Natural Hazards and Climate Exposure: desk report
One row of the risk matrix, EN-08 Natural Hazards and Climate Exposure, in the Environmental Resources section: what the record holds on it.
A desk review of the record as it stood: not a field survey and not a modelled study.
- Information cut-off
- 2023-08-01
- Row in the matrix
- EN-08 Natural Hazards and Climate Exposure
Downloads
This report as a Word file, and the engine's own files for the whole run.
- This reporttamsin-ridge-solar-and-storage-EN-08.docx · Word · 41 KB
- The engine's risk matrixRiskMatrix_TamsinRidgeSolarandStorage.xlsx · Excel · 108 KB
- The engine's permit matrixTamsin Ridge Solar and Storage Permit Matrix.docx · Word · 61 KB
1Finding
Impacts likely but may be easily resolved
The engine shows this rating as 2
- The rule
Code computed the rating from the assessor's inputs:
impact_likely=yes -> 2
Set by the rule
- Decision
- Released with flags
- The engine's reasons
- Agencies not in the register or the evidence: Carroll County Engineer, FEMA
- Independent assessments split on the category (5 samples: {'2': 4, '1': 1})
- Evidence state
- REPORTED · desktop, consultant or developer record
The assessor's comments
Landowners report floodplain fields flood for a day or two most springs, and Sallow Creek overtopped Linnet Road at the county bridge in the June 2019 flash flood. Seasonal high groundwater may be near the surface in the floodplain. Design wind is 115 mph and snow load 20 psf. No hail or wildfire screen is in the data room.
Worst case
The same rule on the worst case gives no rating above the point.
- Scenario
Flood levels prove higher than mapped, the 14 flood-fringe acres are dropped, and access via Linnet Road and elevated equipment need non-standard design and higher deductibles.
- Step still pending
- Local hydraulic model of Sallow Creek and insurer hail and flood review
- Inputs in the worst case
- Extent peripheral · Avoidable partly · Pathway standard · Impact likely yes
- The rule on the worst case
- worst case (impact_likely=yes -> 2) not above the point
- Claims that make it plausible
- C-75d2a2cad3, C-db721b9fe7, C-9f6b8123d8
2What the record shows
The five inputs
Present: yes
Local flood history beyond FEMA mapping is documented: landowners report floodplain fields flood for a day or two most springs (C-9f6b8123d8) and Sallow Creek overtopped Linnet Road in the June 2019 flash flood (C-db721b9fe7). Seasonal high groundwater may be near the surface in the floodplain (C-05146fd25c). Hail, wildfire and heat are not addressed. The seismic-low finding (C-560f40e113) belongs to EN-02 and does not offset this.
Cites C-9f6b8123d8, C-db721b9fe7, C-05146fd25c, C-560f40e113
Extent: peripheral
Flooding and shallow groundwater are tied to the Sallow Creek floodplain, part of the site; about 14 flood-fringe acres are flagged as possibly dropped (C-75d2a2cad3). Design loads of 115 mph wind and 20 psf snow are standard (C-4f11de30a3).
Cites C-9f6b8123d8, C-75d2a2cad3, C-05146fd25c, C-4f11de30a3
Avoidable: yes
Siting outside the floodplain, dropping the 14 flood-fringe acres if a local hydraulic model shows higher levels (C-75d2a2cad3), and elevated equipment and drainage design answer the documented flood exposure.
Cites C-75d2a2cad3, C-9f6b8123d8
Pathway: standard
No hazard approval is documented. Building code loads and drainage review near the floodplain apply at routine terms; construction stormwater coverage is separate (C-4bf6e9a178). Basins are below dam permit size (C-ebc49abde3).
Cites C-75d2a2cad3, C-4bf6e9a178, C-ebc49abde3
Impact likely: yes
Recurring spring flooding, a flash flood that overtopped the county bridge on Linnet Road, and near-surface seasonal groundwater make a physical or design effect likely if array rows or access routes lie in or near the floodplain (C-9f6b8123d8, C-db721b9fe7, C-05146fd25c, C-75d2a2cad3).
Cites C-9f6b8123d8, C-db721b9fe7, C-05146fd25c, C-75d2a2cad3
Supporting statements (8)
Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.
C-05146fd25c
Free water was met at 6 to 14 feet in 9 borings, mostly perched near Sallow Creek; seasonal high groundwater may be near the surface in the floodplain.
Quoted from page 1 Seasonal high groundwater may be near the surface in the floodplain.
Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15
Source field_study · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100
C-4bf6e9a178
Disturbance over one acre requires Ohio EPA construction stormwater general permit OHC000006 coverage, including an SWP3 and Notice of Intent.
