Civil Engineering: desk report

Word file

One row of the risk matrix, EG-01 Civil Engineering, in the Engineering Resources section: what the record holds on it.

A desk review of the record as it stood: not a field survey and not a modelled study.

Information cut-off
2023-08-01
Row in the matrix
EG-01 Civil Engineering

Downloads

This report as a Word file, and the engine's own files for the whole run.

1Finding

2Impacts likely but may be easily resolved

up to3Resource is present, likely difficult to address

The engine shows this rating as 2-3

The rule

Code computed the rating from the assessor's inputs:

impact_likely=yes -> 2

Set by the rule

Decision
Released with flags
The engine's reasons
  • Agencies not in the register or the evidence: Ohio EPA, USACE, Carroll County, Harrison Township Trustees
  • The core evidence supports presence, peripheral extent and category 2. Problems: an unsourced 15–25 percent grading band, Fescue Road haul-route content that belongs in EG-03, avoidable labelled 'yes' when the rationale describes mitigation, and an unsupported link between the NWP 14 quote and the S-4 access road.
Evidence state
VERIFIED · field study or agency determination

The assessor's comments

Slopes reach 18 percent in the East Block and Sallow Creek valley walls. 9 of 30 test piles met refusal before 8 feet, mostly on West Block ridges. Soils show moderate corrosivity; groundwater may be near the surface in the floodplain. About 14 acres of array rows lie in the flood fringe. Fescue Road needs temporary widening.

Worst case

If what is pending at the cut-off went badly, the same rule gives a higher rating.

Scenario

Refusal, seen in 30 percent of test piles so far, proves widespread beyond the West Block ridges, requiring non-standard pre-drilling or rock excavation across much of the site.

Step still pending
Topographic survey and further pile load testing during final design
Inputs in the worst case
Extent core · Avoidable partly · Pathway standard · Impact likely yes
The rule on the worst case
worst case: extent=core, avoidable=partly -> 3
Claims that make it plausible
C-e04f4cf7e1, C-b3cb8c76ac

2What the record shows

The five inputs

Supporting statements (11)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

  1. C-05146fd25c

    Free water was met at 6 to 14 feet in 9 borings, mostly perched near Sallow Creek; seasonal high groundwater may be near the surface in the floodplain.

    Quoted from page 1
    Seasonal high groundwater may be near the surface in the floodplain.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Cited by EN-08 · Filed under EG-01, EN-08

  2. C-336bf30d1a

    The S-4 access road crossing is the only planned fill: about 40 linear feet of ephemeral channel (0.02 acre) under NWP 14.

    Quoted from page 3
    about 40 linear feet of ephemeral channel (0.02 acre), within NWP 14 without pre-construction notification.

    Wetland and Stream Delineation Report - Tamsin Ridge Solar and Storage Project · DR-0013 · Page 3 · 2023-05-22

    Source consultant_memo · Claim type extent · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by AQ-01, PE-03 · Filed under AQ-01, EG-01, PE-03

  3. C-39dffbad33

    Sallow Creek floodplain has soft alluvial soils to 5 ft and is outside the layout.

    Quoted from page 2
    Soft to 5 ft; outside layout

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 2 · 2023-05-15

    Source field_study · Claim type study_finding · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

    Filed under AQ-02, EG-01

  4. C-4c4d92f167

    SWP3 covers a fenced area of about 780 acres, of which about 96 acres will be graded.

    Quoted from page 1
    The SWP3 will cover the fenced area of about 780 acres, of which about 96 acres will be graded;

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 1 · 2023-06-05

    Source consultant_memo · Claim type extent · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Cited by EG-02 · Filed under EG-01, EG-02

  5. C-546dd83365

    About 14 acres of array rows are in the flood fringe on Parcels 9 and 10.

    Quoted from page 2
    About 14 acres of array rows are in the flood fringe (Zone AE outside the floodway) on Parcels 9 and 10,

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 2 · 2023-06-05

    Source consultant_memo · Claim type extent · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Cited by AQ-02 · Filed under AQ-02, EG-01

  6. C-55cbc4b507

    Soils are mostly hydrologic soil groups C and D, with moderate to high runoff potential.

