Skip to content

Traffic and Access Memo - Tamsin Ridge Solar and Storage Project

C-1af8ef8e00 · Page 2 of 2 · DR-0020 · 2023-06-19

The claim, in the assessor's words

Carroll County requires a special hauling permit, a bond of at least $25,000 per mile, and a Roadway Use and Maintenance Agreement.

Quoted from page 2
a bond of at least $25,000 per mile, with the Board of County Commissioners as obligee, and a Roadway Use and Maintenance Agreement for Power Facilities.

Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by PE-01 Local Zoning & Permitting · Filed under EG-03, PE-01

On the page

The page text exactly as the engine read it, with the quote marked.

Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own.

Read as native

Go to the marked quote

Traffic and Access Memo - Tamsin Ridge 3. Permits and agreements • ODOT special hauling permits for loads on State Route 43, and an ODOT access permit if any entrance is added on the state route (none is planned). • Carroll County Engineer special hauling permit before any heavy hauling on county roads; no charge, but Quote starts. a bond of at least $25,000 per mile, with the Board of County Commissioners as obligee, and a Roadway Use and Maintenance Agreement for Power Facilities. Quote ends. • Township trustees to be contacted before hauling on township roads; a road use agreement with Harrison Township for Fescue Road. • Driveway permits for the four entrances from the Board of County Commissioners through the County Engineer, with the temporary-access option for construction entrances. • A county right-of-way permit for any collection line in the Linnet Road right-of-way. Seasonal limits. From December 1 to May 15, legal load limits on county and township roads are reduced by 25 percent, and heavy hauling may be allowed only when the ground is frozen. Heavy deliveries should be scheduled outside that period. Road condition. Pre-construction and post-construction road condition surveys with video will be made on every road in the haul route. The County Engineer prices any damage and bills it against the bond. If the Project seeks the qualified energy project tax exemption, ORC 5727.75 also requires it to repair roads, bridges and culverts affected by construction as the county engineer determines. 4. Traffic management A traffic management plan will set delivery hours (7:00 a.m. to 7:00 p.m., no deliveries on school bus routes during bus hours), flaggers at the entrances during peak hours, signs, and worker parking inside the site. No public road will be closed for more than one day at a time. Anika Tessmer, P.E., Project Engineer, Tessmer Coyle Engineering, Inc. Tessmer Coyle Engineering, Inc. - Job 2317 Page 2 of 2

The page

The outline marks where the quote begins on the page.

Page 2 of Traffic and Access Memo - Tamsin Ridge Solar and Storage Project

Other claims quoted on this page

  • C-4c5acf992f

    A county right-of-way permit is needed for any collection line in the Linnet Road right-of-way.

Lumerian Labs 2026