Regional Siting Climate: desk report

Word file

One row of the risk matrix, PE-07 Regional Siting Climate, in the Additional Permitting section: what the record holds on it.

A desk review of the record as it stood: not a field survey and not a modelled study.

Information cut-off
2023-08-01

Downloads

This report as a Word file, and the engine's own files for the whole run.

1Finding

2Impacts likely but may be easily resolved

up to4Potential fatal flaw

The engine shows this rating as 2-4

The rule

Code computed the rating from the assessor's inputs:

impact_likely=yes -> 2

Set by the rule

Decision
Released with flags
The engine's reasons
  • Numbers not found in cited evidence: 03, 05, 12, 2023, 28
  • Agencies not in the register or the evidence: OPSB
Evidence state
INFERRED · reasoned from several records

The assessor's comments

Ohio SB 52 county veto power reaches the project; the PJM exemption does not apply. Commissioners may prohibit the facility or limit its boundaries within 90 days of the county meeting. No restricted-area resolution for Harrison Township was found as of 2023-03-28. Commissioners took no action at the 2023-05-12 meeting. Sources are not exhaustive.

Worst case

If what is pending at the cut-off went badly, the same rule gives a higher rating.

Scenario

Commissioners adopt an ORC 303.62 resolution prohibiting the facility or designate Harrison Township a restricted area, barring the OPSB application.

Step still pending
Board of County Commissioners decision within 90 days of the 2023-05-12 county public meeting
Inputs in the worst case
Extent core · Avoidable no · Pathway prohibition · Impact likely yes
The rule on the worst case
worst case: pathway=prohibition -> 4 potential fatal flaw

2What the record shows

The five inputs

  • Present: yes

    The SB 52 county veto and restricted-area power reaches the project: the PJM exemption does not apply because AH1-931 entered window AH1 (C-d95cdabeb7, C-5d2a9e4a3a). Commissioners may prohibit the facility or limit its boundaries within 90 days of the county meeting (C-33a9601349) and may designate restricted areas (C-a1e4999eda). Counsel found no restricted-area resolution for Harrison Township as of 2023-03-28 (C-0fe7f42a17). The absence of county and township zoning (C-09acff9294) does not touch the separate ORC 303.57-303.62 powers (C-68cb5c0292), so the absence claims do not conflict with presence of the veto power.

    Cites C-d95cdabeb7, C-5d2a9e4a3a, C-33a9601349, C-a1e4999eda, C-0fe7f42a17, C-09acff9294, C-68cb5c0292

  • Extent: unknown

    The veto power reaches the project, but the room holds no dated record of the county or adjoining counties using it, or of denials by the state siting authority, in the prior 24 months. The Board took no action at the 2023-05-12 meeting (C-27017a88b6). Core is not established and the record does not support peripheral, so extent is unknown.

    Cites C-d95cdabeb7, C-27017a88b6

  • Avoidable: partly

    The project has no exemption, grandfathering or vested protection (C-d95cdabeb7). The county could act before approval within the 90-day window (C-33a9601349, C-27017a88b6). No bar was found over the site as of 2023-03-28 (C-0fe7f42a17), so a bar is not yet shown. Residents have asked the Board to act (C-24271b647d); that opposition is rated in CO-02 and used here only as context.

    Cites C-d95cdabeb7, C-33a9601349, C-27017a88b6, C-0fe7f42a17, C-24271b647d

  • Pathway: standard

    No restriction covering the site was found as of 2023-03-28 (C-0fe7f42a17), and no denial by OPSB or the county of a same-technology project is recorded. Commissioners had taken no action at the meeting (C-27017a88b6). Individual and prohibition are not supported as of the cut-off.

    Cites C-0fe7f42a17, C-27017a88b6

  • Impact likely: yes

    A local veto/restriction power reaches the project, which is sufficient for yes under this row's guidance (C-d95cdabeb7). The county meeting under ORC 303.61 has occurred and a decision is pending (C-27017a88b6). Neighbours' stated intent to intervene is rated in CO-02 and not relied on here.