    Quoted from page 1
    Soils are mostly hydrologic soil groups C and D (slow infiltration), so runoff potential is moderate to high.

    Stormwater, Floodplain and Drainage Memo - Tamsin Ridge Solar and Storage Project · DR-0019 · Page 1 · 2023-06-05

    Source consultant_memo · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-02 · Filed under EG-01, EG-02

  7. C-8172eb7213

    Fescue Road is a narrow 16-foot township road with two 90-degree turns needing temporary widening for tractor-trailers.

    Quoted from page 1
    Fescue Road is a 16-foot chip-and-seal township road with narrow shoulders and two 90-degree turns where swept path analysis shows that tractor-trailers need temporary widening.

    Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · DR-0020 · Page 1 · 2023-06-19

    Source consultant_memo · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EG-03 · Filed under EG-01, EG-03

  8. C-b3cb8c76ac

    Slopes are 0 to 8 percent in the West Block and up to 18 percent in the East Block and Sallow Creek valley walls.

    Quoted from page 1
    Ground slopes are 0 to 8 percent in the West Block and up to 18 percent in the East Block and on the Sallow Creek valley walls

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  9. C-d106c90db2

    ODNR maps show the abandoned Elsby No. 2 underground coal mine beneath approximately 165 acres of the East Block (Parcels 9, 10 and 12).

    Quoted from page 1
    beneath approximately 165 acres of the East Block (Parcels 9, 10 and 12)

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source consultant_memo · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-02 · Filed under EG-01, EN-02

  10. C-d1c044dc6c

    Resistivity of 1,800 to 3,500 ohm-cm and pH 5.1 to 5.8 indicate moderate corrosivity to buried steel; sulfate exposure is negligible.

    Quoted from page 1
    indicate moderate corrosivity to buried steel; sulfate exposure is negligible.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  11. C-e04f4cf7e1

    Weathered shale and sandstone met at 4 to 11 feet; 9 of 30 test piles (30 percent) met refusal before 8 feet embedment, mostly on West Block ridges.

    Quoted from page 1
    Nine of the 30 test piles (30 percent) met refusal before reaching 8 feet of embedment, mostly on the West Block ridges.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 1 · 2023-05-15

    Source field_study · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

3Permits and requirements

The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.

No requirement is tied to the rows of this report.

4What is missing

The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.

Medium priority (2)

  • IR-29617d468a · Medium priority

    Provide the civil design, grading plan or topographic survey for the project area, or confirm none exists.

    Missing evidence
    Civil design, grading plan or topographic survey
    Consequence
    Civil Engineering is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-295dde238b · Medium priority

    Provide the desktop terrain and soil engineering data (dem slope, soil survey) for the project area, or confirm none exists.

    Missing evidence
    Desktop terrain and soil engineering data (DEM slope, soil survey)
    Consequence
    Civil Engineering is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

5Next steps and agencies

Next steps

  • Complete topographic survey and grading design limiting grading on steeper East Block slopes; run more pile tests on West Block ridges.
  • Obtain floodplain development review for Zone AE array rows, or shift rows out.
  • Agree road-use and widening terms for Fescue Road with the township; confirm NWP 14 crossing with USACE.

Agencies

  • Ohio EPA
  • USACE
  • Carroll County
  • Harrison Township Trustees

6Basis and limits

This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.

It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.

Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.

Versions and data hashes

As the engine and the exporter recorded them. Hashes are SHA-256.

Information cut-off
2023-08-01
Engine version
2.11.0
Prompt version
2026-11-08.1
Rows pack
rows.json sha256 a018ecd7e4703bc1
Federal pack
federal.json sha256 8841c555ff35d20b
State pack
oh.json sha256 d4780705e1f18d09
Local pack
oh_carroll_county.json sha256 905cd3308848e7e8
Data room manifest
0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
Audit chain
valid (19 events)
QA status
PASS_WITH_WARNINGS
Rendered at
2026-11-10T15:42:40+00:00
Run record (annex)
66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
Exporter
Prism/room/exporter 1.4.0

Prism desk report · engine 2.11.0 · prompts 2026-11-08.1 · information cut-off 2023-08-01

Lumerian Labs 2026