Aviation, Glare and Communications: desk report
One row of the risk matrix, EN-05 Aviation, Glare and Communications, in the Environmental Resources section: what the record holds on it.
A desk review of the record as it stood: not a field survey and not a modelled study.
- Information cut-off
- 2023-08-01
- Row in the matrix
- EN-05 Aviation, Glare and Communications
Downloads
This report as a Word file, and the engine's own files for the whole run.
- This reporttamsin-ridge-solar-and-storage-EN-05.docx · Word · 44 KB
- The engine's risk matrixRiskMatrix_TamsinRidgeSolarandStorage.xlsx · Excel · 108 KB
- The engine's permit matrixTamsin Ridge Solar and Storage Permit Matrix.docx · Word · 61 KB
1Finding
Resource is present within area, impact unlikely
up toImpacts likely but may be easily resolved
The engine shows this rating as 1-2
- The rule
Code computed the rating from the assessor's inputs:
present, impact unlikely -> 1
Set by the rule
- Decision
- Released
- Evidence state
- REPORTED · desktop, consultant or developer record
The assessor's comments
Nearest public-use airport (TSO) is about 5 miles southeast. Structures are over 20,000 feet from the runway and under 200 feet, so no FAA Form 7460-1 notice is required. Low-potential (green) glare predicted at two residences and a short segment of Linnet Road; no glare at TSO approaches.
Worst case
If what is pending at the cut-off went badly, the same rule gives a higher rating.
- Scenario
Final layout or tilt changes raise glare at residences R-11 and R-14, requiring vegetative screening or module adjustments.
- Step still pending
- Updated glare analysis on the final layout
- Inputs in the worst case
- Extent peripheral · Avoidable yes · Pathway standard · Impact likely yes
- The rule on the worst case
- worst case: impact_likely=yes -> 2
- Claims that make it plausible
- C-1a3c29d782, C-3a488792dd
2What the record shows
The five inputs
Present: yes
A public-use airport (TSO) is documented about 5 miles southeast (C-22ecd9258b), and low-potential green glare is predicted at two residences and a short segment of Linnet Road (C-1a3c29d782, C-3a488792dd). Contrary absence findings (no yellow/red glare, no TSO approach glare, no microwave path, no private airstrip, no military/radar) cover different receptors and are consistent with this (C-06d00931f7, C-7fb4ed5f9f, C-cf1066cd5b, C-47b8505413, C-4c304fc268).
Cites C-22ecd9258b, C-1a3c29d782, C-3a488792dd, C-06d00931f7, C-7fb4ed5f9f, C-cf1066cd5b, C-47b8505413, C-4c304fc268
Extent: peripheral
All structures are over 20,000 feet from the nearest runway, no protected surface is penetrated (C-698d47b3cd, C-7ae4ad619f), no microwave path crosses the area (C-cf1066cd5b). Only low-potential glare at a few receptors remains (C-1a3c29d782).
Cites C-698d47b3cd, C-7ae4ad619f, C-cf1066cd5b, C-1a3c29d782
Avoidable: yes
No yellow or red glare is predicted (C-06d00931f7); the green glare is minor and no airport surface is affected (C-7ae4ad619f). Layout, tilt or screening can address any residual issue.
Cites C-06d00931f7, C-7ae4ad619f
Pathway: none
No FAA Form 7460-1 notice is required, as structures are beyond 20,000 feet of the runway and under 200 feet (C-698d47b3cd). The ODOT Office of Aviation permit does not apply to an OPSB-certificated facility (C-8022ac270d, OH-AIRPORT). The glare study is already complete.
Cites C-698d47b3cd, C-8022ac270d
Impact likely: no
No glare at TSO approaches, no hazard to airspace, and only low-potential green glare at two residences and a short road segment of limited duration (C-7fb4ed5f9f, C-1a3c29d782, C-3a488792dd). A hazard determination or redesign is not likely.
Cites C-7fb4ed5f9f, C-1a3c29d782, C-3a488792dd
Supporting statements (11)
Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.
C-06d00931f7
No yellow or red glare is predicted at any receptor.
Quoted from page 1 No yellow or red glare at any receptor.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source desktop_study · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-1a3c29d782
Low-potential (green) glare is predicted at two residences, R-11 and R-14, for 5 to 15 minutes on spring and autumn mornings.
