Local Zoning & Permitting

PE-01 · Matrix · Additional Permitting

Rating
3Resource is present, likely difficult to address
Why
Core of the site; partly avoidable
Worst case
Up to4Potential fatal flaw
Evidence
Verified
Cited claims
17
Requirements
6
Requests
1

Rating

3Resource is present, likely difficult to address

up to4Potential fatal flaw

The engine shows this rating as 3-4

The rule

Code computed the rating from the assessor's inputs:

extent=core, avoidable=partly -> 3

Set by the rule

Decision
Released with flags
The engine's reasons
Evidence state
Verified · field study or agency determination

Worst case

If what is pending at the cut-off went badly, the same rule gives a higher rating.

Scenario

Commissioners adopt a resolution prohibiting the facility or designating Harrison Township a restricted area, barring the OPSB application.

Step still pending
Board of County Commissioners decision under ORC 303.62 within 90 days of the county public meeting, or a restricted-area resolution under ORC 303.58
Inputs in the worst case
Extent core · Avoidable no · Pathway prohibition · Impact likely yes
The rule on the worst case
worst case: pathway=prohibition -> 4 potential fatal flaw

Revision

Not revised.

The five inputs

Comments

No county or township zoning applies, so no local zoning, conditional use or setback approval is required. Residents have petitioned commissioners to prohibit the facility and designate Harrison Township a restricted area; the Board may decide within 90 days of the county meeting. County hauling and driveway permits still apply.

Critique

Verdict
upheld
Suggested direction for the rating
same
Summary

Assessment is largely supported. Minor issues: the no-restricted-area finding predates the May petition, road-permit applicability ignores the ORC 4906.13(B) uncertainty, the PJM exemption step looks moot, and the extent rationale leans on absence letters. Category 3 is reasonable.

Critic model
Luminol

Issues

  1. Severity minor · Kind as_of_error

    Pathway says no restricted area or prohibition is in force, citing counsel's search (C-0fe7f42a17) dated 2023-03-28. That predates the 2023-05-12 petition and meeting, so it does not cover the cut-off. The petition itself only implies none existed in May. Confirm with the county as of 2023-08-01.

    Cites C-0fe7f42a17, C-24271b647d

  2. Severity minor · Kind unsupported_statement

    County hauling and driveway permits are stated as flatly required. The requirement text notes ORC 4906.13(B) may bar local permits for an OPSB-certificated facility, and the sources do not settle this. The assessment should flag the uncertainty.

    Cites C-489ba43d8d, C-e6b7316e42, C-854b149715

  3. Severity minor · Kind missing_next_step

    The next step to confirm the PJM Section 4 exemption is low value. Queue date 2021-09-24 and the April 2022 feasibility study stage suggest the exemption conditions (accepted application and completed system impact study as of 2021-10-11) are not met. State this, and add a step to confirm whether ORC 4906.13(B) preempts the road permits.

  4. Severity minor · Kind other

    The extent rationale cites the zoning-absence letters (C-8041623932, C-2a27cb9782) to support 'core'. Those show absence of requirements, not extent. Core rests only on the SB 52 county process, which is a judgment call. A county decision on the 90-day window would settle it.

    Cites C-8041623932, C-2a27cb9782

Checks

  • Passed

    rating_has_evidence · blocking

  • Passed

    presence_is_evidenced · not blocking

  • Failed

    counter_evidence_considered · not blocking

    Uncited absence claims to weigh: C-28e17ecd77

  • Passed

    numbers_grounded · not blocking

  • Passed

    agencies_grounded · not blocking

  • Passed

    cutoff_respected · blocking

  • Passed

    critic_not_refuted · blocking

Evidence (17)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

Arrow keys move the selection. A middle-click opens the claim's own page.

  1. Applicant must hold a public meeting in Carroll County 90 to 300 days before filing the application (ORC 303.61).OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  2. Carroll County has not adopted a county zoning resolution, and Harrison Township has not adopted a township zoning resolution under ORC Chapter 519.Zoning Verification - Tamsin Ridge Solar and Storage Project · Page 1Exact
  3. Counsel's search found no ORC 303.58 restricted-area resolution for Harrison Township on the conference date.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  4. Carroll County requires a special hauling permit, a bond of at least $25,000 per mile, and a Roadway Use and Maintenance Agreement.Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · Page 2Exact
  5. A petition signed by 212 residents asks commissioners to adopt a resolution prohibiting the facility and designate Harrison Township a restricted area for large solar.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  6. Commissioners took no action at the meeting; the Board would decide within the statutory 90 days after the meeting.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  7. No setback waivers have been requested because no local or state setback applies to the solar facility.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  8. Within 90 days after the county public meeting, the Board of County Commissioners may adopt a resolution prohibiting the facility or limiting its boundaries (ORC 303.62).OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  9. A Special Hauling Permit is required before heavy hauling on county roads, with no permit charge.Haul Route Review Comments - Tamsin Ridge Solar and Storage Project · Page 1Exact
  10. No local zoning, conditional use, variance or site plan approval is required, and no local setback, height or screening standard applies to the proposed facility.Zoning Verification - Tamsin Ridge Solar and Storage Project · Page 1Exact
  11. Battery enclosures, substation equipment and cranes are overweight or oversize loads needing county and township permits.Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · Page 1Exact
  12. Driveway permits are needed for the four construction entrances through the Engineer's office; temporary access option is acceptable for the two Fescue Road entrances.Email: RE: Haul route and county road permits - Tamsin Ridge · Page 1Exact
  13. Opponents raised property values and views, requesting 500-foot setbacks from homes and taller screening.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  14. A resolution designating restricted areas under ORC 303.58 would bar an application for a facility within them.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  15. Staff indicated solar cases with active local opposition have recently taken 9 to 14 months from filing to decision.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  16. Harrison Township Neighbors for Farmland said it would intervene in the OPSB case and pursue a referendum if the county acted on restricted areas and the decision were challenged.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  17. Driveway permits are required for each entrance on a county road, issued by the Board of County Commissioners through the Engineer's office.Haul Route Review Comments - Tamsin Ridge Solar and Storage Project · Page 1Exact

OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project

C-07afad26a4 · Page 1 of 2 · DR-0026

Open the claim, C-07afad26a4

Applicant must hold a public meeting in Carroll County 90 to 300 days before filing the application (ORC 303.61).

