Skip to content

Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project

C-6a69538071 · Page 3 of 3 · DR-0018 · 2023-05-15

The claim, in the assessor's words

Excluding the undermined area removes about 165 of 240 fenced East Block acres, roughly 20 to 25 MW of capacity.

Quoted from page 3
about 165 acres of the 240 fenced acres in the East Block, or roughly 20 to 25 MW of the Project's capacity

Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

Cited by EN-02 Geotechnical and Soils · Filed under EN-02, PE-04

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

Preliminary Geotechnical Engineering Report - Tamsin Ridge Recommendations Mine area. Either (a) exclude arrays and equipment from the undermined area (Quote starts. about 165 acres of the 240 fenced acres in the East Block, or roughly 20 to 25 MW of the Project's capacity Quote ends.), or (b) carry out a mine subsidence investigation before final design: 12 or more additional borings to the coal, downhole camera logging and a geophysical survey, followed by a grouting program under any area kept in the layout. Grouting of shallow workings typically costs several million dollars for an area of this size and takes 4 to 8 months. Option (b) still leaves residual risk. Foundations. Design driven W6x9 or W6x12 piles for 8 to 10 feet of embedment, with pre-drilling and grouted piles where refusal is met. Add a corrosion allowance or galvanizing for a 35-year life. Substation and BESS foundations may bear on stiff clay or rock at 3 to 4 feet below grade, outside the mine area and after the Phase II environmental sampling at the former tank battery. Access roads and grading. Use 12 inches of crushed aggregate over geotextile on the silty clay. Avoid cuts deeper than 3 feet on the Sallow Creek valley walls. Strip and stockpile topsoil separately; the soil survey maps most of the West Block as prime farmland. Further work. Final design needs borings at the substation, BESS yard and switching station, thermal resistivity tests along the collection routes, and the mine investigation above. Tobias Wren, P.E., Principal Geotechnical Engineer, Graywacke Geotechnical, LLC. Graywacke Geotechnical, LLC - Project G23-0219 Page 3 of 3

The page

The outline marks where the quote begins on the page.

Page 3 of Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project

Other claims quoted on this page

  • C-1efb994b8f

    Grouting of shallow workings typically costs several million dollars and takes 4 to 8 months; option (b) still leaves residual risk.

  • C-94c3a5488e

    Substation and BESS foundations are recommended after Phase II environmental sampling at the former tank battery.

Lumerian Labs 2026