Haul Route Review Comments - Tamsin Ridge Solar and Storage Project
C-c0f949e19e · Page 1 of 1 · DR-0029 · 2023-07-05
The claim, in the assessor's words
A bond of at least $25,000 per mile of county road used is required, with the County Commissioners as obligee.
A bond of not less than $25,000 per mile of county road used is required, with the Carroll County Commissioners as obligee.
Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100
Cited by EG-03 Transportation and Access · Filed under EG-03
On the page
The page text exactly as the engine read it, with the quote marked.
Placed verbatim · The quote occurs on the page exactly as written.
Read as native
The page
The outline marks where the quote begins on the page.

Other claims quoted on this page
A Special Hauling Permit is required before heavy hauling on county roads, with no permit charge.
A Roadway Use and Maintenance Agreement for Power Facilities must be executed before the first permit is issued.
The Linnet Road bridge over Sallow Creek is posted at 10 tons and limits construction vehicles to that weight.
The Dunmore Road culvert at stream S-2 must be load-rated by the applicant's engineer before use.
A stream designated S-2 is crossed by Dunmore Road, and Sallow Creek is crossed by Linnet Road.
From December 1 to May 15 legal load limits are reduced 25 percent; heavy hauling then is allowed only on frozen roads with approval.
Driveway permits are required for each entrance on a county road, issued by the Board of County Commissioners through the Engineer's office.