Decommissioning and Financial Assurance

PE-06 · Matrix · Additional Permitting

Rating
3Resource is present, likely difficult to address
Why
Core of the site; partly avoidable
Worst case
Not above the rating
Evidence
Reported
Cited claims
11
Requirements
0
Requests
2

Rating

3Resource is present, likely difficult to address

The engine shows this rating as 3

The rule

Code computed the rating from the assessor's inputs:

extent=core, avoidable=partly -> 3

Set by the rule

Decision
Released
Evidence state
Reported · desktop, consultant or developer record

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

OPSB requires the gross $11.6 million bond with no salvage credit, and the amount is contested through the OPSB process, with landowner security adding further burden.

Step still pending
OPSB review of the decommissioning plan and bond amount
Inputs in the worst case
Extent core · Avoidable partly · Pathway individual · Impact likely yes
The rule on the worst case
worst case (extent=core, avoidable=partly -> 3) not above the point
Claims that make it plausible
C-7f2ea3298c, C-303a605026, C-b508b5b110, C-0dda429c60

Revision

First verdict
weakened
First critique

Core inputs, the salvage uncertainty and the worst case are well supported. However, the '60 days before construction' and 'engineer' details appear in no cited quote. The Carroll County agency listing is unsupported, and two uncited claims (C-4e2febbe42, C-640e804855) are not used. Category 3 holds.

Revised once after the first critique. Rating unchanged.

The five inputs

Comments

ORC 4906.21 to 4906.222 require a decommissioning plan and performance bond. Bond equal to the estimate is due before construction, updated every five years, never reduced. Estimate is $11.6 million gross, $5.7 million net of salvage; OPSB treatment of salvage is unsettled. Leases require 36-inch removal and separate landowner security.

Critique

Verdict
upheld
Suggested direction for the rating
same
Summary

Assessment is largely supported by the cited claims, and OPSB is the right agency. Two minor problems: the Parcel 7 easement removal term is not in the quote, and the landowner security is framed as additional when the bond is meant to satisfy it.

Critic model
Luminol

Issues

  1. Severity minor · Kind unsupported_statement

    The extent rationale cites C-4e2febbe42 for a Parcel 7 easement requiring removal of above-ground equipment two years after operations stop. The quote only says something 'ends two (2) years after it permanently stops operating'. It names no parcel and mentions no removal obligation. Extent 'core' still holds on the other claims.

    Cites C-4e2febbe42

  2. Severity minor · Kind overstatement

    The worst case says landowner security adds further burden, and the avoidable rationale lists separate security as an extra term. C-f3daa0fd5a says the bond is intended to satisfy the per-landowner security requirement, so it is likely duplicative rather than additional. The next step on aligning lease security with the bond is appropriate.

    Cites C-f3daa0fd5a

Checks

  • Passed

    rating_has_evidence · blocking

  • Passed

    presence_is_evidenced · not blocking

  • Passed

    counter_evidence_considered · not blocking

  • Passed

    numbers_grounded · not blocking

  • Passed

    agencies_grounded · not blocking

  • Passed

    cutoff_respected · blocking

  • Passed

    critic_not_refuted · blocking

Evidence (11)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

Arrow keys move the selection. A middle-click opens the claim's own page.

  1. Lease requires lessee to remove facilities to 36 inches depth and restore soil within 12 months after lease end, with security posted.Option and Lease Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  2. A performance bond with the Board as obligee, equal to the estimate, must be posted before construction, updated every five years and never reduced.Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · Page 1Exact
  3. Decommissioning estimate in 2023 dollars is $11.6 million gross, $5.9 million salvage, $5.7 million net.Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · Page 2Exact
  4. The easement ends two years after the project permanently stops operating; grantee must remove above-ground equipment and remove or leave buried cables at grantor's election.Underground Collection Line Easement Agreement - Parcel 7 · Page 1Exact
  5. Plan for battery removal and recycling at end of life in the decommissioning plan.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 2Exact
  6. Decommissioning plan and performance bond requirements of ORC 4906.21 to 4906.222 apply.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  7. Whether OPSB accepts the estimate net of salvage ($5.7 million) or requires gross ($11.6 million) has not been settled.Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · Page 2Exact
  8. Salvage values rely on volatile scrap prices and could fall well short of the estimate.Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · Page 2Exact
  9. Ohio law requires an engineer-prepared decommissioning plan submitted to the OPSB at least 60 days before construction, with removal ending within 12 months of cessation.Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · Page 1Exact
  10. The leases require removal and restoration within 12 months after they end.Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · Page 1Exact
  11. The leases require separate security for each landowner, which the bond is intended to satisfy.Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · Page 2Exact

