Title and site control report

Word file

Whether the developer has, or can get, the land rights the layout needs: leases and options and when they expire, parcels not yet under control, easements, severed mineral rights and title encumbrances.

A desk review of the record as it stood: not a field survey and not a modelled study.

Information cut-off
2023-08-01

Downloads

This report as a Word file, and the engine's own files for the whole run.

1Finding

3Resource is present, likely difficult to address

The engine shows this rating as 3

The rule

Code computed the rating from the assessor's inputs:

extent=core, avoidable=partly -> 3

Set by the rule

Decision
Released with flags
The engine's reasons
  • Uncited absence claims to weigh: C-f77ef514cf (no record in the annex)
  • Numbers not found in cited evidence: 31.0
  • Agencies not in the register or the evidence: Carroll County
Evidence state
REPORTED · desktop, consultant or developer record

The assessor's comments

Options cover 12 of the 14 parcels (1,063.4 acres). Parcel 11 (31.0 acres) is unleased, needed for collection and East Block access; its trustee declined the option twice. Brenwick accommodation agreement is unsigned; its second pad overlaps about 9 acres of array. Parcel 9 SNDA and coal reservation remain open.

Worst case

The same rule on the worst case gives no rating above the point.

Scenario

The Parcel 11 trustee holds out with no condemnation available, and Brenwick will not waive its second pad, removing array area and forcing a road right-of-way collection route and access redesign.

Step still pending
Parcel 11 negotiation and Brenwick accommodation agreement
Inputs in the worst case
Extent core · Avoidable partly · Pathway individual · Impact likely yes
The rule on the worst case
worst case (extent=core, avoidable=partly -> 3) not above the point

2What the record shows

The five inputs

Supporting statements (20)

Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.

  1. C-04c97c05c7

    Site control is through option-to-lease agreements on 12 of 14 parcels (1,063.4 acres) plus a recorded collection line easement on Parcel 7.

    Quoted from page 1
    holds option-to-lease agreements on 12 of the 14 parcels (1,063.4 acres) and a

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 1 · 2023-05-30

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  2. C-1f788fe1e5

    Option-to-lease agreements cover 12 parcels and a recorded collection line easement covers Parcel 7.

    Quoted from page 1
    Option-to-lease agreements cover 12 parcels, a recorded collection line easement covers Parcel 7

    Tamsin Ridge Solar and Storage Project - Project Description · DR-0001 · Page 1 · 2023-06-12

    Source developer_document · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  3. C-2a27cb9782

    No setback waivers have been requested because no local or state setback applies to the solar facility.

    Quoted from page 2
    No setback waivers have been requested, because no local or state setback applies to the solar facility.

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by PE-01 · Filed under PE-01, PE-05

  4. C-2a9dd4b09a

    Requires an SNDA from Carrow Savings Bank for the Parcel 9 mortgage.

    Quoted from page 1
    Record a subordination, non-disturbance and attornment agreement from Carrow Savings Bank as to the

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 1 · 2023-04-18

    Source public_record · Claim type constraint · Polarity neutral · Confidence high · Quote check exact, 100 of 100

  5. C-343e9b9832

    Coal beneath Parcel 9 was largely mined out by the Elsby No. 2 Mine.

    Quoted from page 2
    The coal was largely mined out by the Elsby No. 2 Mine

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-02

  6. C-3ce7653be3

    Parcel 11 (31 acres) is not under any agreement.

    Quoted from page 2
    Not under agreement (Parcel 11, acres) | 31

    Parcel Schedule 2023-07-14 · DR-0005 · Page 2 · 2023-07-14

    Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

  7. C-489cabb421

    Parcel 11 lies between the West and East Blocks; the planned collection route and East Block access road cross it.

    Quoted from page 2
    The planned collection route and

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence low · Quote check exact, 100 of 100

    Filed under EN-01, PE-05

  8. C-4c5acf992f

    A county right-of-way permit is needed for any collection line in the Linnet Road right-of-way.

    Quoted from page 2
    A county right-of-way permit for any collection line in the Linnet Road right-of-way.

    Traffic and Access Memo - Tamsin Ridge Solar and Storage Project · DR-0020 · Page 2 · 2023-06-19

    Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EG-03, PE-05

  9. C-579694c789

    A 1912 deed severed Parcel 9 coal and reserved the right to mine it by underground methods without liability for surface damage.

    Quoted from page 2
    A 1912 deed severed the coal beneath Parcel 9 and reserved the right to mine it

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source public_record · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-02, PE-05

  10. C-61e6db1965

    The Parcel 11 trustee has declined the standard option twice and asked for a purchase price well above appraisal.

    Quoted from page 2
    The trustee has declined the standard option twice and asked for a

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by CO-02 · Filed under CO-02, PE-05

  11. C-7d33945087

    The lessee's planned second pad on Parcel 2 overlaps about 9 acres of the array layout.

    Quoted from page 2
    The lessee's planned second pad on Parcel 2 overlaps about 9 acres of the

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type presence · Polarity presence · Confidence low · Quote check exact, 100 of 100

    Cited by EN-01 · Filed under EN-01, EN-02, PE-05

  12. C-7dce4e6e67

    Without Parcel 11, the collection line would follow Linnet Road right-of-way about 1.3 miles, needing a county right-of-way permit and adding cost.