Quote check Exact · Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own. · Read as native

Whitlock Ames LLP Energy, siting and regulatory counsel | Columbus, Ohio Ohio Power Siting Board Pre-Application Conference Memorandum to Northfold Energy Partners, LLC. March 28, 2023. Conference held March 21, 2023 at the OPSB offices, Columbus, with OPSB staff. 1. Jurisdiction Staff agreed that the Tamsin Ridge Solar and Storage Project, 120 MW of solar generation with a 60 MW / 240 MWh battery system, is a major utility facility that needs a certificate of environmental compatibility and public need from the OPSB before construction, under the standard certificate process. Staff will treat the battery system as part of the generating facility. A case number will be assigned when the pre-application notification letter is filed. 2. SB 52 Staff noted that Sub. S.B. 52 applies. The Section 4 exemption for projects already in PJM's new services queue does not appear to be available, because no PJM system impact study had been completed for AH1-931 as of October 11, 2021, the act's effective date, and no facilities study fee had been paid. Therefore: (a) Quote starts. the applicant must hold a public meeting in Carroll County at least 90 and not more than 300 days before filing the application Quote ends. (ORC 303.61); (b) within 90 days after that meeting the Board of County Commissioners may adopt a resolution prohibiting the facility or limiting its boundaries (ORC 303.62); (c) two ad hoc members, one for the county commissioners and one for the township trustees, will sit on the Board for this case; and (d) the decommissioning plan and performance bond requirements of ORC 4906.21 to 4906.222 apply. Staff also noted that a resolution designating restricted areas under ORC 303.58 would bar an application for a facility within them. Counsel's search found no such resolution for Harrison Township on the date of the conference. 3. Application content highlighted by staff • A preconstruction background noise study with day and night data, and predicted operating noise at every residence within one mile. • A table of distances from equipment to every structure and property line within 1,500 feet, with the lease status of each property. • Ecological surveys coordinated with ODNR and the U.S. Fish and Wildlife Service, wetland delineation before filing, and the ODNR buffers for Category 3 wetlands. • Cultural resources surveys to SHPO standards, submitted to the SHPO. • A fire protection, safety and medical emergency plan prepared with local responders, including the battery system. • Mapping of agricultural district land and a drain tile repair plan. • A geotechnical report addressing the abandoned underground mine in the East Block. Whitlock Ames LLP - privileged Page 1 of 2

The outline marks where the quote begins on the page.

Page 1 of OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project
  1. C-07afad26a4

    Applicant must hold a public meeting in Carroll County 90 to 300 days before filing the application (ORC 303.61).

    Quoted from page 1
    the applicant must hold a public meeting in Carroll County at least 90 and not more than 300 days before filing the application

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Filed under CO-02, PE-01

  2. C-09acff9294

    Carroll County has not adopted a county zoning resolution, and Harrison Township has not adopted a township zoning resolution under ORC Chapter 519.

    Quoted from page 1
    Carroll County has not adopted a county zoning resolution. Harrison Township has not adopted a township zoning resolution under ORC Chapter 519.

    Zoning Verification - Tamsin Ridge Solar and Storage Project · DR-0022 · Page 1 · 2023-02-14

    Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-07 · Filed under PE-01, PE-07

  3. C-0fe7f42a17

    Counsel's search found no ORC 303.58 restricted-area resolution for Harrison Township on the conference date.

    Quoted from page 1
    Counsel's search found no such resolution for Harrison Township on the date of the

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-07 · Filed under PE-01, PE-07

  4. C-1af8ef8e00

    Carroll County requires a special hauling permit, a bond of at least $25,000 per mile, and a Roadway Use and Maintenance Agreement.

    Quoted from page 2
    a bond of at least $25,000 per mile, with the Board of County Commissioners as obligee, and a Roadway Use and Maintenance Agreement for Power Facilities.

    Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · DR-0020 · Page 2 · 2023-06-19

    Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EG-03, PE-01

  5. C-24271b647d

    A petition signed by 212 residents asks commissioners to adopt a resolution prohibiting the facility and designate Harrison Township a restricted area for large solar.

    Quoted from page 1
    It asks the Board of County Commissioners to adopt a resolution under ORC 303.62 prohibiting the facility and to designate Harrison Township a restricted area for large solar facilities under ORC 303.58.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, PE-07 · Filed under CO-02, PE-01, PE-07

  6. C-27017a88b6

    Commissioners took no action at the meeting; the Board would decide within the statutory 90 days after the meeting.

    Quoted from page 1
    One commissioner said the Board would decide within the 90 days the statute allows after this meeting

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, PE-07 · Filed under CO-02, PE-01, PE-07

  7. C-2a27cb9782

    No setback waivers have been requested because no local or state setback applies to the solar facility.

