Skip to content

Site Control and Land Rights

PE-05 · Matrix · Additional Permitting

Rating
3Resource is present, likely difficult to address
Why
Core of the site; partly avoidable
Worst case
Not above the rating
Evidence
Reported
Cited claims
20
Requirements
0
Requests
2

Rating

3Resource is present, likely difficult to address

The engine shows this rating as 3

The rule

Code computed the rating from the assessor's inputs:

extent=core, avoidable=partly -> 3

Set by the rule

Decision
Released with flags
The engine's reasons
  • Uncited absence claims to weigh: C-f77ef514cf (no record in the annex)
  • Numbers not found in cited evidence: 31.0
  • Agencies not in the register or the evidence: Carroll County
Evidence state
Reported · desktop, consultant or developer record

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

The Parcel 11 trustee holds out with no condemnation available, and Brenwick will not waive its second pad, removing array area and forcing a road right-of-way collection route and access redesign.

Step still pending
Parcel 11 negotiation and Brenwick accommodation agreement
Inputs in the worst case
Extent core · Avoidable partly · Pathway individual · Impact likely yes
The rule on the worst case
worst case (extent=core, avoidable=partly -> 3) not above the point

Revision

First verdict
weakened
First critique

Core and partly-avoidable inputs are reasonable, and Parcel 11 and Brenwick are well supported. Weakened by unsupported specifics: the 1.3-mile route, the 1912 date and no-liability coal wording, and 'well above appraisal'. The agencies are thin. Category 3 looks right.

Revised once after the first critique. Rating unchanged.

The five inputs

Comments

Options cover 12 of the 14 parcels (1,063.4 acres). Parcel 11 (31.0 acres) is unleased, needed for collection and East Block access; its trustee declined the option twice. Brenwick accommodation agreement is unsigned; its second pad overlaps about 9 acres of array. Parcel 9 SNDA and coal reservation remain open.

Critique

Verdict
upheld
Suggested direction for the rating
same
Summary

Assessment is largely supported by the cited quotes. Only minor issues: an unsupported Parcel 9 conservation easement mention, the unexplained 14th parcel, and a judgment-call extent. The uncited assignment clause does not weaken it.

Critic model
Luminol

Issues

  1. Severity minor · Kind unsupported_statement

    The impact_likely rationale mentions a Parcel 9 conservation easement rated under EN-07. No cited claim mentions it. Cite a claim or drop the sentence.

    Cites C-579694c789

  2. Severity minor · Kind missing_next_step

    Options cover 12 of 14 parcels and only Parcel 11 is named as uncontrolled. The 14th parcel's status is never explained. Parcel 7 may be easement-only. Confirm it and add option expiry dates against the December 2026 COD.

    Cites C-04c97c05c7, C-3ce7653be3

  3. Severity minor · Kind overstatement

    Extent 'core' is a judgment call. Parcel 11 is 31 acres and the pad overlap is about 9 acres, against 780 buildable acres. It rests on Parcel 11 being essential for the collection route and access. A confirmed Linnet Road route and an East Block access alternative would settle it. 'Holdout behaviour' is also an inference from a truncated quote.

    Cites C-3ce7653be3, C-61e6db1965, C-cd08e1f358

Checks

  • Passed

    rating_has_evidence · blocking

  • Passed

    presence_is_evidenced · not blocking

  • Failed

    counter_evidence_considered · not blocking

    Uncited absence claims to weigh: C-f77ef514cf (no record in the annex)

  • Failed

    numbers_grounded · not blocking

    Numbers not found in cited evidence: 31.0

  • Failed

    agencies_grounded · not blocking

    Agencies not in the register or the evidence: Carroll County

  • Passed

    cutoff_respected · blocking

  • Passed

    critic_not_refuted · blocking

Evidence (20)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

Arrow keys move the selection. A middle-click opens the claim's own page.

