Natural Hazards and Climate Exposure: desk report

Word file

One row of the risk matrix, EN-08 Natural Hazards and Climate Exposure, in the Environmental Resources section: what the record holds on it.

A desk review of the record as it stood: not a field survey and not a modelled study.

Information cut-off
2023-08-01

Downloads

This report as a Word file, and the engine's own files for the whole run.

1Finding

2Impacts likely but may be easily resolved

The engine shows this rating as 2

The rule

Code computed the rating from the assessor's inputs:

impact_likely=yes -> 2

Set by the rule

Decision
Released with flags
The engine's reasons
  • Agencies not in the register or the evidence: Carroll County Engineer, FEMA
  • Independent assessments split on the category (5 samples: {'2': 4, '1': 1})
Evidence state
REPORTED · desktop, consultant or developer record

The assessor's comments

Landowners report floodplain fields flood for a day or two most springs, and Sallow Creek overtopped Linnet Road at the county bridge in the June 2019 flash flood. Seasonal high groundwater may be near the surface in the floodplain. Design wind is 115 mph and snow load 20 psf. No hail or wildfire screen is in the data room.

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

Flood levels prove higher than mapped, the 14 flood-fringe acres are dropped, and access via Linnet Road and elevated equipment need non-standard design and higher deductibles.

Step still pending
Local hydraulic model of Sallow Creek and insurer hail and flood review
Inputs in the worst case
Extent peripheral · Avoidable partly · Pathway standard · Impact likely yes
The rule on the worst case
worst case (impact_likely=yes -> 2) not above the point
Claims that make it plausible
C-75d2a2cad3, C-db721b9fe7, C-9f6b8123d8

2What the record shows

The five inputs

Supporting statements (8)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

  1. C-05146fd25c

    Free water was met at 6 to 14 feet in 9 borings, mostly perched near Sallow Creek; seasonal high groundwater may be near the surface in the floodplain.

    Quoted from page 1
    Seasonal high groundwater may be near the surface in the floodplain.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Cited by EG-01 · Filed under EG-01, EN-08

  2. C-4bf6e9a178

    Disturbance over one acre requires Ohio EPA construction stormwater general permit OHC000006 coverage, including an SWP3 and Notice of Intent.

    Quoted from page 1
    Construction will disturb more than one acre, so the Project needs coverage under Ohio EPA's construction

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 1 · 2023-06-05

    Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-02, PE-02 · Filed under EG-02, PE-02

  3. C-4f11de30a3

    Design loads: basic wind speed 115 mph, ground snow load 20 psf, and 0.5-inch radial ice for gen-tie structures.

    Quoted from page 1
    basic wind speed 115 mph (Risk Category II), ground snow load 20 psf, and 0.5-inch radial ice for the gen-tie structures.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source consultant_memo · Claim type study_finding · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

  4. C-560f40e113

    Seismic site class C; seismic hazard is low.

    Quoted from page 1
    Seismic site class C; seismic hazard is low.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-02 · Filed under EN-02, EN-08

  5. C-75d2a2cad3

    Flood fringe array rows should be checked against a local hydraulic model; if flood levels are higher than mapped, those 14 acres may need to be dropped.

    Quoted from page 2
    if flood levels prove higher than mapped, those 14 acres may need to be dropped.

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 2 · 2023-06-05

    Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

    Cited by AQ-02 · Filed under AQ-02, EN-08

  6. C-9f6b8123d8

    Landowners report floodplain fields flood for a day or two most springs.

    Quoted from page 2
    the floodplain fields flood for a day or two most springs.

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 2 · 2023-06-05

    Source consultant_memo · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Cited by AQ-02 · Filed under AQ-02, EN-08

  7. C-db721b9fe7

    Landowners report Sallow Creek overtopped Linnet Road at the county bridge in the June 2019 flash flood.

    Quoted from page 2
    Landowners report that Sallow Creek overtopped Linnet Road at the county bridge during the

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 2 · 2023-06-05

    Source consultant_memo · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Cited by AQ-02 · Filed under AQ-02, EN-08

  8. C-ebc49abde3

    Basins have embankments no higher than 6 feet and about 9 acre-feet each, below the size requiring an ODNR dam construction permit.

    Quoted from page 1
    The basins have embankments no higher than 6 feet and hold about 9 acre-feet each, below the size at which

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 1 · 2023-06-05

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-02, PE-02 · Filed under EG-02, PE-02

3Permits and requirements

The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.

No requirement is tied to the rows of this report.

4What is missing

The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.

Medium priority (3)

  • IR-96d020deb4 · Medium priority

    Provide the hazard or climate risk screen (national hazard index, wildfire risk map, hail or tornado frequency data, lender or insurer screen) for the project area, or confirm none exists.

    Missing evidence
    Hazard or climate risk screen (national hazard index, wildfire risk map, hail or tornado frequency data, lender or insurer screen)
    Consequence
    Natural Hazards and Climate Exposure is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-0011d0e4ed · Medium priority

    Provide the design basis report or engineering study (design wind speed, snow and ice loads, module hail rating, stow strategy, design temperature) for the project area, or confirm none exists.

    Missing evidence
    Design basis report or engineering study (design wind speed, snow and ice loads, module hail rating, stow strategy, design temperature)
    Consequence
    Natural Hazards and Climate Exposure is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-248c346d8e · Medium priority

    Provide the wildfire hazard zone designation, wildfire protection plan, or local flood, drainage and dam inundation history beyond fema mapping for the project area, or confirm none exists.

    Missing evidence
    Wildfire hazard zone designation, wildfire protection plan, or local flood, drainage and dam inundation history beyond FEMA mapping
    Consequence
    Natural Hazards and Climate Exposure is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

5Next steps and agencies

Next steps

  • Keep arrays and equipment out of the flood fringe or run the local hydraulic model; confirm Linnet Road access during floods.
  • Request design basis report, insurer hail and wind loss history, and any climate or wildfire screen.

Agencies

  • Carroll County Engineer
  • Ohio EPA
  • FEMA

6Basis and limits

This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.

It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.

Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.

Versions and data hashes

As the engine and the exporter recorded them. Hashes are SHA-256.

Information cut-off
2023-08-01
Engine version
2.11.0
Prompt version
2026-11-08.1
Rows pack
rows.json sha256 a018ecd7e4703bc1
Federal pack
federal.json sha256 8841c555ff35d20b
State pack
oh.json sha256 d4780705e1f18d09
Local pack
oh_carroll_county.json sha256 905cd3308848e7e8
Data room manifest
0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
Audit chain
valid (19 events)
QA status
PASS_WITH_WARNINGS
Rendered at
2026-11-10T15:42:40+00:00
Run record (annex)
66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50