    Quoted from page 2
    No setback waivers have been requested, because no local or state setback applies to the solar facility.

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-05 · Filed under PE-01, PE-05

  8. C-33a9601349

    Within 90 days after the county public meeting, the Board of County Commissioners may adopt a resolution prohibiting the facility or limiting its boundaries (ORC 303.62).

    Quoted from page 1
    the Board of County Commissioners may adopt a resolution prohibiting the facility or limiting its boundaries (ORC 303.62)

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, PE-07 · Filed under CO-02, PE-01, PE-07

  9. C-489ba43d8d

    A Special Hauling Permit is required before heavy hauling on county roads, with no permit charge.

    Quoted from page 1
    A Special Hauling Permit is required before any heavy hauling on county roads. There is no charge for the permit.

    Haul Route Review Comments - Tamsin Ridge Solar and Storage Project · DR-0029 · Page 1 · 2023-07-05

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-03 · Filed under EG-03, PE-01

  10. C-8041623932

    No local zoning, conditional use, variance or site plan approval is required, and no local setback, height or screening standard applies to the proposed facility.

    Quoted from page 1
    No local zoning permit, conditional use permit, variance or site plan approval is therefore required for the proposed facility, and no local setback, height or screening standard applies to it.

    Zoning Verification - Tamsin Ridge Solar and Storage Project · DR-0022 · Page 1 · 2023-02-14

    Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-04, VI-01 · Filed under EG-04, PE-01, VI-01

  11. C-84c9333669

    Battery enclosures, substation equipment and cranes are overweight or oversize loads needing county and township permits.

    Quoted from page 1
    The battery enclosures, the substation equipment and the cranes are overweight or oversize loads and will need county and township permits as well.

    Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · DR-0020 · Page 1 · 2023-06-19

    Source consultant_memo · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EG-03, PE-01

  12. C-854b149715

    Driveway permits are needed for the four construction entrances through the Engineer's office; temporary access option is acceptable for the two Fescue Road entrances.

    Quoted from page 1
    Driveway permits for the four construction entrances through the Engineer's office;

    Email: RE: Haul route and county road permits - Tamsin Ridge · DR-0027 · Page 1 · 2023-07-06

    Source correspondence · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EG-03, PE-01

  13. C-87c8ed2e8e

    Opponents raised property values and views, requesting 500-foot setbacks from homes and taller screening.

    Quoted from page 1
    Property values and views, with requests for 500-foot setbacks from homes and taller screening.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, VI-01 · Filed under CO-02, PE-01, VI-01

  14. C-a1e4999eda

    A resolution designating restricted areas under ORC 303.58 would bar an application for a facility within them.

    Quoted from page 1
    a resolution designating restricted areas under ORC 303.58 would bar an application for a

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-07 · Filed under PE-01, PE-07

  15. C-b61135956d

    Staff indicated solar cases with active local opposition have recently taken 9 to 14 months from filing to decision.

    Quoted from page 2
    Staff indicated that solar cases with active local opposition have recently taken 9 to 14 months from filing to decision.

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 2 · 2023-03-28

    Source agency_determination · Claim type schedule · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, PE-02 · Filed under PE-01, PE-02

  16. C-e3e7beda35

    Harrison Township Neighbors for Farmland said it would intervene in the OPSB case and pursue a referendum if the county acted on restricted areas and the decision were challenged.

    Quoted from page 1
    A group of neighbors, Harrison Township Neighbors for Farmland, said it would intervene in the OPSB case and would pursue a referendum if the county acted on restricted areas and the decision were challenged.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02 · Filed under CO-02, PE-07

  17. C-e6b7316e42

    Driveway permits are required for each entrance on a county road, issued by the Board of County Commissioners through the Engineer's office.

    Quoted from page 1
    Driveway permits are required for each entrance on a county road, issued by the Board of County Commissioners through this office.

    Haul Route Review Comments - Tamsin Ridge Solar and Storage Project · DR-0029 · Page 1 · 2023-07-05

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-03 · Filed under EG-03, PE-01

Requirements and permits

The requirements the assessor tied to this row, by level. Each quote from dated law is shown with its source.

State

  • SB 52 county controls on large solar facilities: restricted areas, the county public meeting and resolution, the two voting ad hoc board members, and the PJM exemption in Section 4

    OH-SB52 · Board of county commissioners and boards of township trustees (county controls); Ohio Power Siting Board (OPSB)

    Applicability
    Required
    Instrument
    Senate Bill 52, 134th General Assembly (effective 2021-10-11), including its uncodified Section 4; ORC 303.57 to 303.62, 4906.02, 4906.021 to 4906.025, 4906.101 to 4906.103, 4906.30 and 4906.31
    Trigger
    An application for a certificate for a large solar facility that is not exempt under Section 4 of SB 52.
    Description

    A board of county commissioners may designate all or part of the unincorporated county as a restricted area where large solar facilities are prohibited. The resolution takes effect 30 days after adoption unless a referendum petition is filed, and no one may file an application for a prohibited facility there. Otherwise the developer must hold a public meeting in each county 90 to 300 days before applying; within 90 days the commissioners may prohibit the facility or limit its boundaries. The board includes two voting ad hoc members for the township trustees and county commissioners. Section 4 exempts a large solar facility in the PJM new services queue if, as of the act's effective date, its application had been found to comply with the application requirements and accepted by the board, and the applicant had a completed PJM system impact study and had paid the facilities study fee. Whether the county has designated a restricted area, and whether the exemption is met, are facts to confirm with the county and PJM records.

