Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge
C-27017a88b6 · Page 1 of 1 · DR-0023 · 2023-05-12
The claim, in the assessor's words
Commissioners took no action at the meeting; the Board would decide within the statutory 90 days after the meeting.
One commissioner said the Board would decide within the 90 days the statute allows after this meeting
Source developer_document · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100
Cited by CO-02 Community Engagement & Relations, PE-01 Local Zoning & Permitting, PE-07 Regional Siting Climate · Filed under CO-02, PE-01, PE-07
On the page
The page text exactly as the engine read it, with the quote marked.
Placed verbatim · The quote occurs on the page exactly as written.
Read as docx
The page
This document has no page picture (only PDF and image documents have one).
Other claims quoted on this page
Of 27 speakers at the public meeting, 21 opposed the project and 6 supported it.
Opponents' most frequent concern was fire risk from the battery storage yard and volunteer fire department response capacity.
Neighbors on Linnet Road raised concern about night noise from the battery yard and substation.
Residents raised concern about flooding along Sallow Creek and runoff from arrays onto neighboring fields.
Opponents raised property values and views, requesting 500-foot setbacks from homes and taller screening.
Residents raised concern about construction damage to township roads and the posted Linnet Road bridge.
A petition signed by 212 residents asks commissioners to adopt a resolution prohibiting the facility and designate Harrison Township a restricted area for large solar.
Harrison Township Neighbors for Farmland said it would intervene in the OPSB case and pursue a referendum if the county acted on restricted areas and the decision were challenged.
Northfold committed to model and mitigate battery yard noise at Linnet Road homes and share the noise study.
Northfold committed to meet the volunteer fire department and county EMA on the emergency response plan and fund training and equipment.
Northfold will offer good neighbor agreements with screening to the 14 nearest non-participating homes.
Northfold will keep the undermined area out of the layout unless the mine investigation shows it is safe.
OPSB public informational meeting will be held after the county's 90-day period.
64 written comments were received at the meeting: 51 opposed and 13 in support.