    Cites C-d95cdabeb7, C-27017a88b6

Supporting statements (9)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

  1. C-09acff9294

    Carroll County has not adopted a county zoning resolution, and Harrison Township has not adopted a township zoning resolution under ORC Chapter 519.

    Quoted from page 1
    Carroll County has not adopted a county zoning resolution. Harrison Township has not adopted a township zoning resolution under ORC Chapter 519.

    Zoning Verification - Tamsin Ridge Solar and Storage Project · DR-0022 · Page 1 · 2023-02-14

    Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-01 · Filed under PE-01, PE-07

  2. C-0fe7f42a17

    Counsel's search found no ORC 303.58 restricted-area resolution for Harrison Township on the conference date.

    Quoted from page 1
    Counsel's search found no such resolution for Harrison Township on the date of the

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-01 · Filed under PE-01, PE-07

  3. C-24271b647d

    A petition signed by 212 residents asks commissioners to adopt a resolution prohibiting the facility and designate Harrison Township a restricted area for large solar.

    Quoted from page 1
    It asks the Board of County Commissioners to adopt a resolution under ORC 303.62 prohibiting the facility and to designate Harrison Township a restricted area for large solar facilities under ORC 303.58.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, PE-01 · Filed under CO-02, PE-01, PE-07

  4. C-27017a88b6

    Commissioners took no action at the meeting; the Board would decide within the statutory 90 days after the meeting.

    Quoted from page 1
    One commissioner said the Board would decide within the 90 days the statute allows after this meeting

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, PE-01 · Filed under CO-02, PE-01, PE-07

  5. C-33a9601349

    Within 90 days after the county public meeting, the Board of County Commissioners may adopt a resolution prohibiting the facility or limiting its boundaries (ORC 303.62).

    Quoted from page 1
    the Board of County Commissioners may adopt a resolution prohibiting the facility or limiting its boundaries (ORC 303.62)

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02, PE-01 · Filed under CO-02, PE-01, PE-07

  6. C-5d2a9e4a3a

    State siting law in force by the cut-off, as catalogued for OH: (1) Sub. S.B. 52 (134th General Assembly), uncodified Section 4(A), effective 2021-10-11: "SECTION 4. (A) The provisions of this act shall not apply to any application for a certificate, or material amendment to an existing certificate, from the power siting board for a large solar facility" (2) Sub. S.B. 52, uncodified Section 4(B), effective 2021-10-11: "(B) For any large solar facility that meets the requirements of division (A) of this section and has multiple positions in the PJM new services queue under the same legal entity as the applicant, all of the queue positions in effect as of the effective date of this section shall be exempt from the provisions of this act, subject to division (C) of this section" (3) Sub. S.B. 52, uncodified Section 4(C), effective 2021-10-11: "(C) If, after the effective date of this section, an applicant for a large solar facility files an additional new service request with PJM, pertaining to the same facility that is in the new services queue, the application shall be subject to review by the board of county commissioners of the county in which the utility facility is to be located" (4) Sub. S.B. 52, uncodified Section 4(D), effective 2021-10-11: "(D) If, after the effective date of this section, in order to participate in PJM's capacity market, a large solar facility submits a new queue position for an increase in its capacity interconnection rights, the change in capacity interconnection rights shall not subject the facility to the provisions of this act, provided that the change in rights occurs without increasing the facility's nameplat" (5) Sub. S.B. 52, uncodified Section 5; ORC 4906.02, 4906.021, 4906.022, effective 2021-10-11: "SECTION 5. For all power siting board proceedings under which an application for a certificate, or a material amendment to an existing certificate, for an economically significant wind farm, large wind farm, or a large solar facility that has not been found to be in compliance with division (A) of section 4906.06 of the Revised Code by the chairperson of the power siting board or the chairperson's" (6) ORC 303.58(E) (enacted by SB 52, effective 2021-10-11), effective 2021-10-11: "(E) A resolution adopted under this section shall not affect the construction of a utility facility that was presented to the board of county commissioners under section 303.61 of the Revised Code, and the board did not adopt a resolution prohibiting the facility within the time required under section 303.62 of the Revised Code" (7) ORC 303.58-303.60, 4906.101 (SB 52, effective 2021-10-11), effective 2021-10-11: "If a resolution described in this section is adopted and becomes effective under sections 303.58 and 303.59 of the Revised Code, no person shall file, and the power siting board shall not accept, an application for a certificate, or a material amendment to an existing certificate, to construct, operate, or maintain a utility facility in a restricted area where the construction of such a utility fa" (8) ORC 303.61, 303.62, 4906.30, 4906.102, 4906.103 (SB 52, effective 2021-10-11), effective 2021-10-11: "(A) At least ninety days, but not more than three hundred days, prior to applying for a certificate from the power siting board, or a material amendment to an existing certificate, for a utility facility, to be located in whole or in part in the unincorporated area of a county, the person intending to apply shall hold a public meeting in each county where the utility facility is to be located" (9) ORC 303.57(C) (SB 52, effective 2021-10-11), effective 2021-10-11: "(C)(1) "Material amendment" means an amendment to an existing power siting board certificate for the construction, operation, or maintenance of a utility facility that does any of the following: (a) For utility facilities: (i) Changes the facility's generation type from one type of utility facility to another; (ii) Increases the facility's nameplate capacity; (iii) Changes the boundaries of the fa"

