Skip to content

Battery Storage Fire Safety

EG-04 · Matrix · Engineering Resources

Rating
3Resource is present, likely difficult to address
Why
Individual permit
Worst case
Not above the rating
Evidence
Reported
Cited claims
19
Requirements
0
Requests
4

Rating

3Resource is present, likely difficult to address

The engine shows this rating as 3

The rule

Code computed the rating from the assessor's inputs:

pathway=individual -> 3

Set by the rule

Decision
Released with flags
The engine's reasons
  • Agencies not in the register or the evidence: SFM, Carroll County
Evidence state
Reported · desktop, consultant or developer record

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

The volunteer fire department finds its response capacity inadequate, and OPSB or the fire official requires large-scale testing, added separation and on-site water tanks that govern the layout of the whole yard amid contested fire-risk opposition.

Step still pending
Fire department and county EMA review of the design and response plan, and OPSB review
Inputs in the worst case
Extent core · Avoidable partly · Pathway individual · Impact likely yes
The rule on the worst case
worst case (extent=core, avoidable=partly -> 3) not above the point

Revision

First verdict
weakened
First critique

The inputs and the category 3 result follow the evidence. The weaknesses are an unsupported 'NFPA 855 (2020)' edition, an unsupported SFM agency, and an overstated 'main concern'. Fixing these would not change the category.

Revised once after the first critique. Rating unchanged.

The five inputs

Comments

UL 9540-listed enclosure with unit-level test data and an FMEA hazard analysis. Design follows NFPA 855 (2020) and the Ohio Fire Code, but the governing edition is unconfirmed. No hydrants (nearest water about 4 miles), no internal suppression, no large-scale test. Fire department has not reviewed the design.

Critique

Verdict
upheld
Suggested direction for the rating
same
Summary

The assessment is largely supported by the cited quotes. The pathway, inputs and category 3 are reasonable. Only minor wording problems remain: 'committed' overstates a recommendation, the county agency role is unclear, and the room-for-code-distances inference is unquoted.

Critic model
Luminol

Issues

  1. Severity minor · Kind unsupported_statement

    The cost note says the developer 'has committed to fund' fire department training and equipment. C-2b046d39ca is typed as a recommendation ('Meet the ... agency ... fund training and equipment'), so it shows a proposed action, not a commitment. Say 'proposes' or 'recommends', unless a binding commitment is documented.

    Cites C-2b046d39ca

  2. Severity minor · Kind other

    The agency list names 'Carroll County', but the evidence shows no county permitting role. C-8041623932 says no local approval applies, and C-e96c5bf196 says the local fire official's permit role is unconfirmed. The county fits only as EMA or fire responder. The worst case mentions 'county EMA' but does not cite C-2b046d39ca, the claim that supports it.

    Cites C-8041623932, C-e96c5bf196, C-2b046d39ca

  3. Severity minor · Kind unsupported_statement

    'Room for code distances appears available' is an inference from the 12.6 kW/m2 heat-flux result and the 150 ft setback. No cited quote states the NFPA 855 separation distances or the yard dimensions, so the peripheral extent call is a judgment. A site layout showing the yard footprint against the undermined area would settle it.

    Cites C-76f3e4d772, C-d757c50e61, C-f29a379025

Checks

  • Passed

    rating_has_evidence · blocking

  • Passed

    presence_is_evidenced · not blocking

  • Passed

    counter_evidence_considered · not blocking

  • Passed

    numbers_grounded · not blocking

  • Failed

    agencies_grounded · not blocking

    Agencies not in the register or the evidence: SFM, Carroll County

  • Passed

    cutoff_respected · blocking

  • Passed

    critic_not_refuted · blocking

Evidence (19)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

Arrow keys move the selection. A middle-click opens the claim's own page.