    Typical timeline

    Law: the county meeting is held 90 to 300 days before the application, and the commissioners may act within 90 days of it, so a filing cannot sensibly come sooner than about 90 days after the meeting (a reading of the two periods). A restricted-area resolution takes effect 30 days after adoption unless a referendum petition is filed.

    Version of the law on the cut-off
    SB 52 as enacted (statute text only)
    As of the cut-off

    As of the cut-off: SB 52 took effect. This is the 'effective date' that Section 4 uses for the PJM test (completed system impact study and paid facilities study fee) and that Section 5 uses for ad hoc members on applications not yet accepted. (2021-10-11)

    Verification
    PACK_PENDING_QUALIFIED_REVIEW
    Source
    pack:oh.json
    In the permit matrix
    OH-SB52
    Legal basis: 11 quotes from dated law
    Quoted from the law, page 3
    The board of county commissioners may adopt a resolution designating all or part of the unincorporated area of a county as a restricted area, prohibiting the construction of any or all of the following: (1) An economically significant wind farm; (2) A large wind farm; (3) A large solar facility.

    Source ORC 303.57 to 303.62 county restricted areas · page 3 · version 2023-08-01

    In force from 2021-10-11 to 2025-04-08, section 303.58

    303.58: version effective 2021-10-11; first change after it 2025-04-09 (H.B. 497, 135th GA), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 6
    The act prohibits a person from filing an application for a certificate, or a material amendment to an existing certificate, to construct, operate, or maintain a utility facility in a restricted area, if such a facility is prohibited in that restricted area.

    Source SB 52 LSC Final Analysis · page 6 · version 2021-10-11

    May be cited on the cut-off date.

    Quoted from the law, page 7
    The act conditions the designation of a restricted area upon the right of referendum the act grants county voters. A resolution designating a restricted area becomes effective 30 days from the day it is adopted, unless a referendum petition is filed with the board of county commissioners.

    Source SB 52 LSC Final Analysis · page 7 · version 2021-10-11

    May be cited on the cut-off date.

    Quoted from the law, page 9
    At least ninety days, but not more than three hundred days, prior to applying for a certificate from the power siting board, or a material amendment to an existing certificate, for a utility facility, to be located in whole or in part in the unincorporated area of a county, the person intending to apply shall hold a public meeting in each county where the utility facility is to be located.

    Source ORC 303.57 to 303.62 county restricted areas · page 9 · version 2023-08-01

    In force from 2021-10-11 to 2026-10-03, section 303.61

    303.61: version effective 2021-10-11, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 11
    Not later than ninety days after the public meeting described in section 303.61 of the Revised Code regarding an application for a certificate, or a material amendment to an existing certificate, for a utility facility, the board of county commissioners may adopt a resolution that does either of the following:

    Source ORC 303.57 to 303.62 county restricted areas · page 11 · version 2023-08-01

    In force from 2021-10-11 to 2026-10-03, section 303.62

    303.62: version effective 2021-10-11, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 11
    (1) Prohibits the construction of the utility facility that is the subject of the certificate; (2) Limits the boundaries of the proposed utility facility to a smaller geographic area of the county, completely within what was proposed by the applicant. (B) If no resolution is adopted within the time required under this section, the application may proceed as filed with the power siting board.

    Source ORC 303.57 to 303.62 county restricted areas · page 11 · version 2023-08-01

    In force from 2021-10-11 to 2026-10-03, section 303.62

    303.62: version effective 2021-10-11, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 24
    Whenever an application is made to the power siting board for a certificate or a material amendment to an existing certificate for a utility facility, the board shall include two voting ad hoc members to represent the interests of the residents of the area in which the utility facility is to be located.

    Source ORC 4906 Power Siting Board · page 24 · version 2023-08-01

    In force from 2021-10-11 to 2026-10-03, section 4906.021

    4906.021: version effective 2021-10-11, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 24
    (C)(1) The ad hoc members shall be: (a) The chairperson of the board of township trustees of the township in which the utility facility is to be located or the chairperson's designee; (b) The president of the board of county commissioners of the county in which the utility facility is to be located or the president's designee

    Source ORC 4906 Power Siting Board · page 24 · version 2023-08-01

    In force from 2021-10-11 to 2026-10-03, section 4906.021

    4906.021: version effective 2021-10-11, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 4
    States that applications for a certificate or material amendment to an existing certificate for a large solar facility are not subject to the act's provisions if, as of October 11, 2021: The facility is in the PJM Interconnection and Regional Transmission Organization, L.L.C. (PJM), New Services Queue;

    Source SB 52 LSC Final Analysis · page 4 · version 2021-10-11

    May be cited on the cut-off date.

    Quoted from the law, page 13
    if, as of the effective date of this section: (1) The applicant has received a completed system impact study from PJM for the large solar facility; and (2) The applicant has paid the fee for the facilities study to PJM.

    Source SB 52 134th GA as enrolled · page 13 · version 2021-10-11

    May be cited on the cut-off date.

    Quoted from the law, page 4
    The application has been found to be in compliance with the application requirements by the PSB Chairperson (or the Chairperson’s designee) and has been accepted by PSB;

    Source SB 52 LSC Final Analysis · page 4 · version 2021-10-11

    May be cited on the cut-off date.

