EN-02 · Matrix · Environmental Resources

Rating
2Impacts likely but may be easily resolved
Why
Impact likely
Worst case
Up to3Resource is present, likely difficult to address
Evidence
Verified
Cited claims
21
Requirements
0
Requests
1

Rating

2Impacts likely but may be easily resolved

up to3Resource is present, likely difficult to address

The engine shows this rating as 2-3

The rule

Code computed the rating from the assessor's inputs:

impact_likely=yes -> 2

Set by the rule

Decision
Released with flags
The engine's reasons
  • Agencies not in the register or the evidence: OPSB
Evidence state
Verified · field study or agency determination

Worst case

If what is pending at the cut-off went badly, the same rule gives a higher rating.

Scenario

Investigation finds void-prone shallow-cover ground more widespread than the mapped 165 acres, removing a larger share of the buildable area or requiring extensive grouting.

Step still pending
Detailed mine-void investigation
Inputs in the worst case
Extent core · Avoidable partly · Pathway standard · Impact likely yes
The rule on the worst case
worst case: extent=core, avoidable=partly -> 3
Claims that make it plausible
C-324cdd0ed0, C-e538cf508c, C-d106c90db2, C-1efb994b8f

Revision

First verdict
weakened
First critique

The assessment is largely well supported, and the category 2 result holds. However, the claim that the mine map is incomplete and may extend west is not backed by the cited quotes, and the worst case relies on it. The 9-acre pad overlap is wording-level.

Revised once after the first critique. Rating unchanged.

The five inputs

Comments

Abandoned Elsby No. 2 underground mine lies beneath approximately 165 acres of the East Block; borings hit voids and two mine-subsidence sinkholes are on Parcel 10. Geotechnical consultant rates further sinkhole probability high over shallow workings. Two plugged wells on site; seismic hazard is low.

Critique

Verdict
upheld
Suggested direction for the rating
same
Summary

The assessment is well supported by the cited quotes. Presence, partial avoidability, a standard pathway and a likely impact (category 2) all follow the evidence. Only minor issues: an overreaching statement on faults, an extent judgment call, and a few omitted next steps.

Critic model
Luminol

Issues

  1. Severity minor · Kind unsupported_statement

    "Seismic hazard is low, so faults are not an issue" goes beyond C-560f40e113. Low seismic hazard does not show that no faults are present. The row should say faults are unaddressed, or that no fault claim exists.

    Cites C-560f40e113

  2. Severity minor · Kind missed_counter_evidence

    The extent rationale omits the consultant's statement that the mine is "the main geotechnical constraint on the Project" (C-324cdd0ed0). It also divides the 165 acres by 780 buildable acres, but no claim says the 165 acres lie inside the buildable area. The loss of 20 to 25 MW is roughly 17 to 21% of 120 MW, which supports peripheral. A mine-void investigation or a layout overlay would settle it.

    Cites C-d106c90db2, C-324cdd0ed0, C-6a69538071

  3. Severity minor · Kind missing_next_step

    The assessment does not say to coordinate the OPSB-requested geotechnical report (C-eaec90390e) with ODNR mine review. It also leaves out monitoring and repair of the two existing sinkholes on Parcel 10.

    Cites C-eaec90390e, C-03c910d4d1, C-e98a4f0f1c

Checks

  • Passed

    rating_has_evidence · blocking

  • Passed

    presence_is_evidenced · not blocking

  • Passed

    counter_evidence_considered · not blocking

  • Passed

    numbers_grounded · not blocking

  • Failed

    agencies_grounded · not blocking

    Agencies not in the register or the evidence: OPSB

  • Passed

    cutoff_respected · blocking

  • Passed

    critic_not_refuted · blocking

Evidence (21)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

Arrow keys move the selection. A middle-click opens the claim's own page.