  1. Site control is through option-to-lease agreements on 12 of 14 parcels (1,063.4 acres) plus a recorded collection line easement on Parcel 7.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  2. Option-to-lease agreements cover 12 parcels and a recorded collection line easement covers Parcel 7.Tamsin Ridge Solar and Storage Project - Project Description · Page 1Exact
  3. No setback waivers have been requested because no local or state setback applies to the solar facility.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  4. Requires an SNDA from Carrow Savings Bank for the Parcel 9 mortgage.Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · Page 1Exact
  5. Coal beneath Parcel 9 was largely mined out by the Elsby No. 2 Mine.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  6. Parcel 11 (31 acres) is not under any agreement.Parcel Schedule 2023-07-14 · Page 2Exact
  7. Parcel 11 lies between the West and East Blocks; the planned collection route and East Block access road cross it.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  8. A county right-of-way permit is needed for any collection line in the Linnet Road right-of-way.Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · Page 2Exact
  9. A 1912 deed severed Parcel 9 coal and reserved the right to mine it by underground methods without liability for surface damage.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  10. The Parcel 11 trustee has declined the standard option twice and asked for a purchase price well above appraisal.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  11. The lessee's planned second pad on Parcel 2 overlaps about 9 acres of the array layout.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  12. Without Parcel 11, the collection line would follow Linnet Road right-of-way about 1.3 miles, needing a county right-of-way permit and adding cost.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  13. An accommodation agreement with Brenwick is in draft and not signed; until then a lender will see an unsubordinated surface use right.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  14. No severed mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found.Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · Page 3Exact
  15. Memoranda of the solar leases for Parcels 2, 5 and 9 must still be recorded.Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · Page 1Exact
  16. Parcel 11 (Okerlund Family Trust) has no agreement, in negotiation, and is needed for collection route and East Block access.Parcel Schedule 2023-07-14 · Page 1Exact
  17. The easement crosses the Calder Gathering Company natural gas gathering line, requiring the grantee to obtain a written crossing agreement and keep required clearance.Underground Collection Line Easement Agreement - Parcel 7 · Page 1Exact
  18. An oil and gas lease to Brenwick Exploration, with pooled unit, allows surface use for wells, pads, roads, pipelines and tanks on Parcels 2 and 5.Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · Page 2Exact
  19. No condemnation power is available to the Project.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 2Exact
  20. An accommodation agreement or partial surface release from Brenwick Exploration is required for oil and gas lease areas to be occupied by the solar facility; otherwise no affirmative coverage.Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · Page 1Exact

Option and Lease Summary - Tamsin Ridge Solar and Storage Project

C-04c97c05c7 · Page 1 of 2 · DR-0004

Open the claim, C-04c97c05c7

Site control is through option-to-lease agreements on 12 of 14 parcels (1,063.4 acres) plus a recorded collection line easement on Parcel 7.

Quote check Exact · Placed verbatim · The quote occurs on the page exactly as written. · Read as native

Northfold Energy Partners, LLC Development office: 88 East Broad Street, Suite 1400, Columbus, Ohio 43215 | northfold-energy.example Option and Lease Summary Tamsin Ridge Solar and Storage Project, Harrison Township, Carroll County, Ohio Prepared by the Northfold land team for Tamsin Ridge Solar, LLC. May 30, 2023. 1. Site control at a glance Tamsin Ridge Solar, LLC Quote starts. holds option-to-lease agreements on 12 of the 14 parcels (1,063.4 acres) and a Quote ends. recorded underground collection line easement on Parcel 7 (45.6 acres). Parcel 11 (31.0 acres, Okerlund Family Trust) is not under agreement. Each option was recorded by a memorandum of option in the Carroll County Recorder's office. Term Standard form (all 12 options) Option period 5 years from execution, with one 3-year extension on notice and payment Option payments Annual per-acre payment during the option period; credited against rent Lease term 35 years from the commercial operation date, with two 5-year renewals Rent Fixed annual rent per fenced acre with a 2% annual escalator; crop damage paid Use Solar generation, battery storage, substation, collection and gen-tie lines, roads Lessor reservations Hunting outside the fence; farming of unfenced land; oil and gas rights Decommissioning Lessee removes all facilities to a depth of 36 inches and restores the soil within 12 months after the lease ends; lessee posts security Drain tile Lessee repairs or reroutes tile damaged by construction Assignment Free assignment to affiliates and lenders; lender protections included 2. Status by landowner Landowner Parcels Acres Agreement Executed Varnum Farms LLC 1, 2 215.1 Option to lease Aug. 16, 2021 Jessamy and Corwin Strohl 3, 4 160.6 Option to lease Oct. 4, 2021 Hallorann Land Company LLC 5, 6 165.5 Option to lease Nov. 22, 2021 Delphine Asquith 7 45.6 Collection line easement Recorded Nov. 3, 2022 Bertrand and Ione Kellerman 8 79.8 Option to lease Jan. 18, 2022 Pettibone heirs (Ada Pettibone, trustee) 9, 10 210.0 Option to lease Feb. 7, 2022 Okerlund Family Trust 11 31.0 None; in negotiation - Marlis Thornbury 12, 13 155.2 Option to lease Mar. 29, 2022 Ruedell Partners LLC 14 77.2 Option to lease June 30, 2022 Northfold land team - privileged and confidential Page 1 of 2