Option and Lease Summary - Tamsin Ridge Solar and Storage Project

C-00d4067593 · Page 1 of 2 · DR-0004

Open the claim, C-00d4067593

Lease requires lessee to remove facilities to 36 inches depth and restore soil within 12 months after lease end, with security posted.

Quote check Exact · Placed verbatim · The quote occurs on the page exactly as written. · Read as native

Northfold Energy Partners, LLC Development office: 88 East Broad Street, Suite 1400, Columbus, Ohio 43215 | northfold-energy.example Option and Lease Summary Tamsin Ridge Solar and Storage Project, Harrison Township, Carroll County, Ohio Prepared by the Northfold land team for Tamsin Ridge Solar, LLC. May 30, 2023. 1. Site control at a glance Tamsin Ridge Solar, LLC holds option-to-lease agreements on 12 of the 14 parcels (1,063.4 acres) and a recorded underground collection line easement on Parcel 7 (45.6 acres). Parcel 11 (31.0 acres, Okerlund Family Trust) is not under agreement. Each option was recorded by a memorandum of option in the Carroll County Recorder's office. Term Standard form (all 12 options) Option period 5 years from execution, with one 3-year extension on notice and payment Option payments Annual per-acre payment during the option period; credited against rent Lease term 35 years from the commercial operation date, with two 5-year renewals Rent Fixed annual rent per fenced acre with a 2% annual escalator; crop damage paid Use Solar generation, battery storage, substation, collection and gen-tie lines, roads Lessor reservations Hunting outside the fence; farming of unfenced land; oil and gas rights Decommissioning Quote starts. Lessee removes all facilities to a depth of 36 inches and restores the soil within 12 months after Quote ends. the lease ends; lessee posts security Drain tile Lessee repairs or reroutes tile damaged by construction Assignment Free assignment to affiliates and lenders; lender protections included 2. Status by landowner Landowner Parcels Acres Agreement Executed Varnum Farms LLC 1, 2 215.1 Option to lease Aug. 16, 2021 Jessamy and Corwin Strohl 3, 4 160.6 Option to lease Oct. 4, 2021 Hallorann Land Company LLC 5, 6 165.5 Option to lease Nov. 22, 2021 Delphine Asquith 7 45.6 Collection line easement Recorded Nov. 3, 2022 Bertrand and Ione Kellerman 8 79.8 Option to lease Jan. 18, 2022 Pettibone heirs (Ada Pettibone, trustee) 9, 10 210.0 Option to lease Feb. 7, 2022 Okerlund Family Trust 11 31.0 None; in negotiation - Marlis Thornbury 12, 13 155.2 Option to lease Mar. 29, 2022 Ruedell Partners LLC 14 77.2 Option to lease June 30, 2022 Northfold land team - privileged and confidential Page 1 of 2

The outline marks where the quote begins on the page.

Page 1 of Option and Lease Summary - Tamsin Ridge Solar and Storage Project
  1. C-00d4067593

    Lease requires lessee to remove facilities to 36 inches depth and restore soil within 12 months after lease end, with security posted.

    Quoted from page 1
    Lessee removes all facilities to a depth of 36 inches and restores the soil within 12 months after

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 1 · 2023-05-30

    Source developer_document · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

  2. C-0dda429c60

    A performance bond with the Board as obligee, equal to the estimate, must be posted before construction, updated every five years and never reduced.

