Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project

C-7f2ea3298c · Page 2 of 2 · DR-0024 · 2023-03-20

The claim, in the assessor's words

Whether OPSB accepts the estimate net of salvage ($5.7 million) or requires gross ($11.6 million) has not been settled.

Quoted from page 2
whether OPSB will accept the estimate net of salvage ($5.7 million) or require the gross figure ($11.6 million) has not been settled.

Source developer_document · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100

Cited by PE-06 Decommissioning and Financial Assurance · Filed under PE-02, PE-06

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge 4. Cost estimate (2023 dollars) Item Cost Salvage or resale Net Modules and trackers $4.9 million $3.6 million $1.3 million Inverters, substation, collection system $1.8 million $1.1 million $0.7 million Battery enclosures and power conversion $2.3 million $0.8 million $1.5 million Piles, foundations, roads, fencing $1.5 million $0.4 million $1.1 million Site restoration, tile repair, seeding $0.6 million - $0.6 million Engineering, permits, contingency (10%) $0.5 million - $0.5 million Total $11.6 million $5.9 million $5.7 million Salvage values use 2023 scrap prices for steel, aluminum and copper and a conservative resale value for used modules. Scrap prices are volatile, and salvage could fall well short of these figures. 5. Financial assurance Northfold proposes a surety bond, posted before construction with the OPSB as obligee and with the landowners as additional beneficiaries, and recalculated every five years. The statute requires the bond to equal the decommissioning cost estimate; Quote starts. whether OPSB will accept the estimate net of salvage ($5.7 million) or require the gross figure ($11.6 million) has not been settled. Quote ends. The leases require separate security for each landowner, which the bond is intended to satisfy. 6. Plan updates The plan and the estimate will be finalized with the OPSB application, resubmitted at least 60 days before construction, and updated every five years of operation. Anika Tessmer, P.E. (Ohio), Project Engineer, Tessmer Coyle Engineering, Inc. Tessmer Coyle Engineering, Inc. - Job 2317 Page 2 of 2

The page

The outline marks where the quote begins on the page.

Page 2 of Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project

Other claims quoted on this page

  • C-303a605026

    Decommissioning estimate in 2023 dollars is $11.6 million gross, $5.9 million salvage, $5.7 million net.

  • C-b508b5b110

    Salvage values rely on volatile scrap prices and could fall well short of the estimate.

  • C-f3daa0fd5a

    The leases require separate security for each landowner, which the bond is intended to satisfy.