Traffic and Access Memo - Tamsin Ridge
3. Permits and agreements
• ODOT special hauling permits for loads on State Route 43, and an ODOT access permit if any entrance is
added on the state route (none is planned).
• Carroll County Engineer special hauling permit before any heavy hauling on county roads; no charge, but a
bond of at least $25,000 per mile, with the Board of County Commissioners as obligee, and a Roadway Use and
Maintenance Agreement for Power Facilities.
• Township trustees to be contacted before hauling on township roads; a road use agreement with Harrison
Township for Fescue Road.
• Driveway permits for the four entrances from the Board of County Commissioners through the County
Engineer, with the temporary-access option for construction entrances.
• Quote starts. A county right-of-way permit for any collection line in the Linnet Road right-of-way. Quote ends.
Seasonal limits. From December 1 to May 15, legal load limits on county and township roads are reduced by 25
percent, and heavy hauling may be allowed only when the ground is frozen. Heavy deliveries should be
scheduled outside that period.
Road condition. Pre-construction and post-construction road condition surveys with video will be made on every
road in the haul route. The County Engineer prices any damage and bills it against the bond. If the Project seeks
the qualified energy project tax exemption, ORC 5727.75 also requires it to repair roads, bridges and culverts
affected by construction as the county engineer determines.
4. Traffic management
A traffic management plan will set delivery hours (7:00 a.m. to 7:00 p.m., no deliveries on school bus routes
during bus hours), flaggers at the entrances during peak hours, signs, and worker parking inside the site. No
public road will be closed for more than one day at a time.
Anika Tessmer, P.E., Project Engineer, Tessmer Coyle Engineering, Inc.
Tessmer Coyle Engineering, Inc. - Job 2317 Page 2 of 2