    Quoted from page 1
    State siting law in force by the cut-off, as catalogued for OH: (1) Sub. S.B. 52 (134th General Assembly), uncodified Section 4(A), effective 2021-10-11: "SECTION 4. (A) The provisions of this act shall not apply to any application for a certificate, or material amendment to an existing certificate, from the power siting board for a large solar facility" (2) Sub. S.B. 52, uncodified Section 4(B), effective 2021-10-11: "(B) For any large solar facility that meets the requirements of division (A) of this section and has multiple positions in the PJM new services queue under the same legal entity as the applicant, all of the queue positions in effect as of the effective date of this section shall be exempt from the provisions of this act, subject to division (C) of this section" (3) Sub. S.B. 52, uncodified Section 4(C), effective 2021-10-11: "(C) If, after the effective date of this section, an applicant for a large solar facility files an additional new service request with PJM, pertaining to the same facility that is in the new services queue, the application shall be subject to review by the board of county commissioners of the county in which the utility facility is to be located" (4) Sub. S.B. 52, uncodified Section 4(D), effective 2021-10-11: "(D) If, after the effective date of this section, in order to participate in PJM's capacity market, a large solar facility submits a new queue position for an increase in its capacity interconnection rights, the change in capacity interconnection rights shall not subject the facility to the provisions of this act, provided that the change in rights occurs without increasing the facility's nameplat" (5) Sub. S.B. 52, uncodified Section 5; ORC 4906.02, 4906.021, 4906.022, effective 2021-10-11: "SECTION 5. For all power siting board proceedings under which an application for a certificate, or a material amendment to an existing certificate, for an economically significant wind farm, large wind farm, or a large solar facility that has not been found to be in compliance with division (A) of section 4906.06 of the Revised Code by the chairperson of the power siting board or the chairperson's" (6) ORC 303.58(E) (enacted by SB 52, effective 2021-10-11), effective 2021-10-11: "(E) A resolution adopted under this section shall not affect the construction of a utility facility that was presented to the board of county commissioners under section 303.61 of the Revised Code, and the board did not adopt a resolution prohibiting the facility within the time required under section 303.62 of the Revised Code" (7) ORC 303.58-303.60, 4906.101 (SB 52, effective 2021-10-11), effective 2021-10-11: "If a resolution described in this section is adopted and becomes effective under sections 303.58 and 303.59 of the Revised Code, no person shall file, and the power siting board shall not accept, an application for a certificate, or a material amendment to an existing certificate, to construct, operate, or maintain a utility facility in a restricted area where the construction of such a utility fa" (8) ORC 303.61, 303.62, 4906.30, 4906.102, 4906.103 (SB 52, effective 2021-10-11), effective 2021-10-11: "(A) At least ninety days, but not more than three hundred days, prior to applying for a certificate from the power siting board, or a material amendment to an existing certificate, for a utility facility, to be located in whole or in part in the unincorporated area of a county, the person intending to apply shall hold a public meeting in each county where the utility facility is to be located" (9) ORC 303.57(C) (SB 52, effective 2021-10-11), effective 2021-10-11: "(C)(1) "Material amendment" means an amendment to an existing power siting board certificate for the construction, operation, or maintenance of a utility facility that does any of the following: (a) For utility facilities: (i) Changes the facility's generation type from one type of utility facility to another; (ii) Increases the facility's nameplate capacity; (iii) Changes the boundaries of the fa"