  1. ODNR comments on wildlife, wetlands and mines are typically made conditions of the certificate.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  2. Grouting of shallow workings typically costs several million dollars and takes 4 to 8 months; option (b) still leaves residual risk.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 3Exact
  3. Structures should be kept at least 100 feet from plugged wells and follow the operator's setbacks from the pad and flowlines.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  4. Two plugged and abandoned oil and gas wells (Parcels 4 and 10) and an active horizontal Utica well pad adjoining Parcel 5 were located.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  5. One small landslide scar was seen on Parcel 12.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  6. Sinkhole-type subsidence is most likely where cover is under about 100 feet, which applies over the whole undermined area; this is the main geotechnical constraint.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  7. Hydric soil indicators were present in all five delineated wetlands.Wetland and Stream Delineation Report - Tamsin Ridge Solar and Storage Project · Page 2Exact
  8. Northfold will keep the undermined area out of the layout unless the mine investigation shows it is safe.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  9. Seismic site class C; seismic hazard is low.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  10. Graywacke considers the probability of further sinkholes over the operating life to be high over the shallow workings; the mine map is incomplete and true limit may reach further west.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 2Exact
  11. Excluding the undermined area removes about 165 of 240 fenced East Block acres, roughly 20 to 25 MW of capacity.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 3Exact
  12. No severed mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found.Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · Page 3Exact
  13. Two plugged and abandoned oil and gas wells are within the project area, and an active horizontal Utica well pad adjoins it.ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477) · Page 1Exact
  14. Mine subsidence is possible over abandoned underground workings.ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477) · Page 1Exact
  15. ODNR maps show the abandoned Elsby No. 2 underground coal mine beneath approximately 165 acres of the East Block (Parcels 9, 10 and 12).Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  16. Records show abandoned underground Elsby No. 2 Mine beneath the eastern part of the project area, plus pre-1977 reclaimed surface mining.ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477) · Page 1Exact
  17. Borings B-17 and B-19 dropped through voids and collapsed rubble at 61 and 74 feet.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  18. Two closed depressions on Parcel 10 are mine subsidence features (sinkholes).Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 1Exact
  19. A geotechnical report must address an abandoned underground mine in the East Block.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  20. The substation, BESS yard and inverters must not be built over the undermined area.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 2Exact
  21. Blasting is not expected.Noise Assessment - Tamsin Ridge Solar and Storage Project · Page 3Exact

OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project

C-03c910d4d1 · Page 2 of 2 · DR-0026

Open the claim, C-03c910d4d1

ODNR comments on wildlife, wetlands and mines are typically made conditions of the certificate.

Quote check Exact · Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own. · Read as native

OPSB Pre-Application Conference Summary - Tamsin Ridge 4. Process and timing The pre-application notification letter must be filed at least 15 days before the public informational meeting, which must be held in the project area no more than 90 days before the application. After the application is filed, the chairman accepts it as complete or rejects it within 60 days, and the hearing is set 60 to 90 days after a complying application is received. Staff indicated that solar cases with active local opposition have recently taken 9 to 14 months from filing to decision. Planned sequence: county public meeting in May 2023; public informational meeting after the 90-day period that follows the county meeting; application filing in the third quarter of 2023; decision expected in 2024. 5. State permits outside the certificate Staff reminded the team that Ohio EPA construction stormwater coverage, any Section 401 certification or isolated wetland permit, and ODOT hauling and access permits are obtained separately, and that Quote starts. ODNR comments on wildlife, wetlands and mines are typically made conditions of the certificate. Quote ends. 6. Action items • Northfold: schedule and notice the county public meeting under ORC 303.61. • Northfold: complete the noise study, the geotechnical mine investigation plan and the emergency plan before the public informational meeting. • Whitlock Ames: prepare the pre-application notification letter and the public notices. • Whitlock Ames: monitor the Board of County Commissioners' agenda for any ORC 303.58 or 303.62 resolution. Prepared by Whitlock Ames LLP for its client. Privileged and confidential. Whitlock Ames LLP - privileged Page 2 of 2

The outline marks where the quote begins on the page.