The outline marks where the quote begins on the page.

Page 1 of Option and Lease Summary - Tamsin Ridge Solar and Storage Project
  1. C-04c97c05c7

    Site control is through option-to-lease agreements on 12 of 14 parcels (1,063.4 acres) plus a recorded collection line easement on Parcel 7.

    Quoted from page 1
    holds option-to-lease agreements on 12 of the 14 parcels (1,063.4 acres) and a

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 1 · 2023-05-30

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  2. C-1f788fe1e5

    Option-to-lease agreements cover 12 parcels and a recorded collection line easement covers Parcel 7.

    Quoted from page 1
    Option-to-lease agreements cover 12 parcels, a recorded collection line easement covers Parcel 7

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  3. C-2a27cb9782

    No setback waivers have been requested because no local or state setback applies to the solar facility.

    Quoted from page 2
    No setback waivers have been requested, because no local or state setback applies to the solar facility.

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-01 · Filed under PE-01, PE-05

  4. C-2a9dd4b09a

    Requires an SNDA from Carrow Savings Bank for the Parcel 9 mortgage.

    Quoted from page 1
    Record a subordination, non-disturbance and attornment agreement from Carrow Savings Bank as to the

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 1 · 2023-04-18

    Source public_record · Claim type constraint · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  5. C-343e9b9832

    Coal beneath Parcel 9 was largely mined out by the Elsby No. 2 Mine.

    Quoted from page 2
    The coal was largely mined out by the Elsby No. 2 Mine

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-02

  6. C-3ce7653be3

    Parcel 11 (31 acres) is not under any agreement.

    Quoted from page 2
    Not under agreement (Parcel 11, acres) | 31

    Parcel Schedule 2023-07-14 · DR-0005 · Page 2 · 2023-07-14

    Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  7. C-489cabb421

    Parcel 11 lies between the West and East Blocks; the planned collection route and East Block access road cross it.

    Quoted from page 2
    The planned collection route and

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence low · Quote check exact, 100 of 100

    Filed under EN-01, PE-05

  8. C-4c5acf992f

    A county right-of-way permit is needed for any collection line in the Linnet Road right-of-way.

    Quoted from page 2
    A county right-of-way permit for any collection line in the Linnet Road right-of-way.

    Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · DR-0020 · Page 2 · 2023-06-19

    Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EG-03, PE-05

  9. C-579694c789

    A 1912 deed severed Parcel 9 coal and reserved the right to mine it by underground methods without liability for surface damage.

    Quoted from page 2
    A 1912 deed severed the coal beneath Parcel 9 and reserved the right to mine it

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source public_record · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-02, PE-05

  10. C-61e6db1965

    The Parcel 11 trustee has declined the standard option twice and asked for a purchase price well above appraisal.

    Quoted from page 2
    The trustee has declined the standard option twice and asked for a

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02 · Filed under CO-02, PE-05

  11. C-7d33945087

    The lessee's planned second pad on Parcel 2 overlaps about 9 acres of the array layout.

    Quoted from page 2
    The lessee's planned second pad on Parcel 2 overlaps about 9 acres of the

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type presence · Polarity presence · Confidence low · Quote check exact, 100 of 100

    Cited by EN-01 · Filed under EN-01, EN-02, PE-05

  12. C-7dce4e6e67

    Without Parcel 11, the collection line would follow Linnet Road right-of-way about 1.3 miles, needing a county right-of-way permit and adding cost.

