Wetland and Stream Delineation Report - Tamsin Ridge Solar and Storage Project
C-65f000df43 · Page 3 of 3 · DR-0013 · 2023-05-22
The claim, in the assessor's words
If W-3 or its 300-foot buffer is affected, Ohio EPA individual review and compensatory mitigation would be needed, with a schedule effect of six months or more.
Ohio EPA individual review and compensatory mitigation would be needed, with a schedule effect of six months or more.
Source consultant_memo · Claim type schedule · Polarity presence · Confidence high · Quote check exact, 100 of 100
Cited by AQ-01 Wetlands and Waterbodies · Filed under AQ-01, PE-02, PE-03
On the page
The page text exactly as the engine read it, with the quote marked.
Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own.
Read as native
The page
The outline marks where the quote begins on the page.

Other claims quoted on this page
Any impact to a Category 3 wetland needs Ohio EPA's individual review, and filling an isolated wetland needs an Ohio EPA permit.
The May 8, 2023 draft layout avoids all five wetlands and keeps the ODNR buffers.
Two collection line crossings of Sallow Creek are planned as HDD bores of about 900 feet, needing no permit absent frac-out.
The S-4 access road crossing is the only planned fill: about 40 linear feet of ephemeral channel (0.02 acre) under NWP 14.