Page 2 of OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project
  1. C-03c910d4d1

    ODNR comments on wildlife, wetlands and mines are typically made conditions of the certificate.

    Quoted from page 2
    ODNR comments on wildlife, wetlands and mines are typically made conditions of the certificate.

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 2 · 2023-03-28

    Source agency_determination · Claim type agency_position · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Cited by EC-01 · Filed under AQ-01, EC-01, EN-02, PE-02

  2. C-1efb994b8f

    Grouting of shallow workings typically costs several million dollars and takes 4 to 8 months; option (b) still leaves residual risk.

    Quoted from page 3
    Grouting of shallow workings typically costs several million dollars for an area of this size and takes 4 to 8 months.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 3 · 2023-05-15

    Source consultant_memo · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100

  3. C-28570f896a

    Structures should be kept at least 100 feet from plugged wells and follow the operator's setbacks from the pad and flowlines.

    Quoted from page 1
    Keep structures at least 100 feet from plugged wells, and follow the operator's setbacks from the pad and its flowlines.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Cited by EN-01 · Filed under EN-01, EN-02

  4. C-2a9ce2a49f

    Two plugged and abandoned oil and gas wells (Parcels 4 and 10) and an active horizontal Utica well pad adjoining Parcel 5 were located.

    Quoted from page 1
    Two plugged and abandoned oil and gas wells (Parcels 4 and 10) and an active horizontal Utica well pad adjoining Parcel 5 were located.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  5. C-2b0121cadd

    One small landslide scar was seen on Parcel 12.

    Quoted from page 1
    one small landslide scar was seen on Parcel 12.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  6. C-324cdd0ed0

    Sinkhole-type subsidence is most likely where cover is under about 100 feet, which applies over the whole undermined area; this is the main geotechnical constraint.

    Quoted from page 1
    This is the main geotechnical constraint on the Project.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

  7. C-440f326a24

    Hydric soil indicators were present in all five delineated wetlands.

    Quoted from page 2
    Hydric soil indicators (depleted matrix, redox dark surface) were present in all five wetlands.

    Wetland and Stream Delineation Report - Tamsin Ridge Solar and Storage Project · DR-0013 · Page 2 · 2023-05-22

    Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under AQ-01, EN-02

  8. C-44efda80b8

    Northfold will keep the undermined area out of the layout unless the mine investigation shows it is safe.

    Quoted from page 1
    Keep the undermined area out of the layout unless the mine investigation shows it is safe.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type recommendation · Polarity presence · Confidence high · Quote check exact, 100 of 100

  9. C-560f40e113

    Seismic site class C; seismic hazard is low.

    Quoted from page 1
    Seismic site class C; seismic hazard is low.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-08 · Filed under EN-02, EN-08

  10. C-5c5e675182

    Graywacke considers the probability of further sinkholes over the operating life to be high over the shallow workings; the mine map is incomplete and true limit may reach further west.

    Quoted from page 2
    Graywacke considers the probability of further sinkholes over the operating life of the Project to be high over the shallow workings.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 2 · 2023-05-15

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

  11. C-6a69538071

    Excluding the undermined area removes about 165 of 240 fenced East Block acres, roughly 20 to 25 MW of capacity.

    Quoted from page 3
    about 165 acres of the 240 fenced acres in the East Block, or roughly 20 to 25 MW of the Project's capacity

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 3 · 2023-05-15

    Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under EN-02, PE-04

  12. C-9dcc852809

    No severed mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found.

    Quoted from page 3
    No mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found severed.

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 3 · 2023-04-18

    Source public_record · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-05 · Filed under EN-02, PE-05

  13. C-a3cebd779c

    Two plugged and abandoned oil and gas wells are within the project area, and an active horizontal Utica well pad adjoins it.