  • Certificate of environmental compatibility and public need for a major utility facility (electric generating plant of 50 MW or more), standard certificate application

    OH-OPSB · Ohio Power Siting Board (OPSB)

    Applicability
    Required
    Instrument
    ORC 4906.01, 4906.04, 4906.06, 4906.07, 4906.10 and 4906.13; OAC 4906-2, 4906-3 and 4906-4
    Trigger
    Construction of an electric generating plant, including a solar plant, designed for or capable of operating at 50 MW or more.
    Description

    An electric generating plant designed for, or capable of, 50 MW or more is a major utility facility, and no one may commence to construct one without an OPSB certificate. The generation-facility application content rules (OAC 4906-4-08) include a fire protection, safety and medical emergency plan developed with local responders. The chairman accepts the application as complete or rejects it within 60 days of receipt, and the hearing is set 60 to 90 days after receipt of a complying application. The board may not grant a certificate, as proposed or as modified, unless it makes the findings in ORC 4906.10(A). Once certificated, no public agency or political subdivision may require any approval, consent, permit or other condition for construction or operation (PE-01); state worker-protection laws and municipal rules not about location or design still apply. Whether a state fire-code or building permit still applies is not settled by the library text.

    Typical timeline

    Law: the chairman accepts or rejects the application within 60 days of receipt (OAC 4906-3-06(A)); the public hearing is fixed not less than 60 nor more than 90 days after receipt of a complying application (ORC 4906.07(A)); the staff report is due 15 days before the hearing and OPSB says it typically comes 60 to 90 days after the completeness letter. The library sets no overall deadline for the Board's decision. Practice estimate: about a year or more from filing to a Board decision on a contested solar case, plus the pre-application public meetings that must come first (see OH-OPSB-PUBLIC and OH-SB52).

    Version of the law on the cut-off
    As in force from 2023-05-15 (the library text)
    As of the cut-off

    As of the cut-off: The OPSB adopted revised rules in OAC Chapters 4906-1 to 4906-7 after a review begun in 2020. They add requirements for solar facilities, including setbacks for panel modules of at least 50 feet from non-participating parcel boundaries, 300 feet from non-participating residences and 150 feet from the edge of pavement of roads. They took effect 2024-05-30 and apply to applications filed on or after that date. Not in force on 2023-08-01: the OAC 4906-4 text cited here is the 2015 to 2020 text. As of 2023-04-19 the OPSB's rule-review page showed the review still pending. (2023-07-20)

    Verification
    PACK_PENDING_QUALIFIED_REVIEW
    Source
    pack:oh.json
    In the permit matrix
    OH-OPSB
    Legal basis: 8 quotes from dated law
    Quoted from the law, page 1
    "Major utility facility" means: (a) Electric generating plant and associated facilities designed for, or capable of, operation at a capacity of fifty megawatts or more;

    Source ORC 4906 Power Siting Board · page 1 · version 2023-08-01

    In force from 2021-10-11 to 2025-08-13, section 4906.01

    4906.01: version effective 2021-10-11; first change after it 2025-08-14 (Am. Sub. H.B. 15, 136th GA), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 9
    No person shall commence to construct a major utility facility in this state without first having obtained a certificate for the facility.

    Source ORC 4906 Power Siting Board · page 9 · version 2023-08-01

    In force from 1981-11-15 to 2026-10-03, section 4906.04

    4906.04: version effective 1981-11-15, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 13
    the power siting board shall promptly fix a date for a public hearing thereon, not less than sixty nor more than ninety days after such receipt, and shall conclude the proceeding as expeditiously as practicable.

    Source ORC 4906 Power Siting Board · page 13 · version 2023-08-01

    In force from 2012-09-10 to 2025-08-13, section 4906.07

    4906.07: version effective 2012-09-10; first change after it 2025-08-14 (Am. Sub. H.B. 15, 136th GA), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 16
    The board shall not grant a certificate for the construction, operation, and maintenance of a major utility facility, either as proposed or as modified by the board, unless it finds and determines all of the following:

    Source ORC 4906 Power Siting Board · page 16 · version 2023-08-01

    In force from 2021-10-11 to 2025-08-13, section 4906.10

    4906.10: version effective 2021-10-11; first change after it 2025-08-14 (Am. Sub. H.B. 15, 136th GA), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 20
    authorized by a certificate issued pursuant to Chapter 4906. of the Revised Code. Nothing herein shall prevent the application of state laws for the protection of employees engaged in the construction of such facility or wind farm nor of municipal regulations that do not pertain to the location or design of,

    Source ORC 4906 Power Siting Board · page 20 · version 2023-08-01

    In force from 2019-10-22 to 2026-10-03, section 4906.13

    4906.13: version effective 2019-10-22, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 8
    the chairman shall examine the certificate application to determine compliance with Chapters 4906-1 to 4906-7 of the Administrative Code. Within sixty days following receipt, the chairman shall either:

    Source OAC 4906 3 OPSB application filing · page 8 · version 2023-08-01

    In force from 2015-12-11 to 2024-05-29, section 4906-3-06

    4906-3-06: version effective 2015-12-11; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 19
    Describe the fire protection, safety, and medical emergency plan(s) to be used during construction and operation of the facility, and how such plan(s) will be developed in consultation with local emergency responders.

    Source OAC 4906 4 OPSB generation facility applications · page 19 · version 2023-08-01

    In force from 2018-04-26 to 2024-05-29, section 4906-4-08

    4906-4-08: version effective 2018-04-26; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

    Quoted from the law, page 1
    The staff report is due 15 days prior to the scheduled public hearing and typically is submitted between 60 and 90 days after the letter of completeness has been issued.

    Source OPSB standard application process · page 1 · version 2023-05-15

    May be cited on the cut-off date.