    Quoted from page 2
    the collection line would follow Linnet Road in the

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Filed under EG-03, PE-05

  13. C-9099731d6e

    An accommodation agreement with Brenwick is in draft and not signed; until then a lender will see an unsubordinated surface use right.

    Quoted from page 2
    in draft and not signed. Until it is, a lender will see an unsubordinated surface use right.

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

  14. C-9dcc852809

    No severed mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found.

    Quoted from page 3
    No mineral estate other than coal (Parcel 9) and oil and gas (Parcels 2 and 5) was found severed.

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 3 · 2023-04-18

    Source public_record · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-02 · Filed under EN-02, PE-05

  15. C-b22b20654d

    Memoranda of the solar leases for Parcels 2, 5 and 9 must still be recorded.

    Quoted from page 1
    Record memoranda of the solar leases for Parcels 2, 5 and 9, executed and acknowledged by the owners of

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 1 · 2023-04-18

    Source public_record · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

  16. C-cd08e1f358

    Parcel 11 (Okerlund Family Trust) has no agreement, in negotiation, and is needed for collection route and East Block access.

    Quoted from page 1
    None (in negotiation) | No | No | Needed for collection route and East Block access

    Parcel Schedule 2023-07-14 · DR-0005 · Page 1 · 2023-07-14

    Source developer_document · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-01, PE-05

  17. C-d257ecfe8e

    The easement crosses the Calder Gathering Company natural gas gathering line, requiring the grantee to obtain a written crossing agreement and keep required clearance.

    Quoted from page 1
    Grantee will obtain that company's written crossing agreement and keep the clearance it requires.

    Underground Collection Line Easement Agreement - Parcel 7 · DR-0003 · Page 1 · 2022-11-03

    Source public_record · Claim type constraint · Polarity presence · Confidence medium · Quote check exact, 100 of 100

    Cited by EN-01, PE-03 · Filed under EN-01, PE-03, PE-05

  18. C-dcf3900993

    An oil and gas lease to Brenwick Exploration, with pooled unit, allows surface use for wells, pads, roads, pipelines and tanks on Parcels 2 and 5.

    Quoted from page 2
    surface as is reasonably necessary for wells, pads, roads, pipelines and tanks. Affects Parcels 2 and 5.

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 2 · 2023-04-18

    Source public_record · Claim type presence · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Cited by EN-01 · Filed under EN-01, EN-02, PE-05

  19. C-ebcacfde9b

    No condemnation power is available to the Project.

    Quoted from page 2
    No condemnation power is available to the Project.

    Option and Lease Summary - Tamsin Ridge Solar and Storage Project · DR-0004 · Page 2 · 2023-05-30

    Source developer_document · Claim type constraint · Polarity presence · Confidence low · Quote check exact, 100 of 100

  20. C-faaf963eae

    An accommodation agreement or partial surface release from Brenwick Exploration is required for oil and gas lease areas to be occupied by the solar facility; otherwise no affirmative coverage.

    Quoted from page 1
    Record an accommodation agreement, or a partial release of surface rights, from Brenwick Exploration, LLC

    Commitment for Title Insurance No. ATA-23-0418 (Parcels 2, 5 and 9) · DR-0006 · Page 1 · 2023-04-18

    Source public_record · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100

    Filed under EN-02, PE-05

3Permits and requirements

The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.

No requirement is tied to the rows of this report.

4What is missing

The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.

High priority (2)

  • IR-7d328a6772 · High priority

    Provide the mineral ownership or surface-use review for the project area, or confirm none exists.

    Missing evidence
    Mineral ownership or surface-use review
    Consequence
    Site Control and Land Rights is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness
  • IR-5f0015e952 · High priority

    Provide the parcel control table or site control summary for the project area, or confirm none exists.

    Missing evidence
    Parcel control table or site control summary
    Consequence
    Site Control and Land Rights is rated on partial evidence without it.
    Blocks the decision
    No
    Raised by
    completeness

5Next steps and agencies

Next steps

  • Resolve Parcel 11 by negotiation, or confirm the Linnet Road alternative (county right-of-way permit) and East Block access.
  • Execute the Brenwick accommodation agreement, the Parcel 9 SNDA and memoranda of lease.
  • Build a parcel control table with option expiry dates against the COD schedule.

Agencies

  • Carroll County

6Basis and limits

This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.

It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.

Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.

Documents quoted (6)

Versions and data hashes

As the engine and the exporter recorded them. Hashes are SHA-256.

Information cut-off
2023-08-01
Engine version
2.11.0
Prompt version
2026-11-08.1
Rows pack
rows.json sha256 a018ecd7e4703bc1
Federal pack
federal.json sha256 8841c555ff35d20b
State pack
oh.json sha256 d4780705e1f18d09
Local pack
oh_carroll_county.json sha256 905cd3308848e7e8
Data room manifest
0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
Audit chain
valid (19 events)
QA status
PASS_WITH_WARNINGS
Rendered at
2026-11-10T15:42:40+00:00
Run record (annex)
66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
Exporter
Prism/room/exporter 1.4.0

Prism desk report · engine 2.11.0 · prompts 2026-11-08.1 · information cut-off 2023-08-01

Lumerian Labs 2026