    Quoted from page 2
    the collection line would follow Linnet Road in the

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Filed under EG-03, PE-05

  13. C-9099731d6e

    An accommodation agreement with Brenwick is in draft and not signed; until then a lender will see an unsubordinated surface use right.

    Quoted from page 2
    in draft and not signed. Until it is, a lender will see an unsubordinated surface use right.

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

  14. C-9dcc852809

    No severed mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found.

    Quoted from page 3
    No mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found severed.

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 3 · 2023-04-18

    Source public_record · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-02 · Filed under EN-02, PE-05

  15. C-b22b20654d

    Memoranda of the solar leases for Parcels 2, 5 and 9 must still be recorded.

    Quoted from page 1
    Record memoranda of the solar leases for Parcels 2, 5 and 9, executed and acknowledged by the owners of

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 1 · 2023-04-18

    Source public_record · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

  16. C-cd08e1f358

    Parcel 11 (Okerlund Family Trust) has no agreement, in negotiation, and is needed for collection route and East Block access.

    Quoted from page 1
    None (in negotiation) | No | No | Needed for collection route and East Block access

    Parcel Schedule 2023-07-14 · DR-0005 · Page 1 · 2023-07-14

    Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-01, PE-05

  17. C-d257ecfe8e

    The easement crosses the Calder Gathering Company natural gas gathering line, requiring the grantee to obtain a written crossing agreement and keep required clearance.

    Quoted from page 1
    Grantee will obtain that company's written crossing agreement and keep the clearance it requires.

    Underground Collection Line Easement Agreement - Parcel 7 · DR-0003 · Page 1 · 2022-11-03

    Source public_record · Claim type constraint · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Cited by EN-01, PE-03 · Filed under EN-01, PE-03, PE-05

  18. C-dcf3900993

    An oil and gas lease to Brenwick Exploration, with pooled unit, allows surface use for wells, pads, roads, pipelines and tanks on Parcels 2 and 5.

    Quoted from page 2
    surface as is reasonably necessary for wells, pads, roads, pipelines and tanks. Affects Parcels 2 and 5.

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 2 · 2023-04-18

    Source public_record · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-01 · Filed under EN-01, EN-02, PE-05

  19. C-ebcacfde9b

    No condemnation power is available to the Project.

    Quoted from page 2
    No condemnation power is available to the Project.

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence low · Quote check exact, 100 of 100

  20. C-faaf963eae

    An accommodation agreement or partial surface release from Brenwick Exploration is required for oil and gas lease areas to be occupied by the solar facility; otherwise no affirmative coverage.

    Quoted from page 1
    Record an accommodation agreement, or a partial release of surface rights, from Brenwick Exploration, LLC

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 1 · 2023-04-18

    Source public_record · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-02, PE-05

Requirements and permits

The requirements the assessor tied to this row, by level. Each quote from dated law is shown with its source.

No requirement is tied to this row.

Information requests

  • IR-7d328a6772 · High priority

    Provide the mineral ownership or surface-use review for the project area, or confirm none exists.

    Missing evidence
    Mineral ownership or surface-use review
    Consequence
    Site Control and Land Rights is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-5f0015e952 · High priority

    Provide the parcel control table or site control summary for the project area, or confirm none exists.

    Missing evidence
    Parcel control table or site control summary
    Consequence
    Site Control and Land Rights is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

Next steps

  • Resolve Parcel 11 by negotiation, or confirm the Linnet Road alternative (county right-of-way permit) and East Block access.
  • Execute the Brenwick accommodation agreement, the Parcel 9 SNDA and memoranda of lease.
  • Build a parcel control table with option expiry dates against the COD schedule.

Agencies

  • Carroll County

Cost and impact

Impact
C, S
Potential cost level
M-H
Why

Essential Parcel 11 is missing and its trustee has declined the option twice. A minerals accommodation, SNDA and possible collection rerouting are pending.

Impact: C = cost, S = schedule. Potential cost level: L, L-M, M, M-H, H (relative to a utility-scale solar budget).

Lumerian Labs 2026