Quoted from page 1 Construction will disturb more than one acre, so the Project needs coverage under Ohio EPA's construction
Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 1 · 2023-06-05
Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-4f11de30a3
Design loads: basic wind speed 115 mph, ground snow load 20 psf, and 0.5-inch radial ice for gen-tie structures.
Quoted from page 1 basic wind speed 115 mph (Risk Category II), ground snow load 20 psf, and 0.5-inch radial ice for the gen-tie structures.
Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15
Source consultant_memo · Claim type study_finding · Polarity neutral · Confidence medium · Quote check exact, 100 of 100
C-560f40e113
Seismic site class C; seismic hazard is low.
Quoted from page 1 Seismic site class C; seismic hazard is low.
Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-75d2a2cad3
Flood fringe array rows should be checked against a local hydraulic model; if flood levels are higher than mapped, those 14 acres may need to be dropped.
Quoted from page 2 if flood levels prove higher than mapped, those 14 acres may need to be dropped.
Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 2 · 2023-06-05
Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence medium · Quote check exact, 100 of 100
C-9f6b8123d8
Landowners report floodplain fields flood for a day or two most springs.
Quoted from page 2 the floodplain fields flood for a day or two most springs.
Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 2 · 2023-06-05
Source consultant_memo · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100
C-db721b9fe7
Landowners report Sallow Creek overtopped Linnet Road at the county bridge in the June 2019 flash flood.
Quoted from page 2 Landowners report that Sallow Creek overtopped Linnet Road at the county bridge during the
Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 2 · 2023-06-05
Source consultant_memo · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100
C-ebc49abde3
Basins have embankments no higher than 6 feet and about 9 acre-feet each, below the size requiring an ODNR dam construction permit.
Quoted from page 1 The basins have embankments no higher than 6 feet and hold about 9 acre-feet each, below the size at which
Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 1 · 2023-06-05
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
3Permits and requirements
The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.
No requirement is tied to the rows of this report.
4What is missing
The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.
Medium priority (3)
IR-96d020deb4 · Medium priority
Provide the hazard or climate risk screen (national hazard index, wildfire risk map, hail or tornado frequency data, lender or insurer screen) for the project area, or confirm none exists.
- Missing evidence
- Hazard or climate risk screen (national hazard index, wildfire risk map, hail or tornado frequency data, lender or insurer screen)
- Consequence
- Natural Hazards and Climate Exposure is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
IR-0011d0e4ed · Medium priority
Provide the design basis report or engineering study (design wind speed, snow and ice loads, module hail rating, stow strategy, design temperature) for the project area, or confirm none exists.
- Missing evidence
- Design basis report or engineering study (design wind speed, snow and ice loads, module hail rating, stow strategy, design temperature)
- Consequence
- Natural Hazards and Climate Exposure is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
IR-248c346d8e · Medium priority
Provide the wildfire hazard zone designation, wildfire protection plan, or local flood, drainage and dam inundation history beyond fema mapping for the project area, or confirm none exists.
- Missing evidence
- Wildfire hazard zone designation, wildfire protection plan, or local flood, drainage and dam inundation history beyond FEMA mapping
- Consequence
- Natural Hazards and Climate Exposure is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
5Next steps and agencies
Next steps
- Keep arrays and equipment out of the flood fringe or run the local hydraulic model; confirm Linnet Road access during floods.
- Request design basis report, insurer hail and wind loss history, and any climate or wildfire screen.
Agencies
- Carroll County Engineer
- Ohio EPA
- FEMA
6Basis and limits
This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.
It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.
Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.
Documents quoted (2)
- Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · 2023-05-15 · page 1
- Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · 2023-06-05 · pages 1, 2
Versions and data hashes
As the engine and the exporter recorded them. Hashes are SHA-256.
- Information cut-off
- 2023-08-01
- Engine version
- 2.11.0
- Prompt version
- 2026-11-08.1
- Rows pack
- rows.json sha256 a018ecd7e4703bc1
- Federal pack
- federal.json sha256 8841c555ff35d20b
- State pack
- oh.json sha256 d4780705e1f18d09
- Local pack
- oh_carroll_county.json sha256 905cd3308848e7e8
- Data room manifest
- 0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
- Audit chain
- valid (19 events)
- QA status
- PASS_WITH_WARNINGS
- Rendered at
- 2026-11-10T15:42:40+00:00
- Run record (annex)
- 66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
- Exporter
- Prism/room/exporter 1.4.0
Prism desk report · engine 2.11.0 · prompts 2026-11-08.1 · information cut-off 2023-08-01