Local

  • County engineer permits for work in the county road right-of-way and for driveways

    CCO-ROW · Carroll County Engineer and Board of County Commissioners (county roads)

    Applicability
    Likely
    Instrument
    County Engineer's Permit for the Use of the County Highway Right-of-Way (rev. 4/2022) and Driveway Permit for Construction within the County Right-of-Way Limits (rev. 5/2020); ORC 5547.04
    Trigger
    Any work within the right-of-way of a county road, or any driveway that connects to a county road.
    Description

    Work within a county road right-of-way needs the Permit for the Use of the County Highway Right-of-Way from the County Engineer's office, with a drawing of the work; underground lines parallel to the road run at least 30 inches deep behind the ditch line. A driveway that connects to a county road needs a permit from the Board of County Commissioners issued through the County Engineer; the form has a temporary-access option, removed when the project ends, with traffic-control measures. The Engineer's page also lists a Roadway Use and Maintenance Agreement for Power Facilities (form text not in the library). ORC 5547.04 bars erecting an obstruction within a highway other than a state highway without the approval of the board of county commissioners. ORC 4906.13(B) bars a political subdivision from requiring 'any approval, consent, permit, certificate, or other condition' for an OPSB-certificated facility, while OAC 4906-4-06(F)(4) has the applicant list all transportation permits required; the sources do not settle whether these permits bind a certificated project.

    Typical timeline

    No review period is stated in the sources; the County Engineer's Office must be notified two working days before work starts in the right-of-way (right-of-way permit condition 3).

    As of the cut-off

    As of the cut-off: ORC 4906.13 (No local jurisdiction) took effect in the version in force on 2023-08-01 (House Bill 6, 133rd General Assembly). (2019-10-22)

    Verification
    PACK_PENDING_QUALIFIED_REVIEW
    Source
    pack:oh_carroll_county.json
    In the permit matrix
    CCO-ROW
    Legal basis: 8 quotes from dated law
    Quoted from the law, page 1
    1. Attach a drawing of the proposed work. Show plan, profile, section, pavement, pipes, bridges, etc. 2. Underground lines, etc. parallel to the road shall be no less than 30” deep, located behind the back side of the ditch line and have permanent markers at the R/W line, angle points every 200 feet within the R/W.

    Source Carroll County OH Engineer Right of Way Permit rev 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    3. The County Engineer’s Office shall be notified two working days before any work is started within the R/W. 4. Any expense incurred by the County due to the applicant’s use of the R/W will be paid by the applicant.

    Source Carroll County OH Engineer Right of Way Permit rev 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    All driveways that connect to a county road in Carroll County require a permit from the Board of County Commissioners issued through the office of the County Engineer.

    Source Carroll County OH Engineer Driveway Construction Permit rev 2020 05 · page 1 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 2
    Temporary access permit only. Driveway to be removed upon completion of the project. Temporary Drive Permit Requirements: All temporary driveway permits must utilize Management of Traffic (MOT) measures (e.g. flagging, signage) as outlined by applicable material from ODOT’s Ohio Manual of Uniform Traffic Control Devices (OMUTCD).

    Source Carroll County OH Engineer Driveway Construction Permit rev 2020 05 · page 2 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 1
    Roadway Use and Maintenance Agreement for Power Facilities Driveway Permit for Construction Within The County Right-of-Way Limits (Commercial) Driveway Permit for Construction within the County Right of Way Limits (Residential) Permit for The Use of The County Highway Right-of-Way Special Hauling Permit Road Bond Form

    Source Carroll County OH Engineer page · page 1 · version 2023-06-05

    May be cited on the cut-off date.

    Quoted from the law, page 10
    No person, partnership, or corporation shall erect, within the bounds of any highway or on the bridges or culverts thereon, any obstruction without first obtaining the approval of the board in case of highways other than roads and highways on the state highway system and the bridges and culverts thereon.

    Source ORC 4513.34 5515 5547.04 5571.16 roads · page 10 · version 2023-08-01

    In force from 1953-10-01 to 2026-10-03, section 5547.04

    5547.04: version effective 1953-10-01, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 20
    No public agency or political subdivision of this state may require any approval, consent, permit, certificate, or other condition for the construction or operation of a major utility facility or economically significant wind farm authorized by a certificate issued pursuant to Chapter 4906. of the Revised Code.

    Source ORC 4906 Power Siting Board · page 20 · version 2023-08-01

    In force from 2019-10-22 to 2026-10-03, section 4906.13

    4906.13: version effective 2019-10-22, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 12
    (4) The applicant shall list all transportation permits required for construction and operation of the project, and describe any necessary coordination with appropriate authorities for temporary or permanent road closures, lane closures, road access restrictions, and traffic control necessary for construction and operation of the proposed facility.

    Source OAC 4906 4 OPSB generation facility applications · page 12 · version 2023-08-01

    In force from 2015-12-11 to 2024-05-29, section 4906-4-06

    4906-4-06: version effective 2015-12-11; first change after it 2024-05-30 (OPSB Case 21-902-GE-BRO (determination 2023-07-20); chapter 4906-4 restructured (formerly generation chapter merged with 5)), from codes.ohio.gov version history in archive captures (confirmed_two_sources)

    May be cited on the cut-off date.

