OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project

C-1f7f13bfbe · Page 2 of 2 · DR-0026 · 2023-03-28

The claim, in the assessor's words

Ohio EPA construction stormwater coverage, any Section 401 or isolated wetland permit, and ODOT hauling and access permits are obtained separately from the certificate.

Quoted from page 2
Ohio EPA construction stormwater coverage, any Section 401 certification or isolated wetland permit, and ODOT hauling and access permits are obtained separately

Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

Cited by PE-02 State Jurisdiction · Filed under AQ-01, EG-02, EG-03, PE-02

On the page

The page text exactly as the engine read it, with the quote marked.

Placed verbatim · The quote occurs on the page exactly as written.

Read as native

Go to the marked quote

OPSB Pre-Application Conference Summary - Tamsin Ridge 4. Process and timing The pre-application notification letter must be filed at least 15 days before the public informational meeting, which must be held in the project area no more than 90 days before the application. After the application is filed, the chairman accepts it as complete or rejects it within 60 days, and the hearing is set 60 to 90 days after a complying application is received. Staff indicated that solar cases with active local opposition have recently taken 9 to 14 months from filing to decision. Planned sequence: county public meeting in May 2023; public informational meeting after the 90-day period that follows the county meeting; application filing in the third quarter of 2023; decision expected in 2024. 5. State permits outside the certificate Staff reminded the team that Quote starts. Ohio EPA construction stormwater coverage, any Section 401 certification or isolated wetland permit, and ODOT hauling and access permits are obtained separately Quote ends., and that ODNR comments on wildlife, wetlands and mines are typically made conditions of the certificate. 6. Action items • Northfold: schedule and notice the county public meeting under ORC 303.61. • Northfold: complete the noise study, the geotechnical mine investigation plan and the emergency plan before the public informational meeting. • Whitlock Ames: prepare the pre-application notification letter and the public notices. • Whitlock Ames: monitor the Board of County Commissioners' agenda for any ORC 303.58 or 303.62 resolution. Prepared by Whitlock Ames LLP for its client. Privileged and confidential. Whitlock Ames LLP - privileged Page 2 of 2

The page

The outline marks where the quote begins on the page.

Page 2 of OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project

Other claims quoted on this page

  • C-b61135956d

    Staff indicated solar cases with active local opposition have recently taken 9 to 14 months from filing to decision.

  • C-785b75ec77

    Planned sequence: county meeting May 2023, application filing third quarter 2023, decision expected 2024.

  • C-03c910d4d1

    ODNR comments on wildlife, wetlands and mines are typically made conditions of the certificate.