  1. A hazard mitigation analysis using FMEA was completed for the enclosure design.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  2. There are no fire hydrants near the yard; the nearest pressurized water is in Carrollton, about 4 miles away.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 2Exact
  3. Staff expects a fire protection, safety and medical emergency plan prepared with local responders, including the battery system.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  4. The first-due volunteer fire department, about 5 miles away with two engines and one tanker, has not yet reviewed the design or response plan.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 2Exact
  5. Proposed improvements include solar arrays, inverters, collection lines, access roads; Parcel 5 would host a substation and battery storage yard.Standard Flood Hazard Determination - Tamsin Ridge Parcels 5, 9 and 10 · Page 1Exact
  6. Northfold committed to meet the volunteer fire department and county EMA on the emergency response plan and fund training and equipment.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  7. Design follows NFPA 855 (2020 edition) and the Ohio Fire Code energy storage provisions as adopted by the State Fire Marshal.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  8. The selected enclosure is listed to UL 9540 as an energy storage system.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  9. Opponents' most frequent concern was fire risk from the battery storage yard and volunteer fire department response capacity.Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · Page 1Exact
  10. The OPSB application must include a fire protection, safety and medical emergency plan developed with local responders.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  11. The BESS yard is 150 feet from the nearest property line and 610 feet from the nearest residence (R-6).Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 2Exact
  12. No local zoning, conditional use, variance or site plan approval is required, and no local setback, height or screening standard applies to the proposed facility.Zoning Verification - Tamsin Ridge Solar and Storage Project · Page 1Exact
  13. There is no internal fire suppression in the enclosures; design relies on containment, spacing, explosion control and defensive firefighting.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  14. No large-scale fire test beyond UL 9540A has been performed for this enclosure.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  15. In the UL 9540A unit-level test, thermal runaway in one module did not spread to adjacent modules and no flaming occurred outside the enclosure.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  16. Heat flux modeling of a single fully involved enclosure shows less than 12.6 kW per square meter at the fence and adjacent enclosure rows.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 2Exact
  17. Staff will treat the battery system as part of the generating facility.OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · Page 1Exact
  18. The governing code edition and whether the local fire code official will require a construction permit for an OPSB-certificated facility have not been confirmed.Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · Page 1Exact
  19. The substation, BESS yard and inverters must not be built over the undermined area.Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · Page 2Exact

Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge

C-00c5859e81 · Page 1 of 2 · DR-0014

Open the claim, C-00c5859e81

A hazard mitigation analysis using FMEA was completed for the enclosure design.

Quote check Exact · Placed normalised · The quote matches the page once line breaks, hyphenation, case and punctuation are set aside, as the engine's matcher compares text. The marked words are the page's own. · Read as native

Tallis Fire Engineering, LLC Fire protection engineering for energy storage | Pittsburgh, Pennsylvania Battery Energy Storage System Fire Safety Narrative Tamsin Ridge Solar and Storage Project, Carroll County, Ohio Prepared for Northfold Energy Partners, LLC. Report TFE-2306. June 28, 2023. 1. System The battery energy storage system (BESS) is rated 60 MW / 240 MWh. It consists of 60 outdoor enclosures of lithium iron phosphate (LFP) batteries, 4 MWh each, with 20 power conversion systems, in a fenced yard of about 6 acres beside the project substation on Parcel 5. Each enclosure has its own battery management system, cooling, gas detection and explosion control. 2. Listing and test evidence The selected enclosure is listed to UL 9540 as an energy storage system. UL 9540A test reports were reviewed at cell, module and unit level. In the unit-level test, thermal runaway started in one module did not spread to adjacent modules, no flaming outside the enclosure was observed, and surface temperatures of the neighboring enclosure targets stayed below the limits. The cell-level test recorded a lower flammability limit of the vent gas and a gas composition used in the explosion control design. 3. Codes The design follows NFPA 855 (2020 edition) and the energy storage provisions of the Ohio Fire Code as adopted by the State Fire Marshal. The edition that will govern, and whether the local fire code official will require a construction permit for a facility certificated by the OPSB, have not been confirmed. The OPSB application must include a fire protection, safety and medical emergency plan developed with local responders. 4. Hazard mitigation analysis Quote starts. A hazard mitigation analysis using failure modes and effects analysis (FMEA) was completed for the enclosure design. Quote ends. It addresses thermal runaway, failure of the battery management system, cooling failure, gas release and deflagration, and external fire. Each enclosure has gas detection for hydrogen and carbon monoxide that starts mechanical ventilation to keep gas below 25 percent of the lower flammability limit (NFPA 69), with deflagration vent panels on the roof (NFPA 68) as backup. There is no internal fire suppression: the enclosure design relies on containment, spacing and explosion control, and on a defensive firefighting approach. No large-scale fire test beyond UL 9540A has been performed for this enclosure; the manufacturer relies on the UL 9540A unit-level test. Tallis Fire Engineering, LLC - Report TFE-2306 Page 1 of 2

The outline marks where the quote begins on the page.

