The claim, in the assessor's words

The Linnet Road bridge over Sallow Creek is posted at 10 tons and limits construction vehicles to that weight.

Quoted from page 1
The Linnet Road bridge over Sallow Creek is posted at 10 tons and may not be used by construction vehicles over that limit.

Source agency_determination · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by EG-03 Transportation and Access · Filed under EG-03

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

Carroll County Engineer's Office Carrollton, Ohio July 5, 2023 To: Northfold Energy Partners, LLC and Tessmer Coyle Engineering, Inc. Re: Haul route review, Tamsin Ridge Solar and Storage Project, Harrison Township Following our meeting today, the County Engineer's Office has these comments on the proposed haul route and road use for the project: • A Special Hauling Permit is required before any heavy hauling on county roads. There is no charge for the permit. A bond of not less than $25,000 per mile of county road used is required, with the Carroll County Commissioners as obligee. • A Roadway Use and Maintenance Agreement for Power Facilities must be executed before the first permit is issued. • Quote starts. The Linnet Road bridge over Sallow Creek is posted at 10 tons and may not be used by construction vehicles over that limit. Quote ends. The Dunmore Road culvert at stream S-2 must be load-rated by the applicant's engineer before use. • From December 1 to May 15 legal load limits on county and township roads are reduced 25 percent; heavy hauling in that period is allowed only on frozen roadways with this office's approval. • Driveway permits are required for each entrance on a county road, issued by the Board of County Commissioners through this office. • Pre-construction and post-construction condition surveys are required. Damage will be priced by this office and billed to the permit holder; the bond is returned or transferred according to the condition of the road after hauling. • The township trustees must be contacted before hauling on township roads. (signed) Deputy Engineer, for the Carroll County Engineer Carroll County Engineer's Office Page 1 of 1

The page

The outline marks where the quote begins on the page.

Page 1 of Haul Route Review Comments - Tamsin Ridge Solar and Storage Project

Other claims quoted on this page

  • C-489ba43d8d

    A Special Hauling Permit is required before heavy hauling on county roads, with no permit charge.

  • C-c0f949e19e

    A bond of at least $25,000 per mile of county road used is required, with the County Commissioners as obligee.

  • C-56a716f989

    A Roadway Use and Maintenance Agreement for Power Facilities must be executed before the first permit is issued.

  • C-1e99f7e335

    The Dunmore Road culvert at stream S-2 must be load-rated by the applicant's engineer before use.

  • C-fe62671132

    A stream designated S-2 is crossed by Dunmore Road, and Sallow Creek is crossed by Linnet Road.

  • C-538c2d7511

    From December 1 to May 15 legal load limits are reduced 25 percent; heavy hauling then is allowed only on frozen roads with approval.

  • C-e6b7316e42

    Driveway permits are required for each entrance on a county road, issued by the Board of County Commissioners through the Engineer's office.