    Context check: Local veto and restriction powers: exemptions and grandfathering · CX-0030 · Page 1 · Undated

    Source public_record · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  7. C-68cb5c0292

    ORC 303.57 to 303.62 give the Board of County Commissioners separate powers over large solar facilities, outside the scope of the letter.

    Quoted from page 1
    We note that ORC 303.57 to 303.62 give the Board of County Commissioners separate powers over large solar facilities, which are outside the scope of this letter.

    Zoning Verification - Tamsin Ridge Solar and Storage Project · DR-0022 · Page 1 · 2023-02-14

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under PE-01, PE-07

  8. C-a1e4999eda

    A resolution designating restricted areas under ORC 303.58 would bar an application for a facility within them.

    Quoted from page 1
    a resolution designating restricted areas under ORC 303.58 would bar an application for a

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-01 · Filed under PE-01, PE-07

  9. C-d95cdabeb7

    Under Ohio's SB 52 (effective 2021-10-11) the board of county commissioners may designate restricted areas that bar large solar facilities, and within 90 days of the required county public meeting may prohibit the facility or limit its boundaries; two voting ad hoc local members sit on the Power Siting Board. This power reaches the project: the SB 52 Section 4 PJM exemption does not apply, because position AH1-931 entered window AH1 (closed 2021-09-30); under the operator's published study timing its system impact study could not be complete before 2022-04-30.

    Quoted from page 1
    Under Ohio's SB 52 (effective 2021-10-11) the board of county commissioners may designate restricted areas that bar large solar facilities, and within 90 days of the required county public meeting may prohibit the facility or limit its boundaries; two voting ad hoc local members sit on the Power Siting Board. This power reaches the project: the SB 52 Section 4 PJM exemption does not apply, because position AH1-931 entered window AH1 (closed 2021-09-30); under the operator's published study timing its system impact study could not be complete before 2022-04-30.

    Context check: Local veto and restriction powers: exemptions and grandfathering · CX-0030 · Page 1 · Undated

    Source computed · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

3Permits and requirements

The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.

No requirement is tied to the rows of this report.

4What is missing

The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.

Medium priority (1)

  • IR-a4070979c7 · Medium priority

    Provide the dated record of local and state siting decisions in the region (engine context check) for the project area, or confirm none exists.

    Missing evidence
    Dated record of local and state siting decisions in the region (engine context check)
    Consequence
    Regional Siting Climate is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

5Next steps and agencies

Next steps

  • Re-check county records for any restricted-area or prohibition resolution after 2023-03-28 and track the Commissioners' 90-day decision.
  • Engage county commissioners directly.
  • Confirm adjacent-county and OPSB decisions on solar.

Agencies

  • Carroll County
  • OPSB

6Basis and limits

This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.

It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.

Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.

Versions and data hashes

As the engine and the exporter recorded them. Hashes are SHA-256.

Information cut-off
2023-08-01
Engine version
2.11.0
Prompt version
2026-11-08.1
Rows pack
rows.json sha256 a018ecd7e4703bc1
Federal pack
federal.json sha256 8841c555ff35d20b
State pack
oh.json sha256 d4780705e1f18d09
Local pack
oh_carroll_county.json sha256 905cd3308848e7e8
Data room manifest
0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
Audit chain
valid (19 events)
QA status
PASS_WITH_WARNINGS
Rendered at
2026-11-10T15:42:40+00:00
Run record (annex)
66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
Exporter
Prism/room/exporter 1.4.0

Prism desk report · engine 2.11.0 · prompts 2026-11-08.1 · information cut-off 2023-08-01