Page 1 of Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge
  1. C-00c5859e81

    A hazard mitigation analysis using FMEA was completed for the enclosure design.

    Quoted from page 1
    A hazard mitigation analysis using failure modes and effects analysis (FMEA) was completed for the enclosure design.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

  2. C-04a3f6e338

    There are no fire hydrants near the yard; the nearest pressurized water is in Carrollton, about 4 miles away.

    Quoted from page 2
    There are no fire hydrants in the area; the nearest pressurized water is in Carrollton, about 4 miles away.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by AQ-03 · Filed under AQ-03, EG-04

  3. C-05d57cf46e

    Staff expects a fire protection, safety and medical emergency plan prepared with local responders, including the battery system.

    Quoted from page 1
    A fire protection, safety and medical emergency plan prepared with local responders, including the battery

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  4. C-08b9d4306e

    The first-due volunteer fire department, about 5 miles away with two engines and one tanker, has not yet reviewed the design or response plan.

    Quoted from page 2
    The first-due fire department is a volunteer department about 5 miles away with two engines and one tanker. It has not yet reviewed the design or the response plan.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28

    Source consultant_memo · Claim type data_gap · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

  5. C-0caa870c61

    Proposed improvements include solar arrays, inverters, collection lines, access roads; Parcel 5 would host a substation and battery storage yard.

    Quoted from page 1
    Proposed improvements: solar arrays, inverters, collection lines, access roads; on Parcel 5 a substation and battery storage yard.

    Standard Flood Hazard Determination - Tamsin Ridge Parcels 5, 9 and 10 · DR-0009 · Page 1 · 2023-03-15

    Source consultant_memo · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under EG-04, EN-01, PE-03

  6. C-2b046d39ca

    Northfold committed to meet the volunteer fire department and county EMA on the emergency response plan and fund training and equipment.

    Quoted from page 1
    Meet the volunteer fire department and the county emergency management agency on the emergency response plan; fund training and equipment.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  7. C-5162b7c0aa

    Design follows NFPA 855 (2020 edition) and the Ohio Fire Code energy storage provisions as adopted by the State Fire Marshal.

    Quoted from page 1
    The design follows NFPA 855 (2020 edition) and the energy storage provisions of the Ohio Fire Code as adopted by the State Fire Marshal.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source consultant_memo · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  8. C-5e6f39a39c

    The selected enclosure is listed to UL 9540 as an energy storage system.

    Quoted from page 1
    The selected enclosure is listed to UL 9540 as an energy storage system.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100

  9. C-6bdcc9fa85

    Opponents' most frequent concern was fire risk from the battery storage yard and volunteer fire department response capacity.

    Quoted from page 1
    Fire risk from the battery storage yard and the response capacity of the volunteer fire department.

    Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02 · Filed under CO-02, EG-04

  10. C-6bf1273c36

    The OPSB application must include a fire protection, safety and medical emergency plan developed with local responders.

    Quoted from page 1
    The OPSB application must include a fire protection, safety and medical emergency plan developed with local responders.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EG-04, PE-02

  11. C-76f3e4d772

    The BESS yard is 150 feet from the nearest property line and 610 feet from the nearest residence (R-6).

    Quoted from page 2
    The yard is 150 feet from the nearest property line and 610 feet from the nearest residence (R-6).

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28

    Source consultant_memo · Claim type study_finding · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under CO-02, EG-04

  12. C-8041623932

    No local zoning, conditional use, variance or site plan approval is required, and no local setback, height or screening standard applies to the proposed facility.

    Quoted from page 1
    No local zoning permit, conditional use permit, variance or site plan approval is therefore required for the proposed facility, and no local setback, height or screening standard applies to it.

    Zoning Verification - Tamsin Ridge Solar and Storage Project · DR-0022 · Page 1 · 2023-02-14

    Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-01, VI-01 · Filed under EG-04, PE-01, VI-01

  13. C-9775cc58ba

    There is no internal fire suppression in the enclosures; design relies on containment, spacing, explosion control and defensive firefighting.

