Battery Storage Fire Safety: desk report
One row of the risk matrix, EG-04 Battery Storage Fire Safety, in the Engineering Resources section: what the record holds on it.
A desk review of the record as it stood: not a field survey and not a modelled study.
- Information cut-off
- 2023-08-01
- Row in the matrix
- EG-04 Battery Storage Fire Safety
Downloads
This report as a Word file, and the engine's own files for the whole run.
- This reporttamsin-ridge-solar-and-storage-EG-04.docx · Word · 43 KB
- The engine's risk matrixRiskMatrix_TamsinRidgeSolarandStorage.xlsx · Excel · 108 KB
- The engine's permit matrixTamsin Ridge Solar and Storage Permit Matrix.docx · Word · 61 KB
1Finding
Resource is present, likely difficult to address
The engine shows this rating as 3
- The rule
Code computed the rating from the assessor's inputs:
pathway=individual -> 3
Set by the rule
- Decision
- Released with flags
- The engine's reasons
- Agencies not in the register or the evidence: SFM, Carroll County
- Evidence state
- REPORTED · desktop, consultant or developer record
The assessor's comments
UL 9540-listed enclosure with unit-level test data and an FMEA hazard analysis. Design follows NFPA 855 (2020) and the Ohio Fire Code, but the governing edition is unconfirmed. No hydrants (nearest water about 4 miles), no internal suppression, no large-scale test. Fire department has not reviewed the design.
Worst case
The same rule on the worst case gives no rating above the point.
- Scenario
The volunteer fire department finds its response capacity inadequate, and OPSB or the fire official requires large-scale testing, added separation and on-site water tanks that govern the layout of the whole yard amid contested fire-risk opposition.
- Step still pending
- Fire department and county EMA review of the design and response plan, and OPSB review
- Inputs in the worst case
- Extent core · Avoidable partly · Pathway individual · Impact likely yes
- The rule on the worst case
- worst case (extent=core, avoidable=partly -> 3) not above the point
- Claims that make it plausible
- C-08b9d4306e, C-04a3f6e338, C-b6407da087, C-6bdcc9fa85, C-9775cc58ba
2What the record shows
The five inputs
Present: yes
Project includes battery storage: BESS yard proposed on Parcel 5 (C-0caa870c61) with a UL 9540-listed enclosure selected (C-5e6f39a39c). The zoning verification (C-8041623932) says no local zoning or setback standard applies; this does not remove fire code or OPSB requirements.
Cites C-0caa870c61, C-5e6f39a39c, C-8041623932
Extent: peripheral
BESS is a defined yard 150 feet from the nearest property line, with heat flux below 12.6 kW per square meter at the fence and adjacent rows (C-76f3e4d772, C-d757c50e61), so room for code distances appears available. Water and response gaps (C-04a3f6e338, C-08b9d4306e) are not shown to make the whole area unbuildable. The yard cannot sit over the undermined area (C-f29a379025).
Cites C-76f3e4d772, C-d757c50e61, C-04a3f6e338, C-08b9d4306e, C-f29a379025
Avoidable: partly
UL 9540 listing, a unit-level test showing no module-to-module propagation and an FMEA hazard mitigation analysis exist (C-5e6f39a39c, C-ce7cc27a08, C-00c5859e81). But no hydrants nearby (C-04a3f6e338), no internal suppression (C-9775cc58ba), no large-scale test beyond UL 9540A (C-b6407da087), a fire department that has not reviewed the design (C-08b9d4306e) and an unconfirmed governing code edition (C-e96c5bf196) mean measures beyond standard design are likely. Design cites NFPA 855 (2020) and the Ohio Fire Code (C-5162b7c0aa).
Cites C-5e6f39a39c, C-ce7cc27a08, C-00c5859e81, C-04a3f6e338, C-9775cc58ba, C-b6407da087, C-08b9d4306e, C-e96c5bf196, C-5162b7c0aa
Pathway: individual
OPSB staff treats the BESS as part of the generating facility and expects a fire protection, safety and medical emergency plan with local responders (C-e7f77313ec, C-05d57cf46e, C-6bf1273c36). Opponents raised battery fire risk and volunteer fire department response capacity (C-6bdcc9fa85), and fire department review is outstanding (C-08b9d4306e). A state-level review with documented fire-risk opposition fits individual. Whether the local fire official requires a permit is unconfirmed (C-e96c5bf196).
Cites C-e7f77313ec, C-05d57cf46e, C-6bf1273c36, C-6bdcc9fa85, C-08b9d4306e, C-e96c5bf196
Impact likely: yes
No hydrants in the area and nearest pressurized water about 4 miles away (C-04a3f6e338); design relies on defensive firefighting with no internal suppression (C-9775cc58ba), so on-site water storage or similar physical measures are likely. No large-scale fire test beyond UL 9540A exists (C-b6407da087).
Cites C-04a3f6e338, C-9775cc58ba, C-b6407da087
Supporting statements (19)
Each claim the row cites: the statement in the assessor's words, then the quote the engine found on the page.
C-00c5859e81
A hazard mitigation analysis using FMEA was completed for the enclosure design.