    Quoted from page 1
    two plugged and abandoned oil and gas wells within the project area and an active horizontal Utica well pad adjoining it.

    ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477) · DR-0011 · Page 1 · 2023-05-02

    Source agency_determination · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-01 · Filed under EN-01, EN-02

  14. C-caad69ed74

    Mine subsidence is possible over abandoned underground workings.

    Quoted from page 1
    Mine subsidence is possible over abandoned underground workings.

    ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477) · DR-0011 · Page 1 · 2023-05-02

    Source agency_determination · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  15. C-d106c90db2

    ODNR maps show the abandoned Elsby No. 2 underground coal mine beneath approximately 165 acres of the East Block (Parcels 9, 10 and 12).

    Quoted from page 1
    beneath approximately 165 acres of the East Block (Parcels 9, 10 and 12)

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source consultant_memo · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-01 · Filed under EG-01, EN-02

  16. C-d9db0a1832

    Records show abandoned underground Elsby No. 2 Mine beneath the eastern part of the project area, plus pre-1977 reclaimed surface mining.

    Quoted from page 1
    Division records show abandoned underground coal mining, the Elsby No. 2 Mine in the Upper Freeport (No. 7) coal, beneath the eastern part of the project area

    ODNR Environmental Review - Tamsin Ridge Solar and Storage Project (ODNR 23-0477) · DR-0011 · Page 1 · 2023-05-02

    Source agency_determination · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-01 · Filed under EN-01, EN-02

  17. C-e538cf508c

    Borings B-17 and B-19 dropped through voids and collapsed rubble at 61 and 74 feet.

    Quoted from page 1
    Borings B-17 and B-19 dropped through voids and collapsed rubble at 61 and 74 feet.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  18. C-e98a4f0f1c

    Two closed depressions on Parcel 10 are mine subsidence features (sinkholes).

    Quoted from page 1
    Two closed depressions, 12 and 20 feet across, on Parcel 10 are mine subsidence features (sinkholes).

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100

  19. C-eaec90390e

    A geotechnical report must address an abandoned underground mine in the East Block.

    Quoted from page 1
    A geotechnical report addressing the abandoned underground mine in the East Block.

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-01, EN-02

  20. C-f29a379025

    The substation, BESS yard and inverters must not be built over the undermined area.

    Quoted from page 2
    The substation, the BESS yard and the inverters must not be built over the undermined area.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 2 · 2023-05-15

    Source consultant_memo · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-04 · Filed under EG-04, EN-02

  21. C-fd52f76b29

    Blasting is not expected.

    Quoted from page 3
    Blasting is not expected;

    Noise Assessment - Tamsin Ridge Solar and Storage Project · DR-0016 · Page 3 · 2023-07-10

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-03 · Filed under CO-03, EN-02

Requirements and permits

The requirements the assessor tied to this row, by level. Each quote from dated law is shown with its source.

No requirement is tied to this row.

Information requests

  • IR-66c5dc2424 · Medium priority

    Provide the karst, mine or oil and gas well mapping for the project area, or confirm none exists.

    Missing evidence
    Karst, mine or oil and gas well mapping
    Consequence
    Geotechnical and Soils is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

Next steps

  • Keep the undermined area out of the layout, with no substation, BESS or inverters over it; commission a mine-void investigation to confirm its limits.
  • Survey, fence and set back plugged wells; coordinate pad setbacks with the operator and ODNR.
  • Compare grouting cost against capacity loss.

Agencies

  • ODNR
  • OPSB

Cost and impact

Impact
C, S
Potential cost level
M-H
Why

Grouting typically costs several million dollars and takes 4 to 8 months (C-1efb994b8f). Excluding the area loses roughly 20 to 25 MW (C-6a69538071). Further geotechnical investigation and well setbacks add cost.

Impact: C = cost, S = schedule. Potential cost level: L, L-M, M, M-H, H (relative to a utility-scale solar budget).