    Quoted from page 1
    There is no internal fire suppression: the enclosure design relies on containment, spacing and explosion control, and on a defensive firefighting approach.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

  14. C-b6407da087

    No large-scale fire test beyond UL 9540A has been performed for this enclosure.

    Quoted from page 1
    No large-scale fire test beyond UL 9540A has been performed for this enclosure

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

  15. C-ce7cc27a08

    In the UL 9540A unit-level test, thermal runaway in one module did not spread to adjacent modules and no flaming occurred outside the enclosure.

    Quoted from page 1
    thermal runaway started in one module did not spread to adjacent modules, no flaming outside the enclosure was observed

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source field_study · Claim type study_finding · Polarity presence · Confidence medium · Quote check exact, 100 of 100

  16. C-d757c50e61

    Heat flux modeling of a single fully involved enclosure shows less than 12.6 kW per square meter at the fence and adjacent enclosure rows.

    Quoted from page 2
    shows less than 12.6 kW per square meter at the fence and at the adjacent enclosure rows

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28

    Source consultant_memo · Claim type study_finding · Polarity absence · Confidence high · Quote check exact, 100 of 100

  17. C-e7f77313ec

    Staff will treat the battery system as part of the generating facility.

    Quoted from page 1
    Staff will treat the battery system as part of the generating facility.

    OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28

    Source agency_determination · Claim type agency_position · Polarity neutral · Confidence medium · Quote check exact, 100 of 100

    Cited by PE-02 · Filed under EG-04, PE-02

  18. C-e96c5bf196

    The governing code edition and whether the local fire code official will require a construction permit for an OPSB-certificated facility have not been confirmed.

    Quoted from page 1
    The edition that will govern, and whether the local fire code official will require a construction permit for a facility certificated by the OPSB, have not been confirmed.

    Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28

    Source consultant_memo · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100

    Filed under EG-04, PE-01

  19. C-f29a379025

    The substation, BESS yard and inverters must not be built over the undermined area.

    Quoted from page 2
    The substation, the BESS yard and the inverters must not be built over the undermined area.

    Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 2 · 2023-05-15

    Source consultant_memo · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-02 · Filed under EG-04, EN-02

Requirements and permits

The requirements the assessor tied to this row, by level. Each quote from dated law is shown with its source.

No requirement is tied to this row.

Information requests

  • IR-5947855eaa · High priority

    Provide the ul 9540 listing and ul 9540a test reports (cell, module, unit and installation level) for the project area, or confirm none exists.

    Missing evidence
    UL 9540 listing and UL 9540A test reports (cell, module, unit and installation level)
    Consequence
    Battery Storage Fire Safety is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-debe8f99e4 · High priority

    Provide the hazard mitigation analysis, fire risk assessment or explosion control study for the project area, or confirm none exists.

    Missing evidence
    Hazard mitigation analysis, fire risk assessment or explosion control study
    Consequence
    Battery Storage Fire Safety is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-03be7e4172 · High priority

    Provide the emergency response plan or fire department and fire marshal correspondence for the project area, or confirm none exists.

    Missing evidence
    Emergency response plan or fire department and fire marshal correspondence
    Consequence
    Battery Storage Fire Safety is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-eb247a9fcd · High priority

    Provide the bess ordinance, moratorium or fire code adoption record for the project area, or confirm none exists.

    Missing evidence
    BESS ordinance, moratorium or fire code adoption record
    Consequence
    Battery Storage Fire Safety is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

Next steps

  • Confirm governing fire code edition and whether the local fire official requires a permit for the OPSB-certificated facility.
  • Meet the volunteer fire department and county EMA early; finalize the emergency response plan and plan on-site water storage.
  • Evaluate need for large-scale fire testing.

Agencies

  • OPSB
  • SFM
  • Carroll County

Cost and impact

Impact
C, S
Potential cost level
M-H
Why

Likely on-site fire water supply and possible large-scale testing; the developer has committed to fund fire department training and equipment (C-2b046d39ca). Schedule exposure from OPSB review amid fire-risk opposition.

Impact: C = cost, S = schedule. Potential cost level: L, L-M, M, M-H, H (relative to a utility-scale solar budget).

Lumerian Labs 2026