Quoted from page 1 low-potential (green) glare at two residences (R-11 and R-14) for 5 to 15 minutes on spring and autumn mornings.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source desktop_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-22ecd9258b
The nearest public-use airport, Carroll County-Tolson Airport (TSO), is about 5 miles southeast of the Project.
Quoted from page 1 The nearest public-use airport is Carroll County-Tolson Airport (TSO), about 5 miles southeast of the Project.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source consultant_memo · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-3a488792dd
Low-potential (green) glare under 10 minutes on a few days a year is predicted on a short segment of Linnet Road; none on SR 43 or Fescue Road.
Quoted from page 1 low-potential (green) glare for under 10 minutes on a few days a year on a short segment of Linnet Road.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source desktop_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-47b8505413
No private airstrip or heliport is within 3 miles of the Project.
Quoted from page 1 No private airstrip or heliport is within 3 miles.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-4c304fc268
No military operations area or radar installation is nearby.
Quoted from page 1 No military operations area or radar installation is nearby.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
Filed under EN-05, EN-09
C-698d47b3cd
All structures are over 20,000 feet from the nearest runway and none exceeds 200 feet, so no FAA Form 7460-1 notice is required.
Quoted from page 1 Every structure is more than 20,000 feet from the nearest runway and none exceeds 200 feet above ground, so no FAA Form 7460-1 notice is required.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-7ae4ad619f
No protected airport surface is penetrated by the proposed structures.
Quoted from page 1 no protected airport surface is penetrated in any case.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source consultant_memo · Claim type absence · Polarity absence · Confidence medium · Quote check exact, 100 of 100
C-7fb4ed5f9f
Glare modeling predicts no glare at the TSO runway approach paths.
Quoted from page 1 TSO approaches: no glare predicted.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source desktop_study · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-8022ac270d
The ODOT Office of Aviation permit does not apply to a facility certificated by the OPSB.
Quoted from page 1 The Ohio Department of Transportation Office of Aviation permit does not apply to a facility certificated by the OPSB
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source consultant_memo · Claim type regulatory · Polarity neutral · Confidence medium · Quote check exact, 100 of 100
C-cf1066cd5b
An FCC licensing records search found no licensed microwave beam path across the Project Area.
Quoted from page 1 A search of FCC licensing records found no licensed microwave beam path across the Project Area.
Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · Page 1 · 2023-04-25
Source desktop_study · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
Filed under EN-05, EN-09
3Permits and requirements
The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.
Federal (1)
Form 7460-1 Notice of Proposed Construction or Alteration
F-FAA77 · Federal Aviation Administration
- Applicability
- Conditional
- Instrument
- 14 CFR Part 77
- Trigger
- Structures or cranes meeting notice criteria near airports or over 200 feet above ground.
- Description
Notice for construction that meets Part 77 notice criteria (for example structures over 200 feet, or within defined distances and slopes of public-use airports). FAA's 2021 glare policy covers solar on federally obligated airports, not off-airport projects.
- Typical timeline
Notice on Form 7460-1 at least 45 days before the start date of construction or the date a construction-permit application is filed, whichever is earliest (14 CFR 77.7(b)); Part 77 sets no FAA decision deadline. A Determination of No Hazard expires 18 months after its effective date unless extended (14 CFR 77.33(b)). Typical: 2 to 4 months for an FAA aeronautical study determination (basis: practice, not stated in the sources).
- As of the cut-off
As of the cut-off: FAA published its interim policy on solar energy systems at federally obligated airports (78 FR 63276). (2013-10-23) FAA's policy on solar energy system projects at federally obligated airports took effect (86 FR 25801), replacing the 2013 interim policy; it covers on-airport systems at towered airports. (2021-05-11)
- Verification
- PACK_PENDING_QUALIFIED_REVIEW
- Source
- pack:federal
- In the permit matrix
- F-FAA77
Legal basis: 4 quotes from dated law
Quoted from the law, page 1 If requested by the FAA, or if you propose any of the following types of construction or alteration, you must file notice with the FAA of: (a) Any construction or alteration that is more than 200 ft. AGL at its site. (b) Any construction or alteration that exceeds an imaginary surface extending outward and upward
Source 14CFR77 · page 1 · version 2023-08-01
Cited for requirement and trigger
In force from 2016-12-30 to 2026-10-07
eCFR versioner: 14 CFR part 77, same text on 2021-10-15, 2022-05-20, 2022-09-12, 2023-04-22, 2023-08-01 and on every amendment date between them; amendment dates 2016-12-30
May be cited on the cut-off date.
