Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project
C-c8e5735fc6 · Page 3 of 3 · DR-0019 · 2023-06-05
The claim, in the assessor's words
Landowners report subsurface drain tile in the West Block fields on Parcels 1 to 4, 6 and 8 and Parcel 14; no tile maps exist.
Landowners report subsurface drain tile in the West Block fields on Parcels 1 to 4, 6 and 8 and on
Source consultant_memo · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
Cited by EN-03 Agricultural Resources · Filed under EG-02, EN-03
On the page
The page text exactly as the engine read it, with the quote marked.
Placed verbatim · The quote occurs on the page exactly as written.
Read as native
The page
The outline marks where the quote begins on the page.

Other claims quoted on this page
A drain tile locating survey should be done before final design, and tile cut by project work must be repaired or rerouted.
Harrison Township No. 4 county ditch crosses Parcel 3 and runs along the southern line of Parcel 5, with a maintenance easement within 25 feet of each bank top.
County ditch has a maintenance easement within 25 feet of the top of each bank; fencing, piles and equipment are kept out.
SSURGO maps about 62 percent of the land as prime farmland and another 21 percent as farmland of statewide importance.
Twelve parcels are enrolled in CAUV and eight are in an agricultural district; recoupment charge and withdrawal penalty may apply unless the energy facility exception applies.