Quoted from page 1 A hazard mitigation analysis using failure modes and effects analysis (FMEA) was completed for the enclosure design.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-04a3f6e338
There are no fire hydrants near the yard; the nearest pressurized water is in Carrollton, about 4 miles away.
Quoted from page 2 There are no fire hydrants in the area; the nearest pressurized water is in Carrollton, about 4 miles away.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-05d57cf46e
Staff expects a fire protection, safety and medical emergency plan prepared with local responders, including the battery system.
Quoted from page 1 A fire protection, safety and medical emergency plan prepared with local responders, including the battery
OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28
Source agency_determination · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-08b9d4306e
The first-due volunteer fire department, about 5 miles away with two engines and one tanker, has not yet reviewed the design or response plan.
Quoted from page 2 The first-due fire department is a volunteer department about 5 miles away with two engines and one tanker. It has not yet reviewed the design or the response plan.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28
Source consultant_memo · Claim type data_gap · Polarity neutral · Confidence medium · Quote check exact, 100 of 100
C-0caa870c61
Proposed improvements include solar arrays, inverters, collection lines, access roads; Parcel 5 would host a substation and battery storage yard.
Quoted from page 1 Proposed improvements: solar arrays, inverters, collection lines, access roads; on Parcel 5 a substation and battery storage yard.
Standard Flood Hazard Determination - Tamsin Ridge Parcels 5, 9 and 10 · DR-0009 · Page 1 · 2023-03-15
Source consultant_memo · Claim type project_fact · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-2b046d39ca
Northfold committed to meet the volunteer fire department and county EMA on the emergency response plan and fund training and equipment.
Quoted from page 1 Meet the volunteer fire department and the county emergency management agency on the emergency response plan; fund training and equipment.
Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12
Source developer_document · Claim type recommendation · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-5162b7c0aa
Design follows NFPA 855 (2020 edition) and the Ohio Fire Code energy storage provisions as adopted by the State Fire Marshal.
Quoted from page 1 The design follows NFPA 855 (2020 edition) and the energy storage provisions of the Ohio Fire Code as adopted by the State Fire Marshal.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source consultant_memo · Claim type regulatory · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-5e6f39a39c
The selected enclosure is listed to UL 9540 as an energy storage system.
Quoted from page 1 The selected enclosure is listed to UL 9540 as an energy storage system.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source consultant_memo · Claim type study_finding · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-6bdcc9fa85
Opponents' most frequent concern was fire risk from the battery storage yard and volunteer fire department response capacity.
Quoted from page 1 Fire risk from the battery storage yard and the response capacity of the volunteer fire department.
Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · Page 1 · 2023-05-12
Source developer_document · Claim type stakeholder · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-6bf1273c36
The OPSB application must include a fire protection, safety and medical emergency plan developed with local responders.
Quoted from page 1 The OPSB application must include a fire protection, safety and medical emergency plan developed with local responders.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source consultant_memo · Claim type regulatory · Polarity presence · Confidence high · Quote check exact, 100 of 100
C-76f3e4d772
The BESS yard is 150 feet from the nearest property line and 610 feet from the nearest residence (R-6).
Quoted from page 2 The yard is 150 feet from the nearest property line and 610 feet from the nearest residence (R-6).
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28
Source consultant_memo · Claim type study_finding · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-8041623932
No local zoning, conditional use, variance or site plan approval is required, and no local setback, height or screening standard applies to the proposed facility.
Quoted from page 1 No local zoning permit, conditional use permit, variance or site plan approval is therefore required for the proposed facility, and no local setback, height or screening standard applies to it.
Zoning Verification - Tamsin Ridge Solar and Storage Project · DR-0022 · Page 1 · 2023-02-14
Source agency_determination · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-9775cc58ba
There is no internal fire suppression in the enclosures; design relies on containment, spacing, explosion control and defensive firefighting.
Quoted from page 1 There is no internal fire suppression: the enclosure design relies on containment, spacing and explosion control, and on a defensive firefighting approach.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-b6407da087
No large-scale fire test beyond UL 9540A has been performed for this enclosure.
Quoted from page 1 No large-scale fire test beyond UL 9540A has been performed for this enclosure
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source consultant_memo · Claim type absence · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-ce7cc27a08
In the UL 9540A unit-level test, thermal runaway in one module did not spread to adjacent modules and no flaming occurred outside the enclosure.
Quoted from page 1 thermal runaway started in one module did not spread to adjacent modules, no flaming outside the enclosure was observed
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source field_study · Claim type study_finding · Polarity presence · Confidence medium · Quote check exact, 100 of 100
C-d757c50e61
Heat flux modeling of a single fully involved enclosure shows less than 12.6 kW per square meter at the fence and adjacent enclosure rows.
Quoted from page 2 shows less than 12.6 kW per square meter at the fence and at the adjacent enclosure rows
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 2 · 2023-06-28
Source consultant_memo · Claim type study_finding · Polarity absence · Confidence high · Quote check exact, 100 of 100
C-e7f77313ec
Staff will treat the battery system as part of the generating facility.
Quoted from page 1 Staff will treat the battery system as part of the generating facility.
OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · Page 1 · 2023-03-28
Source agency_determination · Claim type agency_position · Polarity neutral · Confidence medium · Quote check exact, 100 of 100
C-e96c5bf196
The governing code edition and whether the local fire code official will require a construction permit for an OPSB-certificated facility have not been confirmed.
Quoted from page 1 The edition that will govern, and whether the local fire code official will require a construction permit for a facility certificated by the OPSB, have not been confirmed.
Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · Page 1 · 2023-06-28
Source consultant_memo · Claim type data_gap · Polarity neutral · Confidence high · Quote check exact, 100 of 100
C-f29a379025
The substation, BESS yard and inverters must not be built over the undermined area.
Quoted from page 2 The substation, the BESS yard and the inverters must not be built over the undermined area.
Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · Page 2 · 2023-05-15
Source consultant_memo · Claim type constraint · Polarity presence · Confidence high · Quote check exact, 100 of 100
3Permits and requirements
The requirements tied to the rows of this report, by level. Each quote from dated law is shown with its source, the version in force on the cut-off and the basis for it.
No requirement is tied to the rows of this report.
4What is missing
The information requests the run raised for the rows of this report, by priority: what is missing, what follows from it, and whether it holds up the decision.
High priority (4)
IR-5947855eaa · High priority
Provide the ul 9540 listing and ul 9540a test reports (cell, module, unit and installation level) for the project area, or confirm none exists.
- Missing evidence
- UL 9540 listing and UL 9540A test reports (cell, module, unit and installation level)
- Consequence
- Battery Storage Fire Safety is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
IR-debe8f99e4 · High priority
Provide the hazard mitigation analysis, fire risk assessment or explosion control study for the project area, or confirm none exists.
- Missing evidence
- Hazard mitigation analysis, fire risk assessment or explosion control study
- Consequence
- Battery Storage Fire Safety is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
IR-03be7e4172 · High priority
Provide the emergency response plan or fire department and fire marshal correspondence for the project area, or confirm none exists.
- Missing evidence
- Emergency response plan or fire department and fire marshal correspondence
- Consequence
- Battery Storage Fire Safety is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
IR-eb247a9fcd · High priority
Provide the bess ordinance, moratorium or fire code adoption record for the project area, or confirm none exists.
- Missing evidence
- BESS ordinance, moratorium or fire code adoption record
- Consequence
- Battery Storage Fire Safety is rated on partial evidence without it.
- Blocks the decision
- No
- Raised by
- completeness
5Next steps and agencies
Next steps
- Confirm governing fire code edition and whether the local fire official requires a permit for the OPSB-certificated facility.
- Meet the volunteer fire department and county EMA early; finalize the emergency response plan and plan on-site water storage.
- Evaluate need for large-scale fire testing.
Agencies
- OPSB
- SFM
- Carroll County
6Basis and limits
This report is a desk review of the documents quoted above, as the engine read them for an information cut-off of 2023-08-01.
It is not a field survey and not a modelled study: this review made no site visit and ran no acoustic, hydraulic or other model. Where the record is silent, the report says what is missing; it does not fill the gap.
Every statement, figure and quote is the engine's record as written. The headings and connecting words are fixed text of this room, the same in every report.
Documents quoted (6)
- Battery Energy Storage System Fire Safety Narrative - Tamsin Ridge · DR-0014 · 2023-06-28 · pages 1, 2
- OPSB Pre-Application Conference Summary - Tamsin Ridge Solar and Storage Project · DR-0026 · 2023-03-28 · page 1
- Standard Flood Hazard Determination - Tamsin Ridge Parcels 5, 9 and 10 · DR-0009 · 2023-03-15 · page 1
- Summary of the County Public Meeting under ORC 303.61 - Tamsin Ridge · DR-0023 · 2023-05-12 · page 1
- Zoning Verification - Tamsin Ridge Solar and Storage Project · DR-0022 · 2023-02-14 · page 1
- Preliminary Geotechnical Engineering Report - Tamsin Ridge Solar and Storage Project · DR-0018 · 2023-05-15 · page 2
Versions and data hashes
As the engine and the exporter recorded them. Hashes are SHA-256.
- Information cut-off
- 2023-08-01
- Engine version
- 2.11.0
- Prompt version
- 2026-11-08.1
- Rows pack
- rows.json sha256 a018ecd7e4703bc1
- Federal pack
- federal.json sha256 8841c555ff35d20b
- State pack
- oh.json sha256 d4780705e1f18d09
- Local pack
- oh_carroll_county.json sha256 905cd3308848e7e8
- Data room manifest
- 0c7e80d0ad17d1e3ed4060b9702e5b1905060ae2896e9aad796a57b590005832
- Audit chain
- valid (19 events)
- QA status
- PASS_WITH_WARNINGS
- Rendered at
- 2026-11-10T15:42:40+00:00
- Run record (annex)
- 66fca2c4c0bfa90df1e8efb79c0d2f426536b41f50a6a9b6869dd85e4554fd50
- Exporter
- Prism/room/exporter 1.4.0
Prism desk report · engine 2.11.0 · prompts 2026-11-08.1 · information cut-off 2023-08-01