Decommissioning and Financial Assurance: desk report

Word file

One row of the risk matrix, PE-06 Decommissioning and Financial Assurance, in the Additional Permitting section: what the record holds on it.

A desk review of the record as it stood: not a field survey and not a modelled study.

Information cut-off
2023-08-01

Downloads

This report as a Word file, and the engine's own files for the whole run.

1Finding

3Resource is present, likely difficult to address

The engine shows this rating as 3

The rule

Code computed the rating from the assessor's inputs:

extent=core, avoidable=partly -> 3

Set by the rule

Decision
Released
Evidence state
REPORTED · desktop, consultant or developer record

The assessor's comments

ORC 4906.21 to 4906.222 require a decommissioning plan and performance bond. Bond equal to the estimate is due before construction, updated every five years, never reduced. Estimate is $11.6 million gross, $5.7 million net of salvage; OPSB treatment of salvage is unsettled. Leases require 36-inch removal and separate landowner security.

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

OPSB requires the gross $11.6 million bond with no salvage credit, and the amount is contested through the OPSB process, with landowner security adding further burden.

Step still pending
OPSB review of the decommissioning plan and bond amount
Inputs in the worst case
Extent core · Avoidable partly · Pathway individual · Impact likely yes
The rule on the worst case
worst case (extent=core, avoidable=partly -> 3) not above the point
Claims that make it plausible
C-7f2ea3298c, C-303a605026, C-b508b5b110, C-0dda429c60

2What the record shows

The five inputs

Supporting statements (11)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

  1. C-00d4067593

    Lease requires lessee to remove facilities to 36 inches depth and restore soil within 12 months after lease end, with security posted.

    Quoted from page 1
    Lessee removes all facilities to a depth of 36 inches and restores the soil within 12 months after

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 1 · 2023-05-30

    Source developer_document · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

  2. C-0dda429c60

    A performance bond with the Board as obligee, equal to the estimate, must be posted before construction, updated every five years and never reduced.

    Quoted from page 1
    Before construction it must post a performance bond, with the Board as obligee, equal to the estimate; the bond is updated every five years and is never reduced.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 1 · 2023-03-20

    Source developer_document · Claim type regulatory · Polarity presence · Confidence medium · Quote check exact, 100 of 100

  3. C-303a605026

    Decommissioning estimate in 2023 dollars is $11.6 million gross, $5.9 million salvage, $5.7 million net.

    Quoted from page 2
    Total $11.6 million $5.9 million $5.7 million

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type cost · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  4. C-4e2febbe42

    The easement ends two years after the project permanently stops operating; grantee must remove above-ground equipment and remove or leave buried cables at grantor's election.

    Quoted from page 1
    ends two (2) years after it permanently stops operating

    Underground Collection Line Easement Agreement - Parcel 7 · DR-0003 · Page 1 · 2022-11-03

    Source public_record · Claim type constraint · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under PE-05, PE-06

  5. C-640e804855

    Plan for battery removal and recycling at end of life in the decommissioning plan.

    Quoted from page 2
    Plan for battery removal and recycling at end of life in the decommissioning plan.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28

    Source consultant_memo · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under EG-04, PE-06

  6. C-7818388af6

    Decommissioning plan and performance bond requirements of ORC 4906.21 to 4906.222 apply.

    Quoted from page 1
    decommissioning plan and performance bond requirements of ORC 4906.21 to 4906.222 apply.

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

  7. C-7f2ea3298c

    Whether OPSB accepts the estimate net of salvage ($5.7 million) or requires gross ($11.6 million) has not been settled.

    Quoted from page 2
    whether OPSB will accept the estimate net of salvage ($5.7 million) or require the gross figure ($11.6 million) has not been settled.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under PE-02, PE-06

  8. C-b508b5b110

    Salvage values rely on volatile scrap prices and could fall well short of the estimate.

    Quoted from page 2
    Scrap prices are volatile, and salvage could fall well short of these figures.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  9. C-b6d40fe4d7

    Ohio law requires an engineer-prepared decommissioning plan submitted to the OPSB at least 60 days before construction, with removal ending within 12 months of cessation.

    Quoted from page 1
    the applicant must submit a comprehensive decommissioning plan prepared by a registered professional

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 1 · 2023-03-20

    Source developer_document · Claim type regulatory · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Filed under PE-02, PE-06

  10. C-e278af1a95

    The leases require removal and restoration within 12 months after they end.

    Quoted from page 1
    The leases also require removal and restoration within 12 months after they end.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 1 · 2023-03-20

    Source developer_document · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under PE-05, PE-06

  11. C-f3daa0fd5a

    The leases require separate security for each landowner, which the bond is intended to satisfy.

    Quoted from page 2
    The leases require separate security for each landowner, which the bond is intended to satisfy.

    Preliminary Decommissioning Plan and Cost Estimate - Tamsin Ridge Solar and Storage Project · DR-0024 · Page 2 · 2023-03-20

    Source developer_document · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under PE-05, PE-06

3Permits and requirements

The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.

No requirement is tied to the rows of this report.

4What is missing

The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.

High priority (2)

  • IR-0a712115cd · High priority

    Provide the financial assurance instrument or terms (bond, letter of credit, escrow, parent guarantee) for the project area, or confirm none exists.

    Missing evidence
    Financial assurance instrument or terms (bond, letter of credit, escrow, parent guarantee)
    Consequence
    Decommissioning and Financial Assurance is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-9c85d7f357 · High priority

    Provide the state or local decommissioning rule or permit condition for the project area, or confirm none exists.

    Missing evidence
    State or local decommissioning rule or permit condition
    Consequence
    Decommissioning and Financial Assurance is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

5Next steps and agencies

Next steps

  • Confirm with OPSB whether the bond may be net of salvage.
  • Align lease security with the OPSB bond and confirm bond form with the surety or lender.
  • Include battery removal and recycling in the decommissioning plan and estimate.

Agencies

  • OPSB

6Basis and limits

This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.

It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.

Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.

Versions and data hashes

As the engine and the exporter recorded them. Hashes are SHA-256.

Information cut-off
2023-08-01
Engine version
2.11.0
Prompt version
2026-11-08.1
Rows pack
rows.json sha256 a018ecd7e4703bc1
Federal pack
federal.json sha256 8841c555ff35d20b
State pack
oh.json sha256 d4780705e1f18d09
Local pack
oh_carroll_county.json sha256 905cd3308848e7e8
Data room manifest
0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
Audit chain
valid (19 events)
QA status
PASS_WITH_WARNINGS
Rendered at
2026-11-10T15:42:40+00:00
Run record (annex)
66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
Exporter
Prism/room/exporter 1.4.0