Traffic and Access Memo - Tamsin Ridge Solar and Storage Project

C-8172eb7213 · Page 1 of 2 · DR-0020 · 2023-06-19

The claim, in the assessor's words

Fescue Road is a narrow 16-foot township road with two 90-degree turns needing temporary widening for tractor-trailers.

Quoted from page 1
Fescue Road is a 16-foot chip-and-seal township road with narrow shoulders and two 90-degree turns where swept path analysis shows that tractor-trailers need temporary widening.

Source consultant_memo · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by EG-01 Civil Engineering, EG-03 Transportation and Access · Filed under EG-01, EG-03

On the page

The page text exactly as the engine read it, with the quote marked.

Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own.

Read as native

Go to the marked quote

Tessmer Coyle Engineering, Inc. Civil engineering, stormwater and transportation | New Philadelphia, Ohio Traffic and Access Memo To: Northfold Energy Partners, LLC. From: Tessmer Coyle Engineering. June 19, 2023. Re: Construction traffic, haul routes and road permits, Tamsin Ridge Solar and Storage Project. 1. Construction traffic Construction is expected to take about 16 months. At the peak, about 310 worker vehicles and 60 heavy trucks a day would travel to the site; over the whole build, about 7,900 heavy truck deliveries (modules, piles, trackers, aggregate, cable, inverters and battery enclosures). Regional deliveries will use State Route 43. Four construction entrances are planned: two on Linnet Road (a county road) and two on Fescue Road (a township road). Oversize and overweight loads. The main power transformer (about 230,000 pounds gross on its transporter) is a superload and will need an ODOT special hauling permit with a route survey. The battery enclosures, the substation equipment and the cranes are overweight or oversize loads and will need county and township permits as well. 2. Haul route The county bridge carrying Linnet Road over Sallow Creek is load posted at 10 tons and cannot carry construction trucks. Heavy trucks bound for the East Block will use Fescue Road and Dunmore Road instead, adding about 2.4 miles per trip. Quote starts. Fescue Road is a 16-foot chip-and-seal township road with narrow shoulders and two 90-degree turns where swept path analysis shows that tractor-trailers need temporary widening. Quote ends. Road Jurisdiction Use Concern State Route 43 ODOT Regional deliveries Superload permit and route survey Linnet Road Carroll County West Block entrances Bridge posted 10 tons; no heavy trucks across it Fescue Road Harrison Township West Block and East Block Narrow; turn widening; pavement entrances damage likely Dunmore Road Carroll County East Block access Culvert at S-2 to be checked Tessmer Coyle Engineering, Inc. - Job 2317 Page 1 of 2

The page

The outline marks where the quote begins on the page.

Page 1 of Traffic and Access Memo - Tamsin Ridge Solar and Storage Project

Other claims quoted on this page

  • C-308500498d

    At peak, about 310 worker vehicles and 60 heavy trucks a day would travel to the site.

  • C-c4d1481145

    The main power transformer is a superload needing an ODOT special hauling permit with a route survey.

  • C-84c9333669

    Battery enclosures, substation equipment and cranes are overweight or oversize loads needing county and township permits.

  • C-f5ca528c73

    East Block heavy trucks must detour via Fescue and Dunmore Roads, adding about 2.4 miles per trip.