C-4126d05ae5 · Page 1 of 1 · DR-0001 · 2023-06-12

The claim, in the assessor's words

OPSB pre-application conference was held March 21, 2023, and the county public meeting May 11, 2023.

Quoted from page 1
The pre-application conference with OPSB staff was held on March 21, 2023, and the county public meeting required by ORC 303.61 was held on May 11, 2023.

Source developer_document · Claim type schedule · Polarity neutral · Confidence high · Quote check exact, 100 of 100

Cited by PE-02 State Jurisdiction · Filed under PE-01, PE-02

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as docx

Go to the marked quote

Northfold Energy Partners, LLC - Confidential Tamsin Ridge Solar and Storage Project Project Description, Revision 3. Prepared by Northfold Energy Partners, LLC. June 12, 2023. 1. Overview The Tamsin Ridge Solar and Storage Project (the Project) is a proposed 120 MW (AC) solar photovoltaic generating facility of approximately 168 MW (DC) with a co-located 60 MW / 240 MWh battery energy storage system (BESS). Northfold Energy Partners, LLC is developing the Project through its project company, Tamsin Ridge Solar, LLC. The Project is in Harrison Township, Carroll County, Ohio, west of State Route 43 and about 4 miles northwest of the Village of Carrollton. 2. Site The Project Area covers approximately 1,140 acres on 14 parcels held by 9 landowners. The fenced area is approximately 780 acres, in a West Block and an East Block separated by the Sallow Creek valley. Land cover is cropland and hay with woodlots along Sallow Creek and on reclaimed surface-mined ground in the East Block. An existing 138 kV transmission line crosses the West Block, and natural gas gathering pipelines cross Parcels 5, 7 and 10. There are 23 residences within 1,000 feet of the fence. 3. Facility Single-axis trackers; 40 central inverters of 3.0 MW each; a 34.5/138 kV project substation and the BESS yard (about 6 acres, 60 lithium iron phosphate enclosures) on Parcel 5; underground 34.5 kV collection lines; about 9 miles of gravel access roads; perimeter fencing; and an operations building. Modules carry a hail impact rating and the trackers have an automatic hail stow mode. Structures are designed for an ASCE 7-16 basic wind speed of 115 mph and a 20 psf ground snow load. 4. Interconnection PJM queue position AH1-931; the interconnection request was submitted on September 24, 2021. The point of interconnection is the proposed Tamsin Ridge 138 kV switching station on the Transmission Owner's Vesper Hill-Ardley 138 kV line, reached by a 0.4-mile 138 kV gen-tie line. PJM issued the Feasibility Study report on April 14, 2022. The position is now in PJM's transition to its reformed interconnection process, and the next study phase has not started. 5. Permitting and schedule The Project needs a certificate of environmental compatibility and public need from the Ohio Power Siting Board (OPSB). Quote starts. The pre-application conference with OPSB staff was held on March 21, 2023, and the county public meeting required by ORC 303.61 was held on May 11, 2023. Quote ends. The OPSB application is planned for the third quarter of 2023, construction from the first quarter of 2025, and commercial operation in December 2026. No federal land, federal funding or federal loan program is involved. A U.S. Army Corps of Engineers nationwide permit is expected for one access road crossing of an ephemeral stream. 6. Site control Option-to-lease agreements cover 12 parcels, a recorded collection line easement covers Parcel 7, and Parcel 11 is not yet under agreement (see the Option and Lease Summary and the Parcel Schedule).

The page

This document has no page picture (only PDF and image documents have one).

Other claims quoted on this page

  • C-9d4b1ab8e4

    Land cover is cropland and hay with woodlots along Sallow Creek and on reclaimed surface-mined ground in the East Block.

  • C-ad2c42da82

    An existing 138 kV transmission line crosses the West Block.

  • C-ffd9a025a0

    There are 23 residences within 1,000 feet of the fence.

  • C-387e001e3f

    Interconnection is in PJM.

  • C-a21ca05339

    Interconnection voltage is 138 kV via a 0.4-mile gen-tie.

  • C-502eff95b5

    The position is in PJM's transition to its reformed process and the next study phase has not started.

  • C-857993e699

    The Project needs an OPSB certificate of environmental compatibility and public need.

  • C-01ec477e4b

    No federal land, funding or federal loan program is involved.

  • C-441acfa155

    A USACE nationwide permit is expected for one access road crossing of an ephemeral stream.

  • C-1f788fe1e5

    Option-to-lease agreements cover 12 parcels and a recorded collection line easement covers Parcel 7.