Quoted from the law, page 1 a completed FAA Form 7460-1, Notice of Proposed Construction or Alteration. FAA Form 7460-1 is available at FAA regional offices and on the Internet. (b) You must submit this form at least 45 days before the start date of the proposed construction or alteration or the date an application for a construction permit is filed, whichever is earliest.
Source 14CFR77 · page 1 · version 2023-08-01
Cited for requirement (Form 7460-1) and timeline: 45-day notice
In force from 2016-12-30 to 2026-10-07
eCFR versioner: 14 CFR part 77, same text on 2021-10-15, 2022-05-20, 2022-09-12, 2023-04-22, 2023-08-01 and on every amendment date between them; amendment dates 2016-12-30
May be cited on the cut-off date.
Quoted from the law, page 1 Unless extended, revised, or terminated, each Determination of No Hazard to Air Navigation issued under this subpart expires 18 months after the effective date of the determination, or on the date the proposed construction or alteration is abandoned, whichever is earlier.
Source 14CFR77 · page 1 · version 2023-08-01
Cited for timeline: validity of a determination
In force from 2016-12-30 to 2026-10-07
eCFR versioner: 14 CFR part 77, same text on 2021-10-15, 2022-05-20, 2022-09-12, 2023-04-22, 2023-08-01 and on every amendment date between them; amendment dates 2016-12-30
May be cited on the cut-off date.
Quoted from the law, page 1 The policy applies to proposed on-airport solar energy systems at federally-obligated towered
Source 86FR25801 · page 1 · version 2021-05-11
May be cited on the cut-off date.
State (1)
ODOT Office of Aviation permit for a structure that may obstruct air navigation near an airport; not required for a facility holding an OPSB certificate, which is reviewed through the OPSB process
OH-AIRPORT · Ohio Department of Transportation (ODOT), Office of Aviation (permit); Ohio Power Siting Board (OPSB) (certificated facilities, after consulting the Office of Aviation)
- Applicability
- Conditional
- Instrument
- ORC 4561.30 to 4561.39 (Ohio Airport Protection Act); ORC 4561.341; ORC 4906.10(A)(5)
- Trigger
- A structure or object of natural growth that will penetrate, or is reasonably expected to penetrate, a protected surface of an airport open to the public, for a project that has not received an OPSB certificate.
- Description
No person may begin to install a structure or object of natural growth, any part of which will or is reasonably expected to penetrate an airport's clear zone, horizontal, conical, primary, approach or transitional surface, without an ODOT permit. "Airport" means one certified for commercial purposes by ODOT; ODOT's guidance applies the permit to airports open to the public, and a filed FAA Form 7460-1 meets the state application requirement. ODOT grants or denies the permit by deciding whether the height and location would obstruct air navigation. A person who receives an OPSB certificate is not required to apply. Instead, if the Office of Aviation finds an obstruction, it gives the OPSB that determination in writing with either the conditions needed to remove it or a statement that compliance may be waived, and the OPSB must consult the Office.
- Typical timeline
File not less than thirty days nor more than two years before the planned start of installation; the department may waive this period for unforeseen emergencies (ORC 4561.33(B)).
- Version of the law on the cut-off
- As in force from 2022-07-28 (the library text)
- Verification
- PACK_PENDING_QUALIFIED_REVIEW
- Source
- pack:oh.json
- In the permit matrix
- OH-AIRPORT
Legal basis: 8 quotes from dated law
Quoted from the law, page 2 no person shall commence to install any structure or object of natural growth in this state, any part of which will penetrate or is reasonably expected to penetrate into or through any airport's clear zone surface, horizontal surface, conical surface, primary surface, approach surface, or transitional surface without first obtaining a permit from the department of transportation
Source ORC 4561.30 to 4561.39 airport obstructions · page 2 · version 2023-08-01
In force from 2004-01-01 to 2026-10-03, section 4561.31
4561.31: version effective 2004-01-01, still the current version when the page map was checked (2026-10-03)
May be cited on the cut-off date.
Quoted from the law, page 3 Any person who receives a certificate from the power siting board pursuant to section 4906.03 or 4906.10 of the Revised Code on or after October 15, 1991, is not required to apply for a permit from the department under sections 4561.30 to 4561.39 of the Revised Code.
Source ORC 4561.30 to 4561.39 airport obstructions · page 3 · version 2023-08-01
In force from 2004-01-01 to 2026-10-03, section 4561.31
4561.31: version effective 2004-01-01, still the current version when the page map was checked (2026-10-03)
May be cited on the cut-off date.
