Interconnection and Transmission: desk report
One row of the risk matrix, PE-04 Interconnection and Transmission, in the Additional Permitting section: what the record holds on it.
A desk review of the record as it stood: not a field survey and not a modelled study.
- Information cut-off
- 2023-08-01
- Row in the matrix
- PE-04 Interconnection and Transmission
Downloads
This report as a Word file, and the engine's own files for the whole run.
- This reporttamsin-ridge-solar-and-storage-PE-04.docx · Word · 41 KB
- The engine's risk matrixRiskMatrix_TamsinRidgeSolarandStorage.xlsx · Excel · 108 KB
- The engine's permit matrixTamsin Ridge Solar and Storage Permit Matrix.docx · Word · 61 KB
1Finding
Resource is present, likely difficult to address
The engine shows this rating as 3
- The rule
Code computed the rating from the assessor's inputs:
extent=core, avoidable=partly -> 3
Set by the rule
- Decision
- Released
- Evidence state
- REPORTED · desktop, consultant or developer record
The assessor's comments
PJM queue AH1-931 has a feasibility study (April 14, 2022) listing total network upgrades of $31.4 million (plus or minus 50%); the project's share is not stated. Transmission Owner estimates 36 to 42 months after agreement execution, which may constrain the December 2026 date. No agreement in the data room; next study phase not started.
Worst case
The same rule on the worst case gives no rating above the point.
- Scenario
Restudy raises upgrade costs toward the top of the plus or minus 50% band, affected-system impacts appear, and the 36 to 42 month build leaves no workable route to the December 2026 COD.
- Step still pending
- System Impact and Facilities Studies under PJM's reformed process
- Inputs in the worst case
- Extent core · Avoidable no · Pathway standard · Impact likely yes
- The rule on the worst case
- worst case (extent=core, avoidable=no -> 3) not above the point
- Claims that make it plausible
- C-9696e61ce3, C-bbdfdec1fc, C-cdf3d7697c, C-502eff95b5, C-ab3abd8d5e
2What the record shows
The five inputs
Present: yes
Grid-connected 120 MW solar with storage in PJM queue AH1-931 (C-edf1371b18, C-387e001e3f), 138 kV POI via 0.4-mile gen-tie (C-a21ca05339, C-4a00292b36).
Cites C-edf1371b18, C-387e001e3f, C-a21ca05339, C-4a00292b36
Extent: core
Feasibility study found violations requiring network upgrades, totalling $31.4M at plus or minus 50% (C-fa0fe91ee0, C-9696e61ce3, C-bbdfdec1fc). No interconnection agreement is in the data room, the next study phase has not started and the position is in PJM's transition (C-502eff95b5). The Transmission Owner needs 36 to 42 months after agreement execution, against a December 2026 requested in-service date (C-cdf3d7697c, C-ddff0b0f72). Funding and schedule of required upgrades are unresolved, so grid access as a whole is in doubt. The gen-tie is short (C-a21ca05339).
Cites C-fa0fe91ee0, C-9696e61ce3, C-bbdfdec1fc, C-502eff95b5, C-cdf3d7697c, C-ddff0b0f72, C-a21ca05339
Avoidable: partly
No short circuit violations or affected system impacts were found at feasibility stage only (C-ab3abd8d5e), and nothing in the record shows the position withdrawn or refused, so a route to the grid is not foreclosed. Upgrade cost, restudy in the reformed process and the 36 to 42 month build time are likely to change cost and schedule, and the December 2026 date looks difficult to meet (C-9696e61ce3, C-cdf3d7697c, C-502eff95b5). Kept at partly because no document shows a lack of workable route.
Cites C-ab3abd8d5e, C-9696e61ce3, C-cdf3d7697c, C-502eff95b5
Pathway: standard
The feasibility study states a Facilities Study and Interconnection Service Agreement follow (C-9bf4e1b156). The position is moving to PJM's reformed process (C-502eff95b5), still a tariff process. No dispute or contested gen-tie siting appears in the record, and the 0.4-mile gen-tie is short (C-a21ca05339).
Cites C-9bf4e1b156, C-502eff95b5, C-a21ca05339
Impact likely: yes
The study lists total network upgrades of $31.4M at planning-level accuracy, and the upgrade timeline may constrain the requested in-service date (C-9696e61ce3, C-bbdfdec1fc, C-cdf3d7697c). The project's own share of this total is not shown in the record.
Cites C-9696e61ce3, C-bbdfdec1fc, C-cdf3d7697c
Supporting statements (12)
Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.
C-387e001e3f
Interconnection is in PJM.
Quoted from page 1 PJM queue position AH1-931; the interconnection request was submitted on September 24, 2021.
Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12
Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-4a00292b36
Proposed point of interconnection is a new Tamsin Ridge 138 kV switching station on the Vesper Hill-Ardley 138 kV line.
Quoted from page 1 Proposed Tamsin Ridge 138 kV switching station (new three-breaker ring bus)
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14
Source agency_determination · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-502eff95b5
The position is in PJM's transition to its reformed process and the next study phase has not started.
Quoted from page 1 The position is now in PJM's transition to its reformed interconnection process, and the next study phase has not started.
Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12
Source developer_document · Claim type data_gap · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-9696e61ce3
Total network upgrades allocated to AH1-931 are estimated at $31.4 million.
Quoted from page 1 Total network upgrades $31.4 million
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14
Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-9bf4e1b156
Feasibility study is complete; System Impact Study, Facilities Study and Interconnection Service Agreement follow.
Quoted from page 2 will be followed by a Facilities Study and an Interconnection Service Agreement.
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14
Source agency_determination · Claim type project_fact · Polarity neutral · Confidence medium · Quote check exact, 100 of 100
C-a21ca05339
Interconnection voltage is 138 kV via a 0.4-mile gen-tie.
Quoted from page 1 reached by a 0.4-mile 138 kV gen-tie line
Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12
Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-ab3abd8d5e
No short circuit violations were found and no affected system impacts were identified at this stage.
Quoted from page 2 No short circuit violations were found. No affected system impacts were identified at this stage.
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14
Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-bbdfdec1fc
Cost estimates are planning-level with accuracy of about plus or minus 50 percent and may change.
Quoted from page 2 The costs above are planning-level estimates with an accuracy of about plus or minus 50 percent.
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14
Source agency_determination · Claim type cost · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-cdf3d7697c
Transmission Owner estimates 36 to 42 months after interconnection agreement execution to complete upgrades, which may constrain the requested in-service date.
Quoted from page 2 The Transmission Owner estimates 36 to 42 months from execution of an interconnection agreement to complete the switching station and the network upgrades
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 2 · 2022-04-14
Source agency_determination · Claim type schedule · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-ddff0b0f72
Requested in-service date is December 2026.
Quoted from page 1 Requested in-service date December 2026
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14
Source agency_determination · Claim type project_fact · Polarity neutral · Confidence medium · Quote check exact, 100 of 100
C-edf1371b18
Queue position is AH1-931.
Quoted from page 1 Queue position AH1-931, "Tamsin Ridge 138 kV".
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14
Source agency_determination · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-fa0fe91ee0
Feasibility study found reliability violations under deliverability and multiple facility contingency tests requiring network upgrades.
Quoted from page 1 The study found reliability violations under the generator deliverability and multiple facility contingency tests that require network upgrades.
Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · Page 1 · 2022-04-14
Source agency_determination · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100
3Permits and requirements
The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.
No requirement is tied to the rows of this report.
4What is missing
The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.
High priority (2)
IR-b24dc38cf1 · High priority
Provide the executed or draft interconnection agreement for the project area, or confirm none exists.
- Missing evidence
- Executed or draft interconnection agreement
- Consequence
- Interconnection and Transmission is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
IR-78fe2a615a · High priority
Provide the gen-tie route study, line siting application or route map for the project area, or confirm none exists.
- Missing evidence
- Gen-tie route study, line siting application or route map
- Consequence
- Interconnection and Transmission is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
5Next steps and agencies
Next steps
- Obtain PJM status letter on transition timing and the project's share of upgrade costs.
- Re-baseline COD against the 36 to 42 month build time and the plus or minus 50% estimate.
- Confirm deposits are current and obtain the gen-tie route and permit needs.
Agencies
- PJM
- Transmission Owner
6Basis and limits
This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.
It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.
Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.
Documents quoted (2)
- Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · 2023-06-12 · page 1
- Generation Interconnection Feasibility Study Report - Queue Position AH1-931 · DR-0021 · 2022-04-14 · pages 1, 2
Versions and data hashes
As the engine and the exporter recorded them. Hashes are SHA-256.
- Information cut-off
- 2023-08-01
- Engine version
- 2.11.0
- Prompt version
- 2026-11-08.1
- Rows pack
- rows.json sha256 a018ecd7e4703bc1
- Federal pack
- federal.json sha256 8841c555ff35d20b
- State pack
- oh.json sha256 d4780705e1f18d09
- Local pack
- oh_carroll_county.json sha256 905cd3308848e7e8
- Data room manifest
- 0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
- Audit chain
- valid (19 events)
- QA status
- PASS_WITH_WARNINGS
- Rendered at
- 2026-11-10T15:42:40+00:00
- Run record (annex)
- 66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
- Exporter
- Prism/room/exporter 1.4.0
Prism desk report · engine 2.11.0 · prompts 2026-11-08.1 · information cut-off 2023-08-01