.

    Quoted from page 1
    There are 23 residences within 1,000 feet of the fence.

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under CO-02, CO-03

Requirements and permits

The requirements the assessor tied to this row, by level. Each quote from dated law is shown with its source.

State

  • Noise information in the OPSB certificate application: construction and operating noise at the nearest property boundary, levels at sensitive receptors within one mile, a day and night background study, and mitigation including construction hours

    OH-NOISE · Ohio Power Siting Board (OPSB)

    Applicability
    Required
    Instrument
    OAC 4906-4-08(A)(3) (application noise information)
    Trigger
    An OPSB certificate application for a generating facility of 50 MW or more, including a solar facility.
    Description

    The application must describe construction noise and operating noise expected at the nearest property boundary, locate noise-sensitive areas within one mile of the facility and give the operating noise level at each habitable residence, school, church and other sensitive receptor (any occupied building) by day and by night, describe equipment and procedures to mitigate noise, including limits on the time of day for construction, and include a preconstruction background noise study with day and night measurements. The rules in force set no numeric noise limit for a solar facility: the operating limit and construction hours in OAC 4906-4-09 then applied to wind farms only (rule title 'Regulations associated with wind farms').

    Typical timeline

    Part of the OPSB application (see OH-OPSB); the background noise study needs day and night measurements before filing.

    Version of the law on the cut-off
    OAC 4906-4-08(A)(3) as in force before 2024-05-30
    As of the cut-off

    As of the cut-off: The OPSB adopted revised rules effective 2024-05-30. OAC 4906-4-09 becomes 'Regulations associated with renewable energy generation facilities', with an operating noise limit for solar and wind (the greater of 40 dBA or the ambient L50 plus 5 dBA at non-participating sensitive receptors within one mile of the project boundary), construction hours, and minimum setbacks from solar modules (50 ft from non-participating parcel boundaries, 300 ft from non-participating residences, 150 ft from the edge of road pavement). Amendments apply only to applications filed after the rule's effective date. Not in force on 2023-08-01. (2023-07-20)

    Verification
    PACK_PENDING_QUALIFIED_REVIEW
    Source
    pack:oh.json
    In the permit matrix
    OH-NOISE
    Legal basis: 6 quotes from dated law
    Quoted from the law, page 19
    (3) Noise. The applicant shall provide information on noise from the construction and operation of the facility.

    Source OAC 4906 4 OPSB generation facility applications · page 19 · version 2023-08-01

    In force from 2018-04-26 to 2024-05-29, section 4906-4-08

    4906-4-08: version effective 2018-04-26; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 20
    Describe the operational noise levels expected at the nearest property boundary.

    Source OAC 4906 4 OPSB generation facility applications · page 20 · version 2023-08-01

    In force from 2018-04-26 to 2024-05-29, section 4906-4-08

    4906-4-08: version effective 2018-04-26; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 20
    Indicate the location of any noise-sensitive areas within one mile of the facility

    Source OAC 4906 4 OPSB generation facility applications · page 20 · version 2023-08-01

    In force from 2018-04-26 to 2024-05-29, section 4906-4-08

    4906-4-08: version effective 2018-04-26; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 20
    including limits on the time of day at which construction activities may occur

    Source OAC 4906 4 OPSB generation facility applications · page 20 · version 2023-08-01

    In force from 2018-04-26 to 2024-05-29, section 4906-4-08

    4906-4-08: version effective 2018-04-26; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 21
    Submit a preconstruction background noise study of the project area

    Source OAC 4906 4 OPSB generation facility applications · page 21 · version 2023-08-01

    In force from 2018-04-26 to 2024-05-29, section 4906-4-08

    4906-4-08: version effective 2018-04-26; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 33
    Regulations associated with wind farms.

    Source OAC 4906 4 OPSB generation facility applications · page 33 · version 2023-08-01

    In force from 2020-12-21 to 2024-05-29, section 4906-4-09

    4906-4-09: version effective 2020-12-21; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20); new solar requirements in 4906-4-09 per Bricker), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

Information requests

  • IR-701f687e7f · Medium priority

    Provide the noise ordinance, state noise standard or permit condition for the project area, or confirm none exists.

    Missing evidence
    Noise ordinance, state noise standard or permit condition
    Consequence
    Noise is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-38364f5c1f · Medium priority

    Provide the receptor map or table of homes and noise-sensitive uses for the project area, or confirm none exists.

    Missing evidence
    Receptor map or table of homes and noise-sensitive uses
    Consequence
    Noise is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-da0e177ed0 · Medium priority

    Provide the construction noise, pile driving or blasting plan for the project area, or confirm none exists.

    Missing evidence
    Construction noise, pile driving or blasting plan
    Consequence
    Noise is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

Next steps

  • Select and model mitigation for R-6 and R-7 (BESS cooling, transformer tone, siting).
  • Adopt the recommended construction hours (7 a.m. to 7 p.m., Monday to Saturday) and vibration monitoring in the OPSB application; blasting is not expected.
  • Share the noise study with Linnet Road neighbors as committed.

Agencies

  • OPSB

Cost and impact

Impact
C, S
Potential cost level
L-M
Why

Equipment selection, enclosures or relocation of BESS cooling and the transformer, and construction controls (hours, vibration monitoring) are likely. The noise study is already done and the predicted exceedances are small and at few receptors.

Impact: C = cost, S = schedule. Potential cost level: L, L-M, M, M-H, H (relative to a utility-scale solar budget).

Lumerian Labs 2026