  • County special hauling permit for oversize or overweight loads (county roads; township trustees to be contacted for township roads)

    CCO-HAUL · Carroll County Engineer and Board of County Commissioners (county roads); township trustees (township roads)

    Applicability
    Likely
    Instrument
    Carroll County Special Hauling Permit (rev. 05/2020) with road bond form; ORC 4513.34
    Trigger
    Heavy hauling, meaning a vehicle or load above the legal size or weight, on county roads; the township trustees must also be contacted for township roads.
    Description

    Heavy hauling over county roads needs an approved Special Hauling Permit before any hauling starts, at no charge; the township trustees must be contacted for township roads. A bond of at least $25,000 per mile is required, with the County Commissioners listed as obligee, and a separate Shared Road Use Maintenance Agreement may be required where a road already has one. From December 1 to May 15 legal load limits on county and township roads fall 25% and heavy hauling may be permitted only when the roadway is frozen. The County Engineer prices road damage and bills it, and the bond is returned or transferred by the road's condition after hauling. ORC 4513.34 has local authorities issue special heavy hauling permits for loads above the legal size or weight. ORC 4906.13(B) bars a political subdivision from requiring 'any approval, consent, permit, certificate, or other condition' for an OPSB-certificated facility; the sources do not settle whether that reaches this permit.

    Typical timeline

    No review period is stated in the sources; legal load limits fall 25% from December 1 to May 15, and heavy hauling in that period may be permitted only when the roadway is frozen and the County Engineer's Office is contacted before each haul.

    As of the cut-off

    As of the cut-off: ORC 4906.13 (No local jurisdiction) took effect in the version in force on 2023-08-01 (House Bill 6, 133rd General Assembly). (2019-10-22)

    Verification
    PACK_PENDING_QUALIFIED_REVIEW
    Source
    pack:oh_carroll_county.json
    In the permit matrix
    CCO-HAUL
    Legal basis: 8 quotes from dated law
    Quoted from the law, page 1
    All heavy hauling operations using county roads must obtain an approved “Special Hauling Permit” before starting any hauling. There is no charge for the permit. The appropriate Township Trustees must also be contacted before hauling on township roads.

    Source Carroll County OH Engineer Special Hauling Permit 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    Township Trustee lists are available at the County Engineer’s Office. A minimum $25,000.00 per mile bond will be required.

    Source Carroll County OH Engineer Special Hauling Permit 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    During the period of high soil moisture and potential freeze/thaw cycles, the legal load limits on all county and township roads are reduced 25%. The load reduction period, set by the Carroll County Commissioners, is between December 1 and May 15.

    Source Carroll County OH Engineer Special Hauling Permit 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    Heavy hauling may only be permitted when the roadway is frozen during the Frost Law Period. The company must contact the County Engineer’s Office each time they are planning any heavy hauling during the Frost Law Period.

    Source Carroll County OH Engineer Special Hauling Permit 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    The normal bond during the Frost Law Period is $25,000 per mile surety bond and the Carroll County Commissioners shall be listed as obligees on the bond. In the event that any road on the route has a current Road Use Maintenance Agreement, a separate Shared Road Use Maintenance Agreement may be required.

    Source Carroll County OH Engineer Special Hauling Permit 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    The bond will be returned to the company or transferred to another permit in whole or in part depending on the condition of the road after all hauling is completed. The County Engineer will determine the cost to repair any road damage found and bill the company.

    Source Carroll County OH Engineer Special Hauling Permit 2022 04 · page 1 · version 2022-06-29

    May be cited on the cut-off date.

    Quoted from the law, page 1
    local authorities with respect to highways under their jurisdiction, upon application in writing, shall issue a special regional heavy hauling permit authorizing the applicant to operate or move a vehicle or combination of vehicles as follows: (a) At a size or weight of vehicle or load exceeding the maximum specified in sections 5577.01 to 5577.09 of the Revised Code

    Source ORC 4513.34 5515 5547.04 5571.16 roads · page 1 · version 2023-08-01

    In force from 2023-06-30 to 2026-10-03, section 4513.34

    4513.34: version effective 2023-06-30, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

    Quoted from the law, page 20
    No public agency or political subdivision of this state may require any approval, consent, permit, certificate, or other condition for the construction or operation of a major utility facility or economically significant wind farm authorized by a certificate issued pursuant to Chapter 4906. of the Revised Code.

    Source ORC 4906 Power Siting Board · page 20 · version 2023-08-01

    In force from 2019-10-22 to 2026-10-03, section 4906.13

    4906.13: version effective 2019-10-22, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

  • Road use agreement and pre-construction video survey for Fescue Road

    L-01 · Harrison Township Trustees

    Applicability
    Required
    Instrument
    Township road use agreement
    Trigger
    Hauling on Fescue Road or other township roads.
    Description

    The trustees issue no permit but want a road use agreement and a video survey. They must be contacted before hauling. Fescue Road is a 16-foot chip-and-seal road with two 90-degree turns needing temporary widening for tractor-trailers.

    Typical timeline
    The pack gives no timeline.
    As of the cut-off

    As of 2023-07-06.

    Verification
    DATA_ROOM_EVIDENCED
    Source
    model:jurisdiction
    Basis
    C-c099b1879f (no record in the annex), C-a8a3394ea1, C-849c3eb33d (no record in the annex), C-8172eb7213
    In the permit matrix
    L-01

    No citation of law for this item.