Quoted from the law, page 1 "Airport" means any airport certified for commercial purposes by the department of transportation. "Airport" does not include a military airport owned by the United States government and used for no commercial purposes.
Source ORC 4561.30 to 4561.39 airport obstructions · page 1 · version 2023-08-01
In force from 1991-10-15 to 2026-10-03, section 4561.30
4561.30: version effective 1991-10-15, still the current version when the page map was checked (2026-10-03)
May be cited on the cut-off date.
Quoted from the law, page 6 An applicant shall file an application not less than thirty days nor more than two years prior to the planned date of commencement of installation or substantial change. This period may be waived by the department for unforeseen emergencies.
Source ORC 4561.30 to 4561.39 airport obstructions · page 6 · version 2023-08-01
In force from 1991-10-15 to 2026-10-03, section 4561.33
4561.33: version effective 1991-10-15, still the current version when the page map was checked (2026-10-03)
May be cited on the cut-off date.
Quoted from the law, page 8 In determining whether to grant or deny a permit, the department shall determine whether the height and location of a structure or object of natural growth, as set forth in the permit application, will be an obstruction to air navigation based upon the rules adopted under section 4561.32 of the Revised Code if installed as proposed.
Source ORC 4561.30 to 4561.39 airport obstructions · page 8 · version 2023-08-01
In force from 1991-10-15 to 2026-10-03, section 4561.34
4561.34: version effective 1991-10-15, still the current version when the page map was checked (2026-10-03)
May be cited on the cut-off date.
Quoted from the law, page 14 if the office determines that the facility constitutes or will constitute an obstruction to air navigation, it shall provide, in writing, this determination and either the terms, conditions, and modifications that are necessary for the applicant to eliminate the obstruction or a statement that compliance with the obstruction standards may be waived, to the power siting board
Source ORC 4561.30 to 4561.39 airport obstructions · page 14 · version 2023-08-01
In force from 1999-06-30 to 2026-10-03, section 4561.341
4561.341: version effective 1999-06-30, still the current version when the page map was checked (2026-10-03)
May be cited on the cut-off date.
Quoted from the law, page 17 determining whether the facility will comply with all rules and standards adopted under section 4561.32 of the Revised Code, the board shall consult with the office of aviation of the division of multi-modal planning and programs of the department of transportation under section 4561.341 of the Revised Code.
Source ORC 4906 Power Siting Board · page 17 · version 2023-08-01
In force from 2021-10-11 to 2025-08-13, section 4906.10
4906.10: version effective 2021-10-11; first change after it 2025-08-14 (Am. Sub. H.B. 15, 136th GA), from codes.ohio.gov version history in archive captures (confirmed_two_sources)
May be cited on the cut-off date.
Quoted from the law, page 1 Additionally, a permit from the Ohio Department of Transportation's Office of Aviation must be obtained prior to the start of any construction on or near airports in Ohio that are open to the public. Filing the 7460-1 with the FAA above fulfills the state permit application requirements as set forth in the Ohio Administrative Code, Section 5501:1.
Source ODOT Office of Aviation airport protection act page · page 1 · version 2022-07-28
May be cited on the cut-off date.
4What is missing
The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.
The run raised no information request for the rows of this report.
5Next steps and agencies
Next steps
- Re-run glare analysis if the layout or module tilt changes.
- Confirm no FAA notice is needed against final structure heights and crane use.
Agencies
- FAA
- OPSB
6Basis and limits
This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.
It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.
Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.
Documents quoted (1)
- Glare, Aviation and Visual Memo - Tamsin Ridge Solar and Storage Project · DR-0015 · 2023-04-25 · page 1
Versions and data hashes
As the engine and the exporter recorded them. Hashes are SHA-256.
- Information cut-off
- 2023-08-01
- Engine version
- 2.11.0
- Prompt version
- 2026-11-08.1
- Rows pack
- rows.json sha256 a018ecd7e4703bc1
- Federal pack
- federal.json sha256 8841c555ff35d20b
- State pack
- oh.json sha256 d4780705e1f18d09
- Local pack
- oh_carroll_county.json sha256 905cd3308848e7e8
- Data room manifest
- 0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
- Audit chain
- valid (19 events)
- QA status
- PASS_WITH_WARNINGS
- Rendered at
- 2026-11-10T15:42:40+00:00
- Run record (annex)
- 66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
- Legal source index