Interconnection and Transmission: desk report

Word file

One row of the risk matrix, PE-04 Interconnection and Transmission, in the Additional Permitting section: what the record holds on it.

A desk review of the record as it stood: not a field survey and not a modelled study.

Information cut-off
2023-08-01

Downloads

This report as a Word file, and the engine's own files for the whole run.

1Finding

3Resource is present, likely difficult to address

The engine shows this rating as 3

The rule

Code computed the rating from the assessor's inputs:

extent=core, avoidable=partly -> 3

Set by the rule

Decision
Released
Evidence state
REPORTED · desktop, consultant or developer record

The assessor's comments

PJM queue AH1-931 has a feasibility study (April 14, 2022) listing total network upgrades of $31.4 million (plus or minus 50%); the project's share is not stated. Transmission Owner estimates 36 to 42 months after agreement execution, which may constrain the December 2026 date. No agreement in the data room; next study phase not started.

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

Restudy raises upgrade costs toward the top of the plus or minus 50% band, affected-system impacts appear, and the 36 to 42 month build leaves no workable route to the December 2026 COD.

Step still pending
System Impact and Facilities Studies under PJM's reformed process
Inputs in the worst case
Extent core · Avoidable no · Pathway standard · Impact likely yes
The rule on the worst case
worst case (extent=core, avoidable=no -> 3) not above the point

2What the record shows

The five inputs

Supporting statements (12)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

  1. C-387e001e3f

    Interconnection is in PJM.

    Quoted from page 1
    PJM queue position AH1-931; the interconnection request was submitted on September 24, 2021.

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  2. C-4a00292b36

    Proposed point of interconnection is a new Tamsin Ridge 138 kV switching station on the Vesper Hill-Ardley 138 kV line.

    Quoted from page 1
    Proposed Tamsin Ridge 138 kV switching station (new three-breaker ring bus)

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  3. C-502eff95b5

    The position is in PJM's transition to its reformed process and the next study phase has not started.

    Quoted from page 1
    The position is now in PJM's transition to its reformed interconnection process, and the next study phase has not started.

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type data_gap · Polarity presence · Confidence high · Quote check exact, 100 of 100

  4. C-9696e61ce3

    Total network upgrades allocated to AH1-931 are estimated at $31.4 million.

    Quoted from page 1
    Total network upgrades $31.4 million

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100

  5. C-9bf4e1b156

    Feasibility study is complete; System Impact Study, Facilities Study and Interconnection Service Agreement follow.

    Quoted from page 2
    will be followed by a Facilities Study and an Interconnection Service Agreement.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

  6. C-a21ca05339

    Interconnection voltage is 138 kV via a 0.4-mile gen-tie.

    Quoted from page 1
    reached by a 0.4-mile 138 kV gen-tie line

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  7. C-ab3abd8d5e

    No short circuit violations were found and no affected system impacts were identified at this stage.

    Quoted from page 2
    No short circuit violations were found. No affected system impacts were identified at this stage.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

  8. C-bbdfdec1fc

    Cost estimates are planning-level with accuracy of about plus or minus 50 percent and may change.

    Quoted from page 2
    The costs above are planning-level estimates with an accuracy of about plus or minus 50 percent.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100

  9. C-cdf3d7697c

    Transmission Owner estimates 36 to 42 months after interconnection agreement execution to complete upgrades, which may constrain the requested in-service date.

    Quoted from page 2
    The Transmission Owner estimates 36 to 42 months from execution of an interconnection agreement to complete the switching station and the network upgrades

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14

    Source agency_determination · Claim type schedule · Polarity presence · Confidence high · Quote check exact, 100 of 100

  10. C-ddff0b0f72

    Requested in-service date is December 2026.

    Quoted from page 1
    Requested in-service date December 2026

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

  11. C-edf1371b18

    Queue position is AH1-931.

    Quoted from page 1
    Queue position AH1-931, "Tamsin Ridge 138 kV".

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  12. C-fa0fe91ee0

    Feasibility study found reliability violations under deliverability and multiple facility contingency tests requiring network upgrades.

    Quoted from page 1
    The study found reliability violations under the generator deliverability and multiple facility contingency tests that require network upgrades.

    Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14

    Source agency_determination · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

3Permits and requirements

The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.

No requirement is tied to the rows of this report.

4What is missing

The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.

High priority (2)

  • IR-b24dc38cf1 · High priority

    Provide the executed or draft interconnection agreement for the project area, or confirm none exists.

    Missing evidence
    Executed or draft interconnection agreement
    Consequence
    Interconnection and Transmission is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-78fe2a615a · High priority

    Provide the gen-tie route study, line siting application or route map for the project area, or confirm none exists.

    Missing evidence
    Gen-tie route study, line siting application or route map
    Consequence
    Interconnection and Transmission is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

5Next steps and agencies

Next steps

  • Obtain PJM status letter on transition timing and the project's share of upgrade costs.
  • Re-baseline COD against the 36 to 42 month build time and the plus or minus 50% estimate.
  • Confirm deposits are current and obtain the gen-tie route and permit needs.

Agencies

  • PJM
  • Transmission Owner

6Basis and limits

This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.

It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.

Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.

Documents quoted (2)

Versions and data hashes

As the engine and the exporter recorded them. Hashes are SHA-256.

Information cut-off
2023-08-01
Engine version
2.11.0
Prompt version
2026-11-08.1
Rows pack
rows.json sha256 a018ecd7e4703bc1
Federal pack
federal.json sha256 8841c555ff35d20b
State pack
oh.json sha256 d4780705e1f18d09
Local pack
oh_carroll_county.json sha256 905cd3308848e7e8
Data room manifest
0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
Audit chain
valid (19 events)
QA status
PASS_WITH_WARNINGS
Rendered at
2026-11-10T15:42:40+00:00
Run record (annex)
66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
Exporter
Prism/room/exporter 1.4.0

Prism desk report · engine 2.11.0 · prompts 2026-11-08.1 · information cut-off 2023-08-01