  • Subdivision approval (no-plat minor subdivision or plat) if the project divides parcels, for example a substation parcel conveyed to a utility

    CCO-SUBDIV · Carroll County Regional Planning Commission

    Applicability
    Conditional
    Instrument
    Carroll County Subdivision Regulations (originally adopted 1973-02-26; revision effective 2017-08-16), enacted under ORC Chapter 711
    Trigger
    Dividing a parcel into lots or pieces, any one under five acres, for transfer of ownership, for example a lot split or a substation parcel conveyed to a utility.
    Description

    The regulations apply to dividing a parcel into lots, any one of which is under five acres; a division into parcels of more than five acres with no new street or access easement is outside them. A division of no more than five lots along an existing public street, with no new street, may be submitted for approval without a plat; staff approve or deny within seven full working days, and that approval does not relieve the applicant of Health District or County Engineer requirements. Other divisions go through the plat process, in which the Commission acts on a final plat within 30 days or it is deemed approved. Land within three miles of a city or one and one-half miles of a village that has enacted platting jurisdiction is carved out, so check municipal platting there. ORC 4906.13(B) bars a political subdivision from requiring 'any approval, consent, permit, certificate, or other condition' for an OPSB-certificated facility; the sources do not settle whether that reaches platting of land conveyed to a utility.

    Typical timeline

    No-plat minor subdivision: approved or denied within seven full working days after submission. Final plat: acted on within 30 days after filing, otherwise deemed approved.

    As of the cut-off

    As of the cut-off: Subdivision regulations originally adopted (revision page of the regulations). (1973-02-26) Regulations revised; the revision page lists approval by the County Commissioners on 2017-06-01 and by the Regional Planning Commission on 2017-08-15. (2017-07-10) Effective date handwritten on the cover, read from the page image; the OCR text garbles it as 'August iv, 20/7'. (2017-08-16) ORC 4906.13 (No local jurisdiction) took effect in the version in force on 2023-08-01 (House Bill 6, 133rd General Assembly). (2019-10-22)

    Verification
    PACK_PENDING_QUALIFIED_REVIEW
    Source
    pack:oh_carroll_county.json
    In the permit matrix
    CCO-SUBDIV
    Legal basis: 8 quotes from dated law
    Quoted from the law, page 9
    Divisions of land subject to the provisions of these regulations are: 1. The division of any parcel into two or more lots, or pieces, any one of which is less than five (5) acres.

    Source Carroll County OH Subdivision Regulations adopted 2017 08 16 OCR · page 9 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 9
    Division of land not subject to the provisions of these regulations are: 1. The division of land into parcels of more than five (5) acres each not involving any new streets, roads, or easements of access.

    Source Carroll County OH Subdivision Regulations adopted 2017 08 16 OCR · page 9 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 9
    The subdivision of land located in the unincorporated areas of the County except the territory which is within three (3) miles of the corporate limits of a city or within one and one-half 1-1/2) miles of the corporate limits of a Village, either of which has enacted platting jurisdiction

    Source Carroll County OH Subdivision Regulations adopted 2017 08 16 OCR · page 9 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 17
    is proposed along an existing public street, not involving the opening, widening or extension of any street or road, and involving no more than five (5) lots including the original tract, the said subdivision may be submitted to the Commission for approval without a plat.

    Source Carroll County OH Subdivision Regulations adopted 2017 08 16 OCR · page 17 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 17
    If the Commission, acting through its staff, is satisfied that such proposed subdivision is not contrary to applicable platting, subdividing or zoning regulations, it shall within seven(7) full working days after submission approve or deny such proposed subdivision.

    Source Carroll County OH Subdivision Regulations adopted 2017 08 16 OCR · page 17 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 62
    IMPORTANT: Minor Subdivision approval is provided for convenience. It does not in any way relieve the applicant from meeting all lawful regulations, including but not limited to the requirements of the Carroll County Subdivision Regulations, Carroll County Health District and the Carroll County Engineer.

    Source Carroll County OH Subdivision Regulations adopted 2017 08 16 OCR · page 62 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 21
    Commission: Acts on Final Plat - Gives approval or disapproval along with reasons for refusal in writing within thirty (30) days after plat has been officially filed, otherwise, said plat shall be deemed to have been approved.

    Source Carroll County OH Subdivision Regulations adopted 2017 08 16 OCR · page 21 · version 2022-03-22

    May be cited on the cut-off date.

    Quoted from the law, page 20
    No public agency or political subdivision of this state may require any approval, consent, permit, certificate, or other condition for the construction or operation of a major utility facility or economically significant wind farm authorized by a certificate issued pursuant to Chapter 4906. of the Revised Code.

    Source ORC 4906 Power Siting Board · page 20 · version 2023-08-01

    In force from 2019-10-22 to 2026-10-03, section 4906.13

    4906.13: version effective 2019-10-22, still the current version when the page map was checked (2026-10-03)

    May be cited on the cut-off date.

Also in the permit matrix for this row: OH-DECOM, OH-PILOT, OH-ROAD, OH-DITCH, OH-SETBACK, CCO-CULVERT, CCO-PLAN

Information requests

  • IR-f2153419ed · High priority

    Provide the permitting plan or schedule for the project area, or confirm none exists.

    Missing evidence
    Permitting plan or schedule
    Consequence
    Local Zoning & Permitting is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

Next steps

  • Track the commissioners' decision on the prohibition petition and confirm no restricted-area resolution is adopted.
  • Engage the county, township trustees and county engineer on road use agreements, bond and driveway permits.
  • Confirm whether the PJM exemption in SB 52 Section 4 applies.

Agencies

  • Carroll County
  • OPSB
  • Carroll County Engineer
  • Harrison Township Trustees

Cost and impact

Impact
C, S
Potential cost level
M-H
Why

Contested discretionary county process with schedule exposure (staff cite 9 to 14 months for opposed cases), plus road bond and agreements.

Impact: C = cost, S = schedule. Potential cost level: L, L-M, M, M-H, H (relative to a utility-scale solar budget).