    Quoted from page 1
    Before construction it must post a performance bond, with the Board as obligee, equal to the estimate; the bond is updated every five years and is never reduced.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 1 · 2023-03-20

    Source developer_document · Claim type regulatory · Polarity presence · Confidence medium · Quote check exact, 100 of 100

  3. C-303a605026

    Decommissioning estimate in 2023 dollars is $11.6 million gross, $5.9 million salvage, $5.7 million net.

    Quoted from page 2
    Total $11.6 million $5.9 million $5.7 million

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type cost · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  4. C-4e2febbe42

    The easement ends two years after the project permanently stops operating; grantee must remove above-ground equipment and remove or leave buried cables at grantor's election.

    Quoted from page 1
    ends two (2) years after it permanently stops operating

    Underground Collection Line Easement Agreement - Parcel 7 · DR-0003 · Page 1 · 2022-11-03

    Source public_record · Claim type constraint · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under PE-05, PE-06

  5. C-640e804855

    Plan for battery removal and recycling at end of life in the decommissioning plan.

    Quoted from page 2
    Plan for battery removal and recycling at end of life in the decommissioning plan.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28

    Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under EG-04, PE-06

  6. C-7818388af6

    Decommissioning plan and performance bond requirements of ORC 4906.21 to 4906.222 apply.

    Quoted from page 1
    decommissioning plan and performance bond requirements of ORC 4906.21 to 4906.222 apply.

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

  7. C-7f2ea3298c

    Whether OPSB accepts the estimate net of salvage ($5.7 million) or requires gross ($11.6 million) has not been settled.

    Quoted from page 2
    whether OPSB will accept the estimate net of salvage ($5.7 million) or require the gross figure ($11.6 million) has not been settled.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under PE-02, PE-06

  8. C-b508b5b110

    Salvage values rely on volatile scrap prices and could fall well short of the estimate.

    Quoted from page 2
    Scrap prices are volatile, and salvage could fall well short of these figures.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  9. C-b6d40fe4d7

    Ohio law requires an engineer-prepared decommissioning plan submitted to the OPSB at least 60 days before construction, with removal ending within 12 months of cessation.

    Quoted from page 1
    the applicant must submit a comprehensive decommissioning plan prepared by a registered professional

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 1 · 2023-03-20

    Source developer_document · Claim type regulatory · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Filed under PE-02, PE-06

  10. C-e278af1a95

    The leases require removal and restoration within 12 months after they end.

    Quoted from page 1
    The leases also require removal and restoration within 12 months after they end.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 1 · 2023-03-20

    Source developer_document · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under PE-05, PE-06

  11. C-f3daa0fd5a

    The leases require separate security for each landowner, which the bond is intended to satisfy.

    Quoted from page 2
    The leases require separate security for each landowner, which the bond is intended to satisfy.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under PE-05, PE-06

Requirements and permits

The requirements the assessor tied to this row, by level. Each quote from dated law is shown with its source.

No requirement is tied to this row.

Information requests

  • IR-0a712115cd · High priority

    Provide the financial assurance instrument or terms (bond, letter of credit, escrow, parent guarantee) for the project area, or confirm none exists.

    Missing evidence
    Financial assurance instrument or terms (bond, letter of credit, escrow, parent guarantee)
    Consequence
    Decommissioning and Financial Assurance is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-9c85d7f357 · High priority

    Provide the state or local decommissioning rule or permit condition for the project area, or confirm none exists.

    Missing evidence
    State or local decommissioning rule or permit condition
    Consequence
    Decommissioning and Financial Assurance is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

Next steps

  • Confirm with OPSB whether the bond may be net of salvage.
  • Align lease security with the OPSB bond and confirm bond form with the surety or lender.
  • Include battery removal and recycling in the decommissioning plan and estimate.

Agencies

  • OPSB

Cost and impact

Impact
C, S
Potential cost level
M-H
Why

Bond sized to the estimate must be posted before construction and never reduced; gross figure of $11.6 million possible versus $5.7 million net; battery removal and recycling must be planned.

Impact: C = cost, S = schedule. Potential cost level: L, L-M, M, M-H, H (relative to a utility-scale solar budget).