Email: RE: Haul route and county road permits - Tamsin Ridge

C-fd643f0a74 · Page 1 of 1 · DR-0027 · 2023-07-06

The claim, in the assessor's words

Schedule has battery enclosures and transformer arriving March 2025, which falls in the frost season and has to move.

Quoted from page 1
Our schedule has the battery enclosures and the transformer arriving in March 2025, so that has to move.

Source correspondence · Claim type schedule · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by EG-03 Transportation and Access · Filed under EG-03

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as email

Go to the marked quote

From: Mara Ferreira-Holt <mferreira@northfold-energy.example> To: Tamsin Ridge project team <tamsin-team@northfold-energy.example> Cc: Anika Tessmer <atessmer@tessmer-coyle.example> Date: Thu, 06 Jul 2023 16:42:00 -0400 Subject: RE: Haul route and county road permits - Tamsin Ridge Attachments: County_Engineer_Haul_Route_Comments.pdf Team, Anika and I met the County Engineer's office yesterday about the haul route. The written comments are attached. Main points: 1. Special hauling permit from the County Engineer before any heavy hauling on county roads. No fee, but a bond of at least $25,000 per mile of county road used, Board of County Commissioners as obligee. They want the Roadway Use and Maintenance Agreement for Power Facilities signed before the first permit. 2. The Linnet Road bridge over Sallow Creek stays posted at 10 tons. No construction trucks over it, full stop. East Block traffic goes Fescue Road to Dunmore Road as Tessmer Coyle proposed. The engineer wants the Dunmore Road culvert at S-2 load-rated by us before we use it. 3. Frost season: legal limits drop 25% from December 1 to May 15. Heavy hauling then only on frozen ground with the engineer's approval. Quote starts. Our schedule has the battery enclosures and the transformer arriving in March 2025, so that has to move. Quote ends. 4. Driveway permits for the four construction entrances through the Engineer's office; the temporary-access option is fine for the two Fescue Road entrances. The township trustees issue nothing for Fescue Road, but they want a road use agreement and a pre-construction video survey. 5. Pavement: they expect Fescue Road to need a full rebuild after construction and will price it against the bond. Budget about $1.1M. I have asked counsel to check whether any of this changes once the OPSB certificate is issued; the county says it expects the agreement either way. Mara Mara Ferreira-Holt Development Manager, Northfold Energy Partners, LLC

The page

This document has no page picture (only PDF and image documents have one).

Other claims quoted on this page

  • C-1a66f574d1

    The Linnet Road bridge over Sallow Creek remains posted at 10 tons and no construction trucks may cross it.

  • C-0d4232e3e0

    The County Engineer wants the Dunmore Road culvert at S-2 load-rated by the developer before use; East Block traffic routes via Fescue Road to Dunmore Road.

  • C-854b149715

    Driveway permits are needed for the four construction entrances through the Engineer's office; temporary access option is acceptable for the two Fescue Road entrances.

  • C-a8a3394ea1

    Township trustees issue no permit for Fescue Road but want a road use agreement and pre-construction video survey.

  • C-ff742a0f54

    County expects Fescue Road to need a full rebuild after construction, priced against the bond; about $1.1M budget suggested.