Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project

C-e278af1a95 · Page 1 of 2 · DR-0024 · 2023-03-20

The claim, in the assessor's words

The leases require removal and restoration within 12 months after they end.

Quoted from page 1
The leases also require removal and restoration within 12 months after they end.

Source developer_document · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by PE-06 Decommissioning and Financial Assurance · Filed under PE-05, PE-06

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

Tessmer Coyle Engineering, Inc. Civil engineering, stormwater and transportation | New Philadelphia, Ohio Preliminary Decommissioning Plan and Cost Estimate Tamsin Ridge Solar and Storage Project, Harrison Township, Carroll County, Ohio Prepared for Northfold Energy Partners, LLC. March 20, 2023. 1. Purpose and requirements This plan describes how the 120 MW solar facility and the 60 MW / 240 MWh battery energy storage system will be removed and the land restored at the end of the Project's life. Under ORC 4906.21 to 4906.222, enacted by SB 52, the applicant must submit a comprehensive decommissioning plan prepared by a registered professional engineer to the OPSB at least 60 days before construction, with a schedule that ends within 12 months after the facility stops operating, and a full cost estimate recalculated every five years. Before construction it must post a performance bond, with the Board as obligee, equal to the estimate; the bond is updated every five years and is never reduced. Quote starts. The leases also require removal and restoration within 12 months after they end. Quote ends. 2. Decommissioning triggers and schedule Decommissioning starts when the facility has generated no electricity for 12 consecutive months, when the leases end, or when the owner decides to retire it. Removal and restoration will take about 9 months: equipment removal (months 1 to 6), foundations, cables and roads (months 4 to 8), and soil restoration and seeding (months 7 to 9). 3. Removal and restoration • Modules, trackers, inverters, the substation, the battery enclosures, fencing and the operations building are removed. • All piles are pulled completely. Concrete foundations are removed to 36 inches below grade. • Underground collection cables are removed to 36 inches; deeper cables are removed unless the landowner elects in writing to leave them. • Gravel roads are removed and the subsoil decompacted, unless a landowner keeps a road. • Topsoil is restored, compaction relieved by deep ripping, drain tile repaired, and the land seeded to a cover crop for return to farming. • Modules are sent for reuse or recycling. Battery enclosures are returned to the manufacturer or a licensed recycler under its take-back program; damaged batteries are handled as hazardous waste. Tessmer Coyle Engineering, Inc. - Job 2317 Page 1 of 2

The page

The outline marks where the quote begins on the page.

Page 1 of Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project

Other claims quoted on this page

  • C-b6d40fe4d7

    Ohio law requires an engineer-prepared decommissioning plan submitted to the OPSB at least 60 days before construction, with removal ending within 12 months of cessation.

  • C-0dda429c60

    A performance bond with the Board as obligee, equal to the estimate, must be